Perretta, J.

A Land Court judge sitting by designation in the Superior Court concluded that the defendants’ application for a special permit and site plan approval had been granted constructively and allowed their motion for summary judgment.2 The ensuing appeal by the board of aldermen of Newton [830]*830(board)3 brings before us the same question as was before the trial court judge, that is: “[W]hether the timely filing of a document which sets forth the action of the [board], including the votes of each member, but giving reasons extraneous to the result of the vote, indeed, even reasons which would apply to a contrary vote, constitutes final action within the meaning of G. L. c. 40A, § 9.” We affirm the judgment.

1. The statute. To put the undisputed facts in perspective, we set out the pertinent provisions of G. L. c. 40A, § 9, tenth and eleventh pars., as inserted by St. 1987, c. 498, § 1:

“Each application for a special permit shall be filed by the petitioner with the city . . . clerk and a copy of said application . . . shall be filed forthwith by the petitioner with the special permit granting authority. The special permit granting authority shall hold a public hearing. . . The decision of the special permit granting authority shall be made within ninety days following the date of such public hearing. The required time limits for a public hearing and said action, may be extended by written agreement ....
“Failure by the special permit granting authority to take final action within said ninety days or extended time, if applicable, shall be deemed to be a grant of the special permit. . . . The special permit granting authority shall cause to be made a detailed record of its proceedings, indicating the vote of each member upon each question, or if absent or failing to vote, indicating such fact, and setting forth clearly the reason for its decision and of its official actions . . . .”

2. The undisputed facts. On December 11, 1995, pursuant to G. L. c. 40A, § 9, the defendants applied to the board for a special permit and site plan approval to construct a Stop & Shop supermarket. The board, through its land use committee (committee), held a public hearing and several working sessions to consider the application. Ultimately, the committee recom[831]*831mended that the board approve the defendants’ request with the conditions which were listed in the committee’s draft decision. After a lengthy debate, the board denied the defendants’ application.4

Although the parties previously had agreed that the time for final action on the application would be extended to September 4,1996, the board filed its decision with the city clerk on August 13. At the time of the board’s vote on the application, it had in its possession a four-page draft order setting out the reasons for a denial of the application. However, the victorious minority withdrew that draft, and the decision filed with the city clerk was an almost verbatim tracking of the committee’s recommendation approving the application with one major difference, namely, the vote of the full board noted at the conclusion of the decision. Put another way, the decision contained no reasons for the board’s denial other than its final vote. The defendants filed a timely notice of appeal from that decision pursuant to G. L. c. 40A, § 17.

Before any action was taken on that pending appeal, the ninety-day time period for final action by the board under § 9 elapsed. The defendants then filed a notice of approval with the city clerk. That notice prompted the board to bring the present action.

3. Discussion. In Building Inspector of Attleboro v. Attleboro Landfill, Inc., 384 Mass. 109, 111-112 (1981), the court made clear that timely “final action” by a board includes the filing of its decision with the city or town clerk within the ninety-day period set out in § 9: “Even though § 9 makes no mention of filing the decision of the permit granting authority with a city clerk, such filing is necessary to limit the period [within] which appeals may be taken. . .. Furthermore, unless the board’s decision is filed with the clerk, there would be no commencement of the statutory time within which appeals may be taken.” As provided in § 9, the failure to take timely “final action” results in a constructive grant of the permit, the purpose of which is “to induce the board to act promptly.” Capone v. Zoning Bd. of Appeals of Fitchburg, 389 Mass. 617, 623 (1983).

[832]*832It is the board’s position that the document that it filed with the city clerk on August 13 was sufficient to satisfy the requirement of timely final action and prevent a constructive grant of the permit. It claims that there is nothing in § 9, eleventh par., that prescribes the contents of the decision filed with the city clerk. We held to the contrary in Shea v. Board of Aldermen of Chicopee, 13 Mass. App. Ct. 1046, 1046-1047 (1982).

Although the Shea opinion does not contain a recital of its underlying facts, the record in that case was included among the materials presented to the trial court judge on the motions for summary judgment in the instant matter. Those materials show that the decision filed with the city clerk consisted only of a copy of the landowner’s application for a special permit with the following notation made thereon by the board: “10/7/80: Lost by a roll call vote of 1 yes, 11 no.”

In affirming the trial judge’s annulment of the board’s decision, we stated: “The plaintiff’s application for a special permit under ... the zoning ordinance is deemed to have been granted by operation of law under G. L. c. 40A, § 9 . . . because the board of aldermen, acting as the special permit granting authority under the ordinance . . . failed to render or file with the city clerk within ninety days of either of the public hearings on the application ... a ‘decision’ of the type contemplated by G. L. C.40A, §§ 11 ... and 17.” Ibid.5

A decision to deny an application for a special permit does not require detailed findings. See Schiffone v. Zoning Bd. of Appeals of Walpole, 28 Mass. App. Ct. 981, 984 (1990). Any permissible reason to deny the application will survive appellate review. “The denial of special permits is within the discretion of the board. MacGibbon v. Board of Appeals of Duxbury, 356 Mass. 635, 638 (1970). Vazza Properties, Inc. v. City Council of Woburn, 1 Mass. App. Ct. 308, 311-312 (1973). In addition, ‘[a] judge reviewing a decision of the board denying a permit does not possess the same discretionary power as does the board, and the decision of the board can only be disturbed “if it is based on a legally untenable ground” ... or is “unreasonable, whimsical, capricious or arbitrary.’ ” Subaru of New England, [833]*833Inc. v. Board of Appeals of Canton, 8 Mass. App. Ct. 483, 486 (1979), quoting from Gulf Oil Corp. v. Board of Appeals of Framingham, 355 Mass. 275, 277-278 (1969).” ACW Realty Mgmt., Inc. v. Planning Bd. of Westfield, 40 Mass. App. Ct. 242, 246 (1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boespflug v. Community Housing Resource, Inc.
24 Mass. L. Rptr. 547 (Massachusetts Superior Court, 2007)
Telecorp Realty, LLC v. Town of Edgartown
81 F. Supp. 2d 257 (D. Massachusetts, 2000)
Board of Aldermen v. Maniace
711 N.E.2d 565 (Massachusetts Supreme Judicial Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
702 N.E.2d 391, 45 Mass. App. Ct. 829, 1998 Mass. App. LEXIS 1257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-aldermen-v-maniace-massappct-1998.