Building Inspector of Attleboro v. Attleboro Landfill

423 N.E.2d 1009, 384 Mass. 109, 1981 Mass. LEXIS 1363
CourtMassachusetts Supreme Judicial Court
DecidedJuly 22, 1981
StatusPublished
Cited by28 cases

This text of 423 N.E.2d 1009 (Building Inspector of Attleboro v. Attleboro Landfill) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Inspector of Attleboro v. Attleboro Landfill, 423 N.E.2d 1009, 384 Mass. 109, 1981 Mass. LEXIS 1363 (Mass. 1981).

Opinion

Lynch, J.

The building inspector for the city sought equitable relief and an injunction to bar the defendant from operating a sanitary landfill business on Beckham Street in Attleboro. A judge of the Superior Court entered a judgment which permanently enjoined the defendant from operating its landfill business in contravention of the zoning ordinance of the city. The defendant appealed, and the case was transferred to this court on our own motion. The defendant contends that the permit must be taken to have *110 been granted as a matter of law, since the planning board failed to take final action within the ninety-day period required by G. L. c. 40A, § 9. We agree.

On December 8, 1978, a Superior Court judge determined that the defendant’s landfill was in violation of the city of Attleboro zoning ordinance, rejecting the defendant’s contention that it had a valid nonconforming use. This judgment was stayed for ninety days to allow the defendant to seek relief from the zoning board of appeals, which the defendant failed to do. On March 9, 1979, the stay having expired, the defendant shut down its landfill business. On March 6, 1979, the city amended its zoning ordinance by enacting a landfill permit provision which empowered the city’s planning board to permit sanitary landfill by special permit. The defendant applied for such a permit on July 16, 1979, and a public hearing was held on this application on August 27, 1979. The planning board met and voted to deny the defendant’s application for a special permit on November 19, 1979, and on November 30, 1979, this decision was filed with the city clerk. On December 21, 1979, the defendant resumed operation of its landfill business. Thereafter, the plaintiff commenced this action for injunctive relief, and a permanent injunction issued on March 31, 1980.

The defendant contends that its petition for a special permit was constructively allowed because the planning board failed to take final action on defendant’s petition within the ninety-day period required by G. L. c. 40A, § 9. General Laws c. 40A, § 9, as amended by St. 1977, c. 829, § 3F, provides, in part, that “[fjailure by a special permit granting authority to take final action upon an application for a special permit within . . . ninety days following the date of public hearing shall be deemed to be a grant of the permit applied for” (emphasis supplied). It is, therefore, mandatory that the board act within the statutory period, otherwise the applicant prevails by default. Rinaudo v. Zoning Bd. of Appeals of Plymouth, 383 Mass. 885 (1981). Casasanta v. Zoning Bd. of Appeals of Milford, 377 Mass. 67, 69-70 (1979). There is no question that the action of the *111 planning board denying the defendant’s request for a special permit occurred within the ninety days prescribed by the statute, and that the filing with the city clerk occurred after the ninety-day period had expired. We, therefore, must decide which of these events constitutes final action in regard to an application for a special permit within the meaning of the statute.

At the outset, it is appropriate to observe that the word “final” clearly connotes the last or ultimate. Final action must be, therefore, the last or ultimate act of the planning board in relation to the application for a special permit. See Opinion of the Justices, 300 Mass. 630, 640 (1938). Even though § 9 makes no mention of filing the decision of the permit granting authority with a city clerk, such filing is necessary to limit the period which appeals may be taken. 1 Even though there is no clear exhortium to the permit granting authority to file its decision with the city clerk, such a duty is strongly implied when the statute is read in its entirety and when its requirements are compared with similar statutes. Elsewhere within c. 40A, we find the requirement that the permit granting authority must certify to the successful applicant that its decision has been filed with the city clerk, c. 40A, § 11. 2 Furthermore, unless the board’s *112 decision is filed with the clerk, there would be no commencement of the statutory time within which appeals may be taken. Such an unlimited appeal period is contrary to our appellate practice generally, Mass. R.A.P. 4, as appearing in 378 Mass. 928 (1979), and to the legislative mandate in similar matters, G. L. c. 41, § 81U. To conclude, therefore, that no filing by the permit granting authority with the clerk is mandated flies in the face of reason and logic. Once it is concluded that the permit granting authority must file its decision with the city clerk, it is difficult to conclude that such filing is not the last act required of the board upon the permit application, and thus final action within the meaning of the statute.

