Bryn Mawr Equip. v. Kantor, B.

Superior Court of Pennsylvania·Decided August 31, 2020·No. 2175 EDA 2019·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

BRYN MAWR EQUIPMENT FINANCE : IN THE SUPERIOR COURT OF INC., : PENNSYLVANIA :

Appellee :

:

v. :

:

BRADLEY KANTOR, :

:

Appellant : No. 2175 EDA 2019

Appeal from the Judgment Entered October 22, 2019 in the Court of Common Pleas of Montgomery County Civil Division at No(s): No. 2018-05170

BEFORE: BENDER, P.J.E., LAZARUS, J. and STRASSBURGER, J.* MEMORANDUM BY STRASSBURGER, J.: FILED AUGUST 31, 2020 Appellant Bradley Kantor appeals from the judgment entered October 22, 2019, in favor of Bryn Mawr Equipment Finance, Inc. (BMEF) and against Kantor in the amount of $60,951.84 plus costs, following a bench trial. We affirm.

This case arises from an Equipment Financing Agreement (Agreement)

executed on or about June 7, 2016, between MD Capital Partners, Inc. (MDCP) as creditor, and Mobile Diagnostic Imaging, Inc. (MDI) as debtor,

* Retired Senior Judge assigned to the Superior Court.

with Kantor as personal guarantor of debtor’s obligations. 1 MDCP subsequently assigned the agreement to BMEF.

MDI agreed to make 60 monthly payments of $1,238.09, in addition to other terms. MDI made 16 payments of $1,238.09, but failed to make any payments after December 2, 2017, placing MDI in default under the terms of the Agreement. Due to MDI’s default, BMEF declared all amounts due immediately pursuant to paragraph 12 of the Agreement. Because MDI had ceased operations, BMEF commenced this action against Kantor, as personal guarantor, for monies owed under the Agreement.

Paragraph 12 of the Equipment Finance Agreement provides as follows.

If you do not pay any payment or other sum due to us or other party when due or if you break any of your promises in the Agreement or any other Agreement with us, you will be in default. If any part of a payment is late, you agree to pay a late charge of 15% of the payment which is late or if less, the maximum charge allowed by law. If you are ever in default, we may retain your security deposit and at our option, we can terminate or cancel this Agreement and require that you pay the unpaid balance of this Agreement (discounted at 6%). We may recover interest on any unpaid balance at the rate of 8% per annum. We may also use any of the remedies available to us under Article 2A of the Uniform Commercial Code [(UCC)] as enacted in the State of California or any other law. If we refer this Agreement to an attorney for collection, you agree to pay

1 Although not entirely clear from the record, it appears Kantor was the President of MDI. See N.T., 6/27/2019, at 38, 41, Ex. A. On the same date the Agreement was executed, Kantor signed a personal guaranty of prompt payment and performance of all obligations under the Agreement. Complaint, 3/15/2018, at Ex. A (Guaranty, 6/7/2016).

our reasonable attorney’s fees and actual court costs. If we have to take possession of the Equipment, you agree to pay the cost of repossession. The net proceeds of the sale of any repossessed Equipment will be credited against what you owe us under this Agreement. YOU AGREE THAT WE WILL NOT BE RESPONSIBLE TO PAY YOU ANY CONSEQUENTIAL OR INCIDENTAL DAMAGES FOR ANY DEFAULT BY US UNDER THIS AGREEMENT. You agree that any delay or failure to enforce our rights under this Agreement does not prevent us from enforcing any rights at a later time. It is further agreed that your rights and remedies are governed exclusively by this Agreement and you waive your rights under Article 2A (508-522) of the UCC. If your delinquency requires additional collection efforts, a charge will be assessed in accordance with our collection charge schedule.

Complaint, 3/15/2018, at Ex. A (Equipment Finance Agreement, 6/7/2016, at ¶ 12).

On September 10, 2018, Kantor filed a demand for a jury trial and preliminary objections, to which BMEF filed an answer on September 13, 2018. The trial court overruled Kantor’s preliminary objections on October 26, 2018. Kantor filed an answer with new matter on November 19, 2018, to which BMEF replied on November 21, 2018. A bench trial was held on June 27, 2019.2 The trial court summarized the evidence presented at trial as follows.

2 At the start of trial, the trial court heard argument from counsel for the parties and testimony from Kantor regarding waiver of a jury trial under the Agreement. The court ruled that a jury trial was waived under the Agreement and the matter proceeded as a bench trial. N.T., 6/27/2019, at 3-19.

