Browne v. R. & R. ENGINEERING CO.

164 F. Supp. 315, 1 Fed. R. Serv. 2d 199, 1958 U.S. Dist. LEXIS 3808
CourtDistrict Court, D. Delaware
DecidedJuly 21, 1958
DocketCiv. A. 1873
StatusPublished
Cited by10 cases

This text of 164 F. Supp. 315 (Browne v. R. & R. ENGINEERING CO.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Browne v. R. & R. ENGINEERING CO., 164 F. Supp. 315, 1 Fed. R. Serv. 2d 199, 1958 U.S. Dist. LEXIS 3808 (D. Del. 1958).

Opinion

LAYTON, District Judge.

Jurisdiction here is based upon diversity of citizenship.

I find the following facts: Plaintiff, a registered engineer of eighteen years experience, is employed by Catalytic Construction Co. in Philadelphia. He is experienced in bidding on government contracts. Through his work at Catalytic, he learned