Buck Kreihs Company, Inc. v. The United States

427 F.2d 770, 192 Ct. Cl. 297, 1970 U.S. Ct. Cl. LEXIS 131
CourtUnited States Court of Claims
DecidedJune 12, 1970
Docket240-69
StatusPublished
Cited by11 cases

This text of 427 F.2d 770 (Buck Kreihs Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buck Kreihs Company, Inc. v. The United States, 427 F.2d 770, 192 Ct. Cl. 297, 1970 U.S. Ct. Cl. LEXIS 131 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS MOTION FOR SUMMARY JUDGMENT

NICHOLS, Judge.

Plaintiff, a Louisiana corporation, brings this action to recover certain monies paid to defendant consequent to the application of an allegedly unlawful profit limitations provision in its Government contract. This court’s jurisdiction is said to spring from our Tucker Act authority to render judgments upon any claims against the United States founded upon express or implied contract. 28 U.S.C. § 1491 (1964). As the ensuing opinion will establish, however, the instant Contract is maritime in nature, and therefore cognizable under the exclusive admiralty jurisdiction of the Federal District Courts. 46 U.S.C. § 742 (1964).

On July 30, 1965, plaintiff, Buck Kreihs Company, entered into Master Lump Sum Repair Contract MA-738 with defendant acting through the Director, National Shipping Authority of the Department of Commerce, Maritime Administration (MARAD). By this Contract, plaintiff agreed to repair, alter, convert, and otherwise restore certain vessels of the “Victory” ship classification then laying in “mothballs” in the New Orleans area. Pursuant to MA-738, MARAD issued plaintiff eight job orders for the repair and general restoration of the following vessels:

S/S Hobart Victory Job Order # 4
S/S Oberlin Victory #
S/S Cornell Victory #
S/S San Mateo Victory # 8
S/S Southwestern Victory # 9
S/S Hattiesburg Victory #
S/S Rutgers Victory #
S/S Loma Victory #

Prior to their delivery to plaintiff’s shipyard, these vessels formed part of this nation’s reserve fleet of merchant ships. It is undisputed that MARAD’s purpose for restoring these vessels was to ready them for active sea duty as supply carriers to serve American soldiers in Vietnam.

Plaintiff alleges that all work prescribed by the job orders was completed in calendar year 1966, resulting in a bill to defendant of $1,871,826.50. After paying this amount in full MARAD audited plaintiff’s books and determined that it had received $54,437.96 in excess of allowable profits. Plaintiff was immediately invoiced for this amount and following subsequent negotiations, it was mutually agreed that plaintiff should remit $45,717.01. The remaining $8,720.-95 was left as the basis of a dispute unrelated to this case.

MARAD also sought to audit one of plaintiff’s subcontractors but was refused. Consequently, plaintiff was invoiced an additional $17,382.60 as a penalty for its subcontractor’s refusal.

Plaintiff’s objective in this suit is to recover the sum of the excess profits and penalty assessments.

The substantive issue presented would require us to determine the validity of the Article 41 provision found in Addendum 3 to the Contract which purports to impose certain limits on the profits that plaintiff and its subcontractors may derive from the Contract.

Briefly, plaintiff makes the following arguments on the merits: The Renegotiation Act of 1951, 50 U.S.C. App. § *772 1212(e) (1964) governs profits derived from the instant Contract to the exclusion of the profit limitation provisions found in § 505(b) of the Merchant Marine Act of 1936, 46 U.S.C. § 1155(b) (1964). Defendant attempted to circumvent this statutory exclusion by paraphrasing § 505(b) and incorporating it into the Contract as Article 41. Since § 1212(e) of the Renegotiation Act expressly provides that: “notwithstanding any agreement to the contrary,” § 505(b) of the Merchant Marine Act is inapplicable where a contract is covered by the Renegotiation Act, Addendum 3 (Article 41) is a nullity and the monies collected under its terms should be refunded. Excess profits liability for plaintiff and its subcontractors can only be determined under the provisions of the Renegotiation Act.

Defendant counters with these rebuttals : Article 41 was not added to the Contract pursuant to § 505(b), supra, as evidenced by the nature of the Contract. Plaintiff, under MA-738, was required to repair vessels; § 505(b) is limited to control only those profits derived from new vessel construction contracts or from contracts to repair vessels engaged in charter operations. Article 41 is a valid contract provision. In drafting amendments to the Renegotiation Act, the Senate considered preempting Article 41 provisions along with the profit limitations of § 505(b), but when enacted, the resulting § 1212(e), supra, was silent as to Article 41s, thus impliedly validating their use.

We are unable to reach this issue without overstepping our established jurisdictional boundaries. Our discussion below explains why plaintiff must seek relief elsewhere.

The following fundamental premises provide a good introduction to our jurisdictional problem: Under the Suits in Admiralty Act, 46 U.S.C. § 742 (1964), any cause of action which, if brought against a privately owned vessel or cargo, would compel a proceeding in admiralty, can now be maintained against the United States in personam in an appropriate non-jury proceeding. Such suits “shall be brought in the district court of the United States for the district in which the parties so suing, or any of them, reside or have their principal place of business in the United States, or in which the vessel or cargo charged with liability is found.” (Id.) (Emphasis supplied). Even where such suits are founded upon express or implied contracts made with the United States, they are not cognizable under the Court of Claims’ Tucker Act jurisdiction. New Orleans Stevedoring Co. v. United States, 185 Ct.Cl. 604 (1968), cert. denied, 397 U.S. 1064, 90 S.Ct. 1501, 25 L.Ed.2d 685 (1970); Smith-Johnson Steamship Corp. v. United States, 142 F.Supp. 367, 135 Ct.Cl. 866, cert. denied, 352 U.S. 895, 77 S.Ct. 127, 1 L.Ed.2d 85 (1956). Finally, claims founded upon maritime contracts give rise to admiralty jurisdiction. See e. g., De Lovio v. Boit, 7 F.Cas. 418, 444 (No. 3776) (C.C.D.Mass.1815).

Defendant contends that a contract to repair a vessel is maritime. Alcoa Steamship Co. v. Charles Ferran & Co., 383 F.2d 46 (5th Cir. 1967); see also Flowers v. Travelers Ins. Co., 258 F.2d 220 (5th Cir. 1958). Since the instant Contract was written by MARAD and interpreted by plaintiff to be for vessel repairs, defendant concludes that the Contract is maritime and beyond our jurisdiction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orient Overseas Container Line (UK) Ltd. v. United States
48 Fed. Cl. 284 (Federal Claims, 2000)
Asta Engineering, Inc. v. United States
46 Fed. Cl. 674 (Federal Claims, 2000)
Broward Marine, Inc. v. Bernier
453 So. 2d 868 (District Court of Appeal of Florida, 1984)
Poole & Kent Co.
566 F.2d 1189 (Court of Claims, 1977)
Northwest Marine Iron Works v. United States
493 F.2d 652 (Court of Claims, 1974)
D. F. Fischer & Sons, Ltd.
200 Ct. Cl. 742 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
427 F.2d 770, 192 Ct. Cl. 297, 1970 U.S. Ct. Cl. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buck-kreihs-company-inc-v-the-united-states-cc-1970.