MDI, and by extension, Kantor, is in default for 44 payments, plus late charges. BMEF’s witness, James Zelinskie,[3], testified that 44 payments remain under the [A]greement. Of the remaining payments, 19 are delinquent, and 25 are future payments that have been reduced by a 6% present value discount as required under the [Agreement]. The remaining 19 delinquent payments of $1,238.09 each total damages of $23,523.71. The remaining 25 future payments discounted at 6% total damages of $29,373.36. Late charges from August 13, 2015 until June 27, 2019 at 10% total damages of $2,104.77.

Attorney’s fees are damages in the amount of $5,950[].

Zelinskie also testified that late charges of 10% have been sought on delinquent payments, although the [Agreement]

authorizes late charges up to 15%. Zelinskie testified that BMEF pays attorney’s fees each month and has not had a reason to dispute the charges or refuse to pay. Zelinskie further testified on cross[-examination] that BMEF has been unable to locate the equipment or [obtain] good contact with Kantor, and as such has been unable to repossess the equipment at issue. Th[e trial court found] the testimony of Zelinskie credible. Kantor testified that the equipment is located in Florida and is available to BMEF.

However, Kantor was unclear on which pieces of equipment were owned by BMEF, and th[e trial court did] not credit this testimony.

Trial Court Opinion, 9/16/2019, at 2-3 (some name designations altered; citations and unnecessary capitalization omitted). At trial, Kantor moved to dismiss, which the trial court denied. N.T., 6/27/2019, at 21, 36-39, 56-58. At the close of trial, the court did not render a decision and took the matter under advisement. N.T., 6/27/2019, at 58.

The next day, June 28, 2019, Kantor filed what he titled a “Supplemental Petition to Dismiss.” On July 2, 2019, the trial court filed its

order and decision, which denied Kantor’s petition and ordered judgment

3 Zelinskie is President of BMEF. N.T., 6/27/2019, at 22.

entered in favor of BMEF and against Kantor in the amount of $60,951.84, plus costs. Judgment was entered on the docket that same date, July 2, 2019. Even though judgment had been entered, the following occurred. BMEF responded to Kantor’s “Supplemental Petition to Dismiss” on July 10, 2019; Kantor filed a “Supplemental Post-trial Motion to Dismiss or Motion for a New Trial” on July 16, 2019; and the trial court denied Kantor’s July 16, 2019 motion the same day, July 16, 2019.

This appeal followed.4 On September 30, 2019, this Court entered an order directing Kantor to show cause as to why this appeal should not be quashed or dismissed for failure to preserve any issues for appellate review. Specifically, the order stated that the trial court docket indicated Kantor had not filed a timely post-trial motion, and no final judgment had been entered. Order, 9/30/2019. Kantor responded on October 8, 2019, asserting that his issues were preserved before, during, and after trial, and that the July 2, 2019 order was a final order. Response, 10/8/2019, at ¶¶ 1-6. Thereafter, on October 16, 2019, this Court entered a second rule to show cause order directing Kantor to praecipe the trial court prothonotary to enter judgment on the decision of the trial court as required by Pa.R.A.P. 301. Order, 10/16/2019; see also Pa.R.C.P. 227.4 (entry of judgment upon praecipe of

Free access — add to your briefcase to read the full text and ask questions with AI

Bryn Mawr Equip. v. Kantor, B., (Pa. Ct. App. 2020).

Bryn Mawr Equip. v. Kantor, B. (Bryn Mawr Equip. v. Kantor, B.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chalkey v. Roush
805 A.2d 491 (Supreme Court of Pennsylvania, 2002)
Commonwealth v. Rodgers
605 A.2d 1228 (Superior Court of Pennsylvania, 1992)
Millard v. Nagle
587 A.2d 10 (Superior Court of Pennsylvania, 1991)
Moore v. Quigley
168 A.2d 334 (Supreme Court of Pennsylvania, 1961)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Commonwealth v. Briggs
12 A.3d 291 (Supreme Court of Pennsylvania, 2011)
Milby, L. v. Pote, C. v. Southern Christrian
189 A.3d 1065 (Superior Court of Pennsylvania, 2018)
Brown, J. v. Halpern, M.
202 A.3d 687 (Superior Court of Pennsylvania, 2019)
Harvey v. Rouse Chamberlin, Ltd.
901 A.2d 523 (Superior Court of Pennsylvania, 2006)
Umbelina v. Adams
34 A.3d 151 (Superior Court of Pennsylvania, 2011)
J.J. DeLuca Co. v. Toll Naval Associates
56 A.3d 402 (Superior Court of Pennsylvania, 2012)
Ferguson v. Morton
84 A.3d 715 (Superior Court of Pennsylvania, 2013)
Centrone v. Tuchinsky
439 A.2d 1226 (Superior Court of Pennsylvania, 1982)
Linde, B. v. Linde, S.
2019 Pa. Super. 305 (Superior Court of Pennsylvania, 2019)