Bruce Cope v. Thrasher Construction, Inc.

Mississippi Supreme Court·Decided November 30, 2017·No. 2014-CT-01474-SCT·Published

Opinion

IN THE SUPREME COURT OF MISSISSIPPI NO. 2014-CT-01474-SCT

BRUCE COPE, MARY COPE AND IKE W. THRASH

v. THRASHER CONSTRUCTION, INC.

ON WRIT OF CERTIORARI

DATE OF JUDGMENT: 10/01/2014 TRIAL JUDGE: HON. MICHAEL H. WARD TRIAL COURT ATTORNEYS: TAYLOR B. McNEEL SAMUEL C. KELLY

KAREN E. HOWELL

NICHOLAS VAN WISER

WILLIAM J. LITTLE

COURT FROM WHICH APPEALED: HARRISON COUNTY CIRCUIT COURT ATTORNEY FOR APPELLANTS: NICHOLAS VAN WISER ATTORNEYS FOR APPELLEE: TAYLOR B. McNEEL SAMUEL C. KELLY

KAREN E. HOWELL

NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: THE JUDGMENT OF THE COURT OF APPEALS IS REVERSED; THE

JUDGMENTS OF THE COUNTY COURT AND CIRCUIT COURT OF HARRISON COUNTY ARE REINSTATED AND AFFIRMED - 11/30/2017

MOTION FOR REHEARING FILED: MANDATE ISSUED:

EN BANC.

WALLER, CHIEF JUSTICE, FOR THE COURT:

¶1. Thrasher Construction, Inc. (Thrasher) brought a third-party beneficiary action against Bruce Cope, Mary Cope, and Ike Thrash (the Copes and Thrash) in the County Court of the First Judicial District of Harrison County. Thrasher sought damages for payments owed for waterproofing the Inn by the Sea, a condominium in which the Copes and Thrash had acquired a full ownership interest by agreeing, in part, to pay all outstanding bills for work previously performed on the property. During trial, the county court dismissed the third-party beneficiary claim but allowed Thrasher to proceed on a quantum meruit theory of the case. The jury returned a verdict in favor of Thrasher for $69,290, and the county court entered judgment based on that verdict. The Copes and Thrash appealed the judgment to the Circuit Court of the First Judicial District of Harrison County, which affirmed the judgment of the county court. The Copes and Thrash then appealed to the Court of Appeals, arguing the facts do not support a recovery on quantum meruit. Thrasher cross-appealed, arguing the trial court erred in dismissing its third-party beneficiary claim.

¶2. The Court of Appeals held quantum meruit was not the proper method of relief because the action should have proceeded as a third-party beneficiary claim. The Court of Appeals reversed the judgment and remanded for further proceedings consistent with its opinion. We agree the third-party beneficiary action was the appropriate basis for Thrasher’s recovery; however, because the trial court ultimately reached the correct result, no further proceedings are needed in this case.

FACTS AND PROCEDURAL HISTORY

¶3. The facts of this case required for review on appeal are adequately set out by the Court of Appeals in its majority opinion. Cope v. Thrasher Const., Inc., 2016 WL 3523874, at **1–2 (Miss. Ct. App. June 28, 2016).

Inn by the Sea was destroyed by Hurricane Katrina in 2005. The owners of the individual units engaged SeaInn LLC (SeaInn) to develop a new complex and rebuild. SeaInn consisted of two members, Greg Stewart and Kenny Labelle.

The unit owners conveyed their interest in the property to SeaInn in order to begin the project. SeaInn then hired Madison Homes as its general contractor.

Greg Stewart is the only known representative of Madison Homes.

In February 2009, Madison Homes contracted with Thrasher Construction in order to waterproof Inn by the Sea. Thrasher Construction was to be paid $106,600 for this project. Thrasher Construction worked on the Inn by the Sea project from April to July of 2009. Each month, it sent an invoice to Madison Homes, but none of the invoices were paid. Eventually, upon completion of sixty-five percent of the work on the Inn by the Sea project, Thrasher Construction stopped work due to nonpayment. Thrasher Construction then filed a Notice of Construction Lien against the Inn by the Sea property in September 2009. The amount due at the time that Thrasher Construction stopped work was $69,290, calculated based on the percentage of the project completed.

Ike Thrash later purchased Labelle’s fifty percent interest in SeaInn. He then signed over part of his interest to Bruce Cope and Mary Cope. After realizing that neither Stewart nor Madison Homes was paying the subcontractors, Cope and Thrash entered into a settlement agreement with Stewart to remove him.

Cope and Thrash agreed to take over and complete certain projects. Cope and Thrash agreed to pay the subcontractors on the Inn by the Sea project to the extent that the invoices provided by Stewart were “true, valid[,] and correct.”

Attached to the agreement was a list of unpaid invoices for each project;

Thrasher Construction’s multiple invoices were listed.

