Building Erection Services Co. v. Walton Construction Co.

CourtCourt of Appeals of Kansas
DecidedJuly 20, 2018
Docket117839
StatusUnpublished

This text of Building Erection Services Co. v. Walton Construction Co. (Building Erection Services Co. v. Walton Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Erection Services Co. v. Walton Construction Co., (kanctapp 2018).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 117,839

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

BUILDING ERECTION SERVICES COMPANY, INC., Appellant,

v.

WALTON CONSTRUCTION COMPANY, INC. and AMERICAN HOME ASSURANCE COMPANY, Appellees.

WALTON CONSTRUCTION COMPANY, INC., Appellee,

BUILDING ERECTION SERVICES COMPANY, INC., Appellant.

MEMORANDUM OPINION

Appeal from Johnson District Court; KEVIN P. MORIARTY, judge. Opinion filed July 20, 2018. Reversed.

R. Scott Beeler and Carrie E. Josserand, of Lathrop Gage LLP, of Overland Park, and Kurt S. Brack, of Brown & Ruprecht, of Kansas City, Missouri, for appellant.

Danne W. Webb, of Horn Aylward & Brandy, LLC, of Kansas City, Missouri, for appellee.

Before GARDNER, P.J., PIERRON, J., and WALKER, S.J.

PIERRON, J.: This case concerns problems with the construction of a press box at the University of Kansas (KU) Memorial Stadium almost 20 years ago. It now comes

1 before this court for a third time. On the first appeal, the court held that Building Erection Services Company, Inc. (BESCO), one of the subcontractors on the project, was contractually obligated to indemnify Walton Construction Company, Inc. (Walton), the general contractor and assignee of KU's indemnification rights, for remediation damages, attorney fees, and expenses because BESCO failed to anchor a glass curtain wall system to the press box substructure in accordance with shop drawings. This court reversed the district court's order that BESCO pay all the remediation costs as damages and remanded for the district court's "determination of those damages that arose out of, or resulted from, BESCO's negligent acts or omissions." Building Erection Services Co., Inc. v. Walton Const. Co., Inc., No. 100,906, 2009 WL 4639486, at *6-7 (Kan. App. 2009) (unpublished opinion) (BESCO I).

On remand, the district court conducted a second evidentiary hearing and assessed half the costs of removing the metal wall panels and glass that comprised the press box's curtain wall to BESCO.

On a second appeal, the court held substantial competent evidence did not support an assessment of half the remediation costs to BESCO. The court also reversed the attorney fees award, finding it was not supported by substantial competent evidence. Building Erection Services Co., Inc. v. Walton Const. Co., Inc., No. 111,706, 2015 WL 4879075, at *19-21 (Kan. App. 2015) (unpublished opinion) (BESCO II).

On the second remand, the district reinstated the award assessing half the glass removal costs and increased the award for the metal panel removal costs to 85% with no new evidence from Walton. The district court also reinstated the reversed attorney fees award. BESCO appeals, arguing the district court failed to comply with BESCO II's mandate and substantial competent evidence does not support the third damages award.

2 The press box design included a glass curtain wall with a metal wall panel system to provide support. After completion, the press box was discovered to have two problems: water was infiltrating the curtain wall, and the curtain wall was not properly fastened to the press box's structural steel. These errors have resulted in years of litigation between KU, Walton, and BESCO. The case is now before us on its third appeal.

First Trial

The first trial established the underlying facts, as set forth in BESCO I:

"On June 29, 1998, the University of Kansas (KU) and Walton signed a nearly $13 million construction contract to renovate KU's Memorial Stadium press box. BESCO signed a subcontract with Walton in August 1998 for BESCO to assemble the press box's structural steel, install aluminum door hardware, install glazing of operable windows, and install steel reinforcing of the glass curtain wall. Another of Walton's subcontracts for other work on the project was Cosentino Contracting, Inc. (CCI). "During the first test of the stadium press box on August 6, 1999, considerable water leakage was discovered. On September 29, 1999, Walton wrote CCI stating that the leakage on the east side of the building occurred at 'your' panels and needed to be resolved 'ASAP.' Walton also stated: 'These costs and damage are the responsibility of Cosentino Contracting Inc.' "Because Walton was unable to correct the water leakage problem, KU hired Slemmons Associates Architects, P.A. (Slemmons) in association with Engineering Diagnostics, LLC (ED) to study the problem. The Slemmons report of June 13, 2000, determined that the water leaks in the east elevation curtain wall were due to failed internal window seals, failed seals at metal panel splices, sealant failure of various panel joints, and lack of seals around camera catcher bolt holes. The west elevation curtain wall had failed internal window seals, the subsill flashing did not have functional end dams, and sealant in some joints was not properly applied. ED's report noted that wood screws were not fully engaged with the wood blocking at one window anchor, and 'recommend [ed] that the window manufacturer review the structural adequacy of the wood screws.' There is no evidence in the record on appeal that the window manufacturer was contacted concerning the structural adequacy of the wood screws. 3 "The Slemmons report assigned the responsibility for the water problem and repair cost as follows: KU was 10 percent responsible because of 'the project's compressed time schedule'; the architect was 10 percent responsible 'because their exterior wall system did not incorporate redundant seals that could have reduced the building's weather infiltration problems'; and Walton was 80 percent responsible because of 'failure of internal seals within the widow system; failed seals at metal panel splices; improper sealant installation; lack of seals around camera catcher bolt holes; and lack of end dams at subsill flashing.' "Daniel Miller of BESCO testified that during the August 6 test, the curtain wall did not leak. He stated that the splash plates of the panel system leaked because the windows were not properly sealed internally when they came from the manufacturer, EFCO. EFCO sent technicians to KU to reseal the operable vents. Miller discovered that water was coming in from the 7-inch splashes and draining into the top of the window. In a letter to Mary Ann Elliot at Walton, Miller asked what was 'being done to prevent the water penetration into the top of our systems.' BESCO sent a letter to Walton on October 11, 1999, stating that the 7-inch system was inadequate to meet wind load requirements and was replaced with a 9-inch system, which should have initially been installed. The metal panel system and the J-channel was installed by CCI. "James Modig, KU's director of design construction management and an architect, testified that the project architect, GLPM, and the engineer of record forwarded their concerns about the water leaks to Walton 'with the expectation that they would address that issue.' Walton responded by defending its work, saying: 'We have some issues with the design that was outside of our control. That's why your building may be leaking. "Initially, because of the water infiltration, KU withheld a $422,209 payment to Walton, which included $26,548.54 that Walton still owed BESCO. Because Walton did not receive its payment from KU, Walton did not pay BESCO. "On June 10, 2002, BESCO sued Walton, KU, the State of Kansas, and American Home Assurance Company (American), Walton's bonding company, for breach of contract, claiming that BESCO performed its contract and was entitled to its payment. In turn, each defendant denied liability and asserted cross-claims against the others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cerretti v. Flint Hills Rural Electric Cooperative Ass'n
837 P.2d 330 (Supreme Court of Kansas, 1992)
State v. Collier
952 P.2d 1326 (Supreme Court of Kansas, 1998)
Leffel v. CITY OF MISSION HILLS
270 P.3d 1 (Court of Appeals of Kansas, 2011)
In Re the Marriage of Strieby
255 P.3d 34 (Court of Appeals of Kansas, 2011)
Rose v. via Christi Health System, Inc.
113 P.3d 241 (Supreme Court of Kansas, 2003)
INTELLISPORTS, LLC v. Fitzgerald
204 P.3d 1191 (Court of Appeals of Kansas, 2009)
Building Erection Services Co., Inc. v. Walton Const. Co., Inc.
219 P.3d 1243 (Court of Appeals of Kansas, 2009)
Owen Lumber Co. v. Chartrand
157 P.3d 1109 (Supreme Court of Kansas, 2007)
LSF FRANCHISE REO I, LLC v. Emporia Restaurants, Inc.
152 P.3d 34 (Supreme Court of Kansas, 2007)
Wiles v. American Family Life Assurance Co.
350 P.3d 1071 (Supreme Court of Kansas, 2015)
Peterson v. Ferrell
349 P.3d 1269 (Supreme Court of Kansas, 2015)
Thoroughbred Associates, L.L.C. v. Kansas City Royalty Co., L.L.C.
308 P.3d 1238 (Supreme Court of Kansas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Building Erection Services Co. v. Walton Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-erection-services-co-v-walton-construction-co-kanctapp-2018.