This text of 119 N.E.3d 603 (Bryan Alexander, Karl Cameron, William Love, Charlie Lovins, Kevin McMurray and Matt Oelker, on behalf of themselves and all others similarly situated v. Linkmeyer Development II, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bryan Alexander, Karl Cameron, William Love, Charlie Lovins, Kevin McMurray and Matt Oelker, on behalf of themselves and all others similarly situated v. Linkmeyer Development II, LLC, 119 N.E.3d 603 (Ind. Ct. App. 2019).

Opinion

[1] This case comes before this court as an interlocutory appeal from the parties' respective cross-motions for summary judgment. Specifically, a class of laborers ("the Class") formerly employed by Linkmeyer Development II, LLC, and its members Steve Linkmeyer and Brian Bischoff (collectively, "the Defendants"), appeal the trial court's denial of their motion for summary judgment and the granting, in part, of the Defendants' motion for summary judgment. The Defendants appeal the remaining issues for which their motion for summary judgment was denied. The parties now present several issues for our review which we consolidate and restate as two: (1) whether the trial court erred in denying the parties' motions for summary judgment on the issue of breach of contract, and (2) whether the trial court erred in denying the Defendants' motion for summary judgment regarding the Indiana Wage Payment Statutes. Concluding the trial court did not err, we affirm.

Facts and Procedural History

[2] Around June of 2009, Steve Linkmeyer approached the City of Lawrenceburg requesting a $ 3,000,000 loan to facilitate a development project on behalf of his company, Linkmeyer Development. On November 30, 2009, Linkmeyer, along with another member of Linkmeyer Development, Brian Bishoff, signed a document entitled "Development Agreement Between the City of Lawrenceburg, Indiana, and Linkmeyer Development II, LLC" ("the Development Agreement"). Appellants' Appendix, Volume II at 103. The City of Lawrenceburg's city manager, Tom Steidel, and mayor, William Cunningham, also signed the contract.

[3] The Development Agreement involved three properties: the Ellis property, the Walters property, and the Tanners Creek property. According to its terms, the City of Lawrenceburg would provide a $ 3,000,000 line of credit to Linkmeyer Development in return for the excavation and filling of the properties. Linkmeyer Development was required to purchase the Ellis property and the Walters property. The Lawrenceburg Redevelopment Commission would then convey the Tanners Creek property to Linkmeyer Development, some 21.5 acres of land which ran adjacent to Tanners Creek Drive, free of charge. Dirt was to be moved from the Ellis property to both the Walters property and the Tanners Creek property in order for the properties to be elevated out of the flood plain. In so doing, all three previously-undevelopable properties would become developable. Linkmeyer Development also agreed to petition the City of Lawrenceburg for the annexation of the Ellis property at the completion of the project.

[4] The loan itself was to be paid in three installments, with the first $ 1,000,000 to be paid at the completion of the work on the east side of Tanners Creek, the second $ 1,000,000 to be paid at the completion of the project, and the third $ 1,000,000 to be paid when the Ellis property was successfully annexed. The $ 3,000,000 was loaned for a maximum of five years with an annual interest rate of 2%. Steidel prepared the Development Agreement using a form document that he generally used in connection with loans made by the City of Lawrenceburg.

[5] Under "Section II" entitled "Responsibilities of the Developer" the Development Agreement stated:

The Developer must begin the project on or before August l, 2009 and complete the project by October 1, 2010. Developer shall comply with all appropriate codes, laws and ordinances including the payment of prevailing wages for labor as required by the State of Indiana and the City of Lawrenceburg. The Developer shall provide a final set of engineering plans and a final project construction cost estimate that shall be attached to, and become a part of, this agreement.
* * *
The Developer(s) and their spouses must agree to sign personal guarantees for the amount borrowed as well as provide first mortgages for both the Ellis Properties and any city owned land that is conveyed to the Developer as part of this agreement. In, addition, they must agree to sign any other documents that may be appropriate to ensure that the City investment is secure.

Appellants' App., Vol. II at 46-47. 1

[6] Consistent with the Development Agreement, the parties executed several additional documents, including a Promissory Note and a Mortgage in favor of the City of Lawrenceburg on the Tanners Creek and Ellis properties. Additionally, Bischoff, Linkmeyer, and both of their spouses, executed a personal guaranty. The guaranty stated:

ln consideration of the extension of credit by The City of Lawrenceburg, Indiana ... ("Lender") to Linkmeyer Development ... ("Debtor") and other good and valuable consideration, the receipt of which is acknowledged [by] the undersigned, jointly and severally if more than one, hereby guarantee to Lender the prompt performance and payment of all indebtedness, interest, principal, liabilities and obligations of Debtor to Lender pursuant to Debtor's Note ... in the principal amount of $ 3,000.000.00, Mortgage of Real Property ("Mortgage"); and Development Agreement ("Development Agreement") .... This is a Guaranty of payment and performance, including all collection efforts. Without limiting the foregoing, the undersigned, absolutely, irrevocably and unconditionally indemnifies and saves Lender harmless from and against all liabilities, suits, proceedings, actions, claims, assertions, charges, demands, delays, injuries, expenses (including reasonable attorney fees and disbursements) which are incurred by Lender as a result of any allegation determination or that the Obligations involve a fraudulent conveyance, transfer or obligation under federal or state law.

Id. at 116.

[7] At the completion of the project, Linkmeyer Development made the first few payments on the loan but eventually defaulted. On July 3, 2013, the six individuals now composing the Class, 2 filed a complaint in Dearborn County Circuit Court alleging that a Lawrenceburg City Ordinance was incorporated by the Development Agreement and that the ordinance required the payment of prevailing wages.

Entitled "Contractors Required to Pay Prevailing Wages," Lawrenceburg Code Section 33.02 provides:

On any construction project approved by the Lawrenceburg Development Corporation and financed in whole or in part by proceeds from sale of economic development bonds, grants or approved by or financed through any city agency, board, committee or commission, pursuant to an Investment Incentive Program, contractors retained to complete the project shall be required to pay the employed on the project wages equal to the prevailing wage customarily paid to each class of worker engaged in similar work in Lawrenceburg and surrounding areas.
('94 Code, § 33.02) (Ord. 1-1986, passed 4-7-86).

Pursuant thereto, the Class brought the following claims:

Count I: Breach of Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
119 N.E.3d 603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bryan-alexander-karl-cameron-william-love-charlie-lovins-kevin-mcmurray-indctapp-2019.