Cope and Thrash then began to contact the subcontractors. They requested that the subcontractors come to Inn by the Sea during a specific two-day period to verify the work performed. Upon verification, Cope and Thrash would pay each subcontractor what was owed. Thrash contacted Thrasher Construction approximately four times during this two-day period, but Thrasher Construction did not come to the project to verify its work because of the

existing lien. Cope and Thrash paid every other subcontractor on the Inn by the Sea project. In November 2009, Thrasher Construction withdrew its lien.

Thrasher Construction then filed a lawsuit against Madison Homes as well as Cope and Thrash claiming breach of contract. Specifically, Thrasher Construction alleged breach of contract as a third-party beneficiary against Cope and Thrash based on the settlement agreement.

During trial, after Thrasher Construction’s case-in-chief, the county court dismissed the third-party beneficiary breach-of-contract claim after Cope and Thrash moved for a directed verdict. The court allowed Thrasher Construction to proceed on the theory of quantum meruit. The jury returned a verdict in favor of Thrasher Construction in the amount of $69,290. Cope and Thrash then filed a motion for a judgment notwithstanding the verdict (JNOV), which was denied by the county court. They appealed to the circuit court, which affirmed.

Id. The Copes and Thrash then appealed to this Court, and we assigned the case to the Court of Appeals, where both sides raised the same arguments as before the circuit court.

¶4. The Court of Appeals held Thrasher could not recover under quantum meruit but should have been allowed to proceed on its third-party beneficiary claim. Accordingly, the Court of Appeals reversed and rendered the judgment of the circuit court and reversed and remanded the judgment of the county court. With respect to remand, the Court of Appeals held further proceedings were necessary as to the third-party beneficiary action. Both sides filed petitions for certiorari, which we granted. Before this Court, the Copes and Thrash argue the Court of Appeals correctly reversed the quantum meruit claim but erroneously revived the third-party beneficiary claim. Thrasher argues the Court of Appeals incorrectly reversed the judgment, because under either a quantum meruit or a third-party beneficiary theory, the judgment of the county court should be affirmed.

STANDARD OF REVIEW

¶5. The standards of review for a grant or denial of a directed verdict and judgment notwithstanding the verdict (JNOV) are identical. Coho Res., Inc. v. Chapman, 913 So. 2d 899, 904 (Miss. 2005). We review both “de novo as to the law applied by the trial court judge as well as the evidence presented during trial.” Johnson v. St. Dominics–Jackson Mem’l Hosp., 967 So. 2d 20, 22 (¶ 3) (Miss. 2007). This Court views the evidence in the light most favorable to the verdict, and if substantial evidence supports the verdict, we will affirm the judgment of the trial court. Adcock v. Miss. Transp. Comm’n, 981 So. 2d 942, 948 (¶ 25) (Miss. 2008). “For questions of law, the standard of review is de novo.” O’Neal v. O’Neal, 17 So. 3d 572, 574 (¶ 11) (Miss. 2009) (citations omitted).

DISCUSSION

¶6. The Court of Appeals held Thrasher presented a valid third-party beneficiary claim, which should not have been dismissed on directed verdict. We agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Bruce Cope v. Thrasher Construction, Inc., (Mich. 2017).

Bruce Cope v. Thrasher Construction, Inc. (Bruce Cope v. Thrasher Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Adcock v. MISSISSIPPI TRANSP. COM'N
981 So. 2d 942 (Mississippi Supreme Court, 2008)
Shewbrooks v. AC AND S. INC.
529 So. 2d 557 (Mississippi Supreme Court, 1988)
MISSISSIPPI HIGH SCHOOL ACTIVITIES v. Farris
501 So. 2d 393 (Mississippi Supreme Court, 1987)
SIMMONS HOUSING, INC. v. Shelton
36 So. 3d 1283 (Mississippi Supreme Court, 2010)
O'Neal v. O'Neal
17 So. 3d 572 (Mississippi Supreme Court, 2009)
Burns v. Washington Savings & Great Southern Savings & Loan Ass'n
171 So. 2d 322 (Mississippi Supreme Court, 1965)
Estate of Johnson v. Adkins
513 So. 2d 922 (Mississippi Supreme Court, 1987)
Coho Resources, Inc. v. Chapman
913 So. 2d 899 (Mississippi Supreme Court, 2005)
Patel v. Telerent Leasing Corp.
574 So. 2d 3 (Mississippi Supreme Court, 1990)
Johnson v. ST. DOMINICS-JACKSON MEM. HOSP.
967 So. 2d 20 (Mississippi Supreme Court, 2007)
Falco Lime, Inc. v. Mayor & Aldermen of City of Vicksburg
836 So. 2d 711 (Mississippi Supreme Court, 2002)
Crystal Finnie v. Lee County Board of Supervisors
186 So. 3d 831 (Mississippi Supreme Court, 2016)
Yazoo M.V.R. Co. v. Sideboard
133 So. 669 (Mississippi Supreme Court, 1931)
North American Midway Entertainment, LLC v. Tommy W. Murray
200 So. 3d 437 (Mississippi Supreme Court, 2016)