Brubaker v. East Hempfield Township

234 F. App'x 32
CourtCourt of Appeals for the Third Circuit
DecidedApril 27, 2007
Docket06-2531
StatusUnpublished
Cited by1 cases

This text of 234 F. App'x 32 (Brubaker v. East Hempfield Township) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brubaker v. East Hempfield Township, 234 F. App'x 32 (3d Cir. 2007).

Opinion

OPINION OF THE COURT

SMITH, Circuit Judge.

This appeal from the District Court’s grant of summary judgment poses the question of whether a property owner may recover under the takings clause or as the result of a substantive due process violation by a township for deprivation of his reasonably expected economic use of his property during a two-year period. Preliminary to that examination, however, is the question of whether this case is ripe for review. We hold that it is not.

I.

Brubaker owns a parcel of land in East Hempfield Township. In 2000 and 2001, he sought to construct a 250 feet tall communication tower on his property, and consulted with the Township Zoning Officer and Director of Planning toward that end. The Zoning Officer determined that the tower would be an accessory use to Bru-baker’s principal use of the property and mentioned to Brubaker that he would probably be contacted by companies about collocation of their antennas on the tower. Brubaker did not personally review the Township Zoning Ordinance before applying for the building permit.

Section 207 of the East Hempfield Zoning Ordinance provides the regulations for structures within “Community Commercial Zones.” The permitted uses in this zone include “[pjublic uses and public utilities structures,” and “[ajccessory uses customarily incidental to the ... permitted uses.” § 207.2(8) and (10). Special exception uses include “[cjommunication antennas mounted on an existing public utility transmission tower, building, or other structure, including existing communications towers and communications equipment buildings.” § 207.3(13). The maximum permitted height for structures in this zone is 35 feet. § 207.9.

On May 29, 2001, Brubaker received a building permit to construct the communications tower. It is uncontested that the Township erroneously granted this permit. The tower was completed on July 16, 2001, and on August 17, 2001, Brubaker entered into a lease agreement with Nextel Partners, Inc. for collocation of Nextel antennas on the tower at a rate of $l,500/mo. for 25 years. Nextel applied to the Zoning Hearing Board for a special exception for the collocation, and the Hearing Board approved its application on September 17, 2001. 1 Brubaker then applied to the Township for a Certificate of Occupancy, but was informed that there were problems with the tower.

*34 On September 19, 2001, the Board of Supervisors revoked Brubaker’s building permit. 2 The Township asserted that the antennas were not compliant because the tower and antennas were not an accessory use to the property, and that the tower did not comply with the set back requirement of § 304.1, which allows antennas and “other similar structures” an exclusion from the height regulations so long as they are set back a horizontal distance at least equal to their height from the property line. On October 3, 2001, the Township brought an equity action in the Lancaster County Court of Common Pleas, seeking an injunction and an order of removal or relocation of the tower. The Court of Common Pleas entered a decree nisi in the equity action on May 23, 2002, finding that Brubaker had a vested right in the building permit, but that the right was defeasi-ble if the Township found that there was a public danger that required the tower’s removal or relocation, and paid for it.

At a July 17, 2002 meeting, the Township determined that the tower presented a great public danger and stated that it would “exercise its rights” under the Court of Common Pleas’ decree nisi. Nextel terminated its lease and withdrew its application for a special exception. Brubaker filed an appeal from the Court of Common Pleas, and the Commonwealth Court reversed, concluding that Brubaker had an indefeasible right to the tower at the location specified in the original building permit.

Brubaker also filed suit under §§ 1983 and 1985 in federal district court claiming violations of the Fifth Amendment and Fourteenth Amendment. The Court granted the Township summary judgment on March 31, 2006, holding that the takings claim was not ripe and that it failed on the merits, the substantive due process claim failed because the defendants’ actions did not shock the conscience, and the § 1983 claim failed because the plaintiff could not prove a Fifth or Fourteenth Amendment violation.

II.

We have plenary review of the order granting the defendants’ motion for summary judgment. Carter v. McGrady, 292 F.3d 152, 157 (3d Cir.2002). We also exercise plenary review over the District Court’s ripeness decision. Felmeister v. Office of Attorney Ethics, 856 F.2d 529, 535 n. 8 (3d Cir.1988).

The District Court had jurisdiction pursuant to 28 U.S.C. §§ 1331 and 1343. We have jurisdiction pursuant to 28 U.S.C. § 1291.

III.

The initial question is whether Brubaker’s claim is ripe for review. In order to survive a ripeness challenge, Brubaker must show that the Township made a “final decision” with respect to the manner in which it will enforce its regulations. See Williamson County Regional Planning Comm’n v. Hamilton Bank, 473 U.S. 172, 191, 105 S.Ct. 3108, 87 L.Ed.2d 126 (1985) (requiring a “final, definitive position regarding how it will apply the regulations at issue to the particular land in question” from the administrative agency before the case is ripe for review). The ripeness inquiry has a “twofold aspect, requiring us to evaluate both the fitness of *35 the issues for judicial decision and the hardship to the parties of withholding court consideration.” Abbott Labs. v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967); Surrick v. Killion, 449 F.3d 520 (3d Cir.2006). Neither aspect is met by Brubaker. The Township’s revocation of the building permit did not answer the question of how the Township intended to implement its decree—i.e., whether it would require removal of the structure or relocation. Brubaker has not demonstrated any hardship in delayed judicial consideration and cannot do so because the property is currently being used as contemplated without interference from the Township. 3

The Township’s revocation of Brubaker’s building permit on September 19, 2001 interfered with Brubaker’s vested property interest. At the July 17, 2002 Township Board of Supervisors meeting, the Board voted to exercise its “rights” under the May 23 decree nisi of the Common Pleas Court. This vote had the potential to further interfere with Brubaker’s property rights.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
234 F. App'x 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brubaker-v-east-hempfield-township-ca3-2007.