Although we have never determined the meaning of the words “final action” under § 9, we have, in an analogous situation, reached a conclusion consistent with our result here. In Selectmen of Pembroke v. R. & P. Realty Corp., 348 Mass. 120, 127 (1964), we construed identical language as it was then contained in G. L. c. 41, § 81U, as requiring, in the case of subdivision control, planning board filing of its certificate of decision with the town clerk, in order for “final action” to be complete. What was said in that case with regard to filing with the town clerk applies here: “The act of filing the certificate with the town clerk is an act that affects the rights of the owner, his grantees, and the public in respect of the plan. Such an act, within usual and well understood meanings of the words used, is action regarding the plan. That act, and the giving of notice to the applicant, are the final acts in any way related to the plan that the planning board must perform under § 81U.

*113 “Sections 81U . . . and 81BB, read together, showed the intention that inaction in respect of a plan within the sixty day period should result in constructive approval and that a person aggrieved by that result should have a right of appeal. Those sections also showed the intention that an interested party should be able to ascertain at the town clerk’s office the action or inaction of the board that had been determinative of his rights. If the ‘final action regarding a plan’ that must be taken within sixty days of submission included the filing of the certificate with the town clerk, the latter’s records were complete and the rights of a person aggrieved were ascertainable at the clerk’s office. On the other hand, if the ‘final action’ that would bar the constructive approval of the plan was a decision of the board made within the sixty day period but not recorded, these different results followed: The town clerk’s records would not show the facts determinative of the right to appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vaillancourt v. Gray Wolf Realty, LLC
29 Mass. L. Rptr. 496 (Massachusetts Superior Court, 2012)
Devine v. Board of Health
845 N.E.2d 444 (Massachusetts Appeals Court, 2006)
Craig v. Planning Board
835 N.E.2d 270 (Massachusetts Appeals Court, 2005)
Cardwell v. Board of Appeals of Woburn
807 N.E.2d 207 (Massachusetts Appeals Court, 2004)
Burnham v. Town of Hadley
790 N.E.2d 1098 (Massachusetts Appeals Court, 2003)
Board of Aldermen v. Maniace
711 N.E.2d 565 (Massachusetts Supreme Judicial Court, 1999)
Board of Aldermen v. Maniace
702 N.E.2d 391 (Massachusetts Appeals Court, 1998)
Uglietta v. City Clerk of Somerville
594 N.E.2d 887 (Massachusetts Appeals Court, 1992)
Tanner v. Board of Appeals
541 N.E.2d 576 (Massachusetts Appeals Court, 1989)
Windsor v. PLANNING BOARD OF WAYLAND
531 N.E.2d 272 (Massachusetts Appeals Court, 1988)
Korkuch v. Planning Board
526 N.E.2d 1301 (Massachusetts Appeals Court, 1988)
Angelus v. Board of Appeals
521 N.E.2d 1373 (Massachusetts Appeals Court, 1988)
Eli & Bessie Cohen Hillel Academy, Inc. v. Director of the Division of Employment Security
484 N.E.2d 1022 (Massachusetts Supreme Judicial Court, 1985)
O'KANE v. Board of Appeals of Hingham
478 N.E.2d 962 (Massachusetts Appeals Court, 1985)
Zuckerman v. Zoning Board of Appeals of Greenfield
477 N.E.2d 132 (Massachusetts Supreme Judicial Court, 1985)
Vokes v. Avery W. Lovell, Inc.
468 N.E.2d 271 (Massachusetts Appeals Court, 1984)
Elder Care Services, Inc. v. Zoning Board of Appeals
459 N.E.2d 832 (Massachusetts Appeals Court, 1984)
Mullin v. Planning Board of Brewster
456 N.E.2d 780 (Massachusetts Appeals Court, 1983)
Capone v. Zoning Board of Appeals of Fitchburg
451 N.E.2d 1141 (Massachusetts Supreme Judicial Court, 1983)
Girard v. Board of Appeals of Easton
439 N.E.2d 308 (Massachusetts Appeals Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
423 N.E.2d 1009, 384 Mass. 109, 1981 Mass. LEXIS 1363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-inspector-of-attleboro-v-attleboro-landfill-mass-1981.