Building & Construction Trades Council of Northern Nevada v. State Ex Rel. Public Works Board

836 P.2d 633, 108 Nev. 605, 1992 Nev. LEXIS 130
CourtNevada Supreme Court
DecidedAugust 20, 1992
Docket21951
StatusPublished
Cited by51 cases

This text of 836 P.2d 633 (Building & Construction Trades Council of Northern Nevada v. State Ex Rel. Public Works Board) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building & Construction Trades Council of Northern Nevada v. State Ex Rel. Public Works Board, 836 P.2d 633, 108 Nev. 605, 1992 Nev. LEXIS 130 (Neb. 1992).

Opinions

[607]*607OPINION

By the Court,

Mowbrary, C. J.:

Respondents solicited and received bids for a construction project at the University of Nevada, Reno campus. After determining that all of the bids exceeded the project budget, respondents notified all bidders that their bids had been rejected and that the project would be redesigned and re-bid. Instead of re-bidding the project, however, respondents negotiated and executed a contract with the construction company that had submitted the lowest bid during the initial bidding. Approximately one month after construction of the project began, appellants petitioned for a writ of mandamus, arguing that respondents had a legal duty to re-bid the project. After a hearing on the return date of the writ, the district court denied appellants’ petition.

On appeal, appellants challenge the district court’s denial of their petition. While we agree with appellants that respondents were required by law to re-bid the project, we also agree with the district court that the doctrine of laches barred issuance of the writ.

THE FACTS

In July and August of 1990, respondent Public Works Board, acting on behalf of respondent Board of Regents, publicly invited construction contractors to bid on a project to restore the Mackay School of Mines Building on the University of Nevada, Reno campus (“the project”). The budget for the project was $6,113,275.00.

Approximately $5,000,000.00 of the proposed construction budget consisted of a federal grant from the Defense Logistics Agency of the Department of Defense. Private sources donated [608]*608the remainder of the funds. No state funds were appropriated for the project.

Respondents received numerous bids for the project. Of these bids, Weyher Brothers Company (“Weyher”) submitted the lowest, at $6,645,000.00. By letter dated September 25, 1990, however, respondents notified all bidders that “[a]ll of the responsive bids received were significantly over the available construction budget,” and that as a result, “this project will be redesigned with a reduced scope of work and re-bid, as soon as possible.”

Despite the letter of September 25, 1990, respondents immediately entered into negotiations with Weyher. Respondents undertook these negotiations because Weyher was the lowest responsible bidder and because Weyher’s original bid for the project was within ten percent of the budget for the project. See NRS 341.145(3)(b). Respondents did not negotiate with any of the other bidders.

As a result of the negotiations, on October 15, 1990, respondents received a revised bid from Weyher. The next day, representatives of respondents met with federal government officials to discuss the project. During this meeting, the federal officials expressed concern that the $5,000,000.00 federal grant might be lost if it was not utilized soon.1 Based upon their concern that the federal funds would be lost if the project were delayed, respondents decided to accept Weyher’s revised bid and not re-bid the project.

In early January 1991, appellant Building Trades Council of Northern Nevada (“the Council”) learned that negotiations between respondents and Weyher had taken place and that respondents intended to award the project contract to Weyher. On January 8, 1991, a representative of the Council telephoned respondents and protested that the project contract had been awarded to Weyher without first re-bidding.

On January 14, 1991, respondents formally executed a project contract with Weyher and notified the other original bidders of the decision to award the project contract to Weyher. On January 15, 1991, Weyher began work on the project. On that same date, the Council learned that Weyher had begun working on the project.

On February 11, 1991, the Council filed a petition for a writ of [609]*609mandamus seeking to force respondents to re-bid the project. After a hearing, the district court entered findings of fact, conclusions of law and a decision denying the petition. The district court concluded that (1) respondents had discretion to negotiate a contract with Weyher instead of re-bidding the project, and (2) even if respondents did not have such discretion, the doctrine of laches barred issuance of the writ. This appeal followed.

DISCUSSION

I.Mandamus.

Appellants contend that respondents had a legal duty to re-bid the project and, therefore, the district court erred in denying appellants’ petition for a writ of mandamus.

A writ of mandamus is available to compel the performance of an act which the law requires as a duty resulting from an office, trust or station. NRS 34.160. Mandamus, however, will not lie to compel an officer or board to perform a discretionary act. Young v. Board of County Comm’rs, 91 Nev. 52, 530 P.2d 1203 (1975). Nor will mandamus lie to control discretionary action, Gragson v. Toco, 90 Nev. 131, 520 P.2d 616 (1974), unless discretion is manifestly abused or is exercised arbitrarily or capriciously. Henderson v. Henderson Auto, 77 Nev. 118, 359 P.2d 743 (1961).

Here, because of the $5,000,000.00 federal grant, the project was a “public work” as defined by NRS 338.010(3)(b). NRS 338.143 and NRS 341.145 specify the procedures that must be followed in bidding a public work. NRS 341.145, the critical section for this appeal, states in relevant part:

The [public works] board:
2. Shall solicit bids for and let all contracts for new construction or major repairs.
3. May negotiate with the lowest responsible bidder on any contract to obtain a revised bid if:
(a) The bid is less than the appropriation made by the legislature for that building project; and
(b) The bid does not exceed the relevant budget item for that building project as established by the board by more than 10 percent.
4. May reject any or all bids.

Appellants argue that although respondents had discretion to [610]*610determine whether or not to undertake the project in the first place, once respondents exercised their discretion by undertaking the project, they became bound by NRS 341.145.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shahrokhi Vs. Dist. Ct. (Burrow)
Nevada Supreme Court, 2021
In Re: Lindblade Family Trust
Nevada Supreme Court, 2020
Turner v. the Eighth Jud. Dist. Ct.
Nevada Supreme Court, 2019
Branch Banking and Trust Co. v. D.M.S.I., LLC
871 F.3d 751 (Ninth Circuit, 2017)
State v. Dist. Ct. Grant (Gregory)
Nevada Supreme Court, 2014
Buckles (James) v. Dist. Ct. (State)
Nevada Supreme Court, 2014
In Re Nj
221 P.3d 1255 (Nevada Supreme Court, 2009)
Dawn M. v. Nevada State Division of Child & Family Services
221 P.3d 1255 (Nevada Supreme Court, 2009)
Moseley v. Eighth Judicial District Court
188 P.3d 1136 (Nevada Supreme Court, 2008)
Miller v. Burk
188 P.3d 1112 (Nevada Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
836 P.2d 633, 108 Nev. 605, 1992 Nev. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-construction-trades-council-of-northern-nevada-v-state-ex-rel-nev-1992.