Buck Town Contractors & Co.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 11, 2018
DocketASBCA No. 60939
StatusPublished

This text of Buck Town Contractors & Co. (Buck Town Contractors & Co.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buck Town Contractors & Co., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Buck Town Contractors & Co. ) ASBCA No. 60939 ) Under Contract No. W912P8-09-D-0052 )

APPEARANCES FOR THE APPELLANT: W. Lee Kohler, Esq. Douglas A. Kewley, Esq. Thomas F. Gardner, Esq. Gardner & Kewley, APLC Metairie, LA

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney William G. Meiners, Esq. Stephen S. Bland, Esq. Engineer Trial Attorneys U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGED' ALESSANDRIS ON APPELLANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT

The United States Army Corps of Engineers (Corps or government) contracted with Buck Town Contractors & Co. (Buck Town) to reconstruct a hurricane protection levee in St. Charles Parish, Louisiana. Buck Town subcontracted the work in question to Circle LLC (Circle). The contract required placement of a layer of geotextile material at the base of the levee, and that the geotextile be provided in continuous machine-direction lengths without seams, with all seams and overlaps to be installed perpendicular to the centerline of the levee. For reasons of efficiency related to the length of the rolls of geotextile material used on the project, every third row of geotextile material on the levee installed by Circle consisted of two strips of material joined by an overlap running parallel to the centerline of the levee. The Corps objected to this method only after one segment of the levee was complete (and the geotextile buried) and another segment had a large part of the geotextile installed. Buck Town was required to remedy this situation by the Corps, leading to the dispute now before us.

Buck Town moves for partial summary judgment on an issue of contract interpretation, seeking a holding that the contract permitted the use of partial rows of geotextile. We deny Buck Town's motion. 1 We find that the plain language of the contract does not permit the use of overlaps parallel to the centerline of the levee. 2

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

On 28 September 2009, the Corps awarded to Buck Town under Multiple Award Task Order Contract No. W9I2P8-09-D-0052 (the contract), Task Order No. 0004, for construction of Reach IA, part of a hurricane protection levee in St. Charles Parish, Louisiana (R4, tab 2). Buck Town subcontracted work, including, geotextile placement, to Circle (Statement of Genuine Issues (SGI) ii 2). The task order for Reach IA required a layer of geotextile material covering an area approximately I20-feet wide by 2,900-feet long (R4, tab 79 at I 890).

The contract's specification for reinforcement geotextile provided, in relevant part:

.3. I . I Procedure

The geotextile shall be installed to the lines and grades as shown on the contract drawings. Objects, or debris that are capable of damaging the geotextile shall be removed before the geotextile is placed. At the time of installation, the geotextile shall be rejected if it has defects, rips, holes, deterioration, or damage which was incurred during manufacture, transportation, or storage. The geotextile shall be installed with the seams facing up to allow for visual inspection. All seams and overlaps shall be placed perpendicular to the centerline of the levee. Fill shall not be placed on the geotextile until the seams or overlaps are within 5 degrees of being perpendicular to the levee centerline and all sags and wrinkles are removed from the geotextile. The Contractor shall take precautions to avoid damaging the geotextile during placement.

1 The present motion concerns only ASBCA No. 60939, which is consolidated with ASBCA Nos. 60940 and 6094 I. Buck Town initially filed a second motion for summary judgment in ASBCA No. 6094 I, regarding a dispute as to whether it was required to replace certain geotextile based upon testing of the fabric's tensile strength. Buck Town withdrew that motion on 2 October 20I 7. 2 The Corps did not cross-move for summary judgment, so we deny Buck Town's motion, but do not enter summary judgment in favor of the Corps. 2 3.3.1 Seams

Geotextile panels shall be sewn along the selvedged edges so that seams run parallel with the machine direction to produce geotextile pieces that are wider than the weaving machine produces. Geotextiles shall be supplied in continuous machine direction lengths without seams. All seams shall be made with thread that meets the requirements for plastic yam, as specified in paragraph GEOTEXTILE REQUIREMENTS. The Contractor is responsible for choosing the sewing machine, thread, stitch type, number of stitches per inch and any other particulars that are required to achieve the seam strength that is specified in Table 1.

3 .3 .1. 1 Damaged Seams

Rips in seams that occur as a result of placement, and which are less than two feet from the end of the geotextile panel do not require repair. Rips that are longer than two feet, or of any length that occur at locations that are more than two feet from the end of the panel, shall be repaired by placing a single layer of geotextile of the same strength to cover the entire affected seam. The piece of geotextile shall extend a minimum of five feet on each side of the damaged seam.

3.3 .2 Overlaps

Overlaps may be used at [points of intersection 3] or to join pieces of geotextile that become too heavy to handle with construction machinery. All overlaps shall run in the same direction as the seams. A minimum of two feet is required at each overlap.

(R4, tab 5 at 110-12) In December 2009, Buck Town submitted to the Corps a geotextile fabric placement plan with a plan view showing overlapping, full length panels installed perpendicular to the centerline of the levee (R4, tab 6).

In January 2010, Circle placed the geotextile material in Reach IA of the levee (R4, tabs 8, 9). Circle used 15' x 300' rolls of geotextile material for the project (R4, tab 11 ). To minimize waste from the 300' rolls of geotextile, Circle typically placed two 120',

3 A point of intersection is where the centerline of the levee changes direction. 3 full-length panels, and one 60', partial-length panel, from each roll. In rows that used two partial-length panels, Circle joined the panels with a 2' overlap. (R4, tab 2 at 20; SGI ,-r 6) To prevent ultraviolet radiation damage, each day Circle would place the first layer of fill over the newly-placed geotextile, covering the overlaps from view (R4, tab 8).

Several representatives of the Corps, including quality assurance inspectors, were on site at various times while Circle placed the geotextile material in Reach IA (R4, tab 8; app. supp. R4, tab 33). Buck Town's quality control reports, submitted to the Corps, included the statement that "2' overlapping was applied at every ?djoining new roll of geotextile" (R4, tab 8; app. supp. R4, tabs 9, 11, 13, 21, 23, 25, 27, 29, 31, 33, 35). The Corps' quality assurance inspectors did not raise any issues with Circle's geotextile placement (R4, tab 9; app. supp. R4, tabs 10, 12, 14, 22, 24, 26, 28, 30, 32, 34, 36). During February and March, 2010, Circle continued to place embankment fill over the geotextile (comp I. ,-i 121, answer ,-i 121). By 24 March 2010, Circle had placed roughly seven feet of embankment fill along the entire levee crest covering the geotextile (app. supp. R4, tab 129).

Under a different task order, Task Order No. 0005, Buck Town and Circle constructed a second reach of the same levee, referred to as Reach 2A (app. supp. R4, tab 5). On I 0 March 2010, during the Reach 2A Geotextile Preparatory Phase Meeting, Buck Town and Circle discussed with Mr. Otho Barnes, P.E., a Corps engineer, that, the "material for two (2) rows will be installed in complete/whole 90' sections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Bannum, Inc. v. United States
121 Fed. Cl. 543 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Buck Town Contractors & Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/buck-town-contractors-co-asbca-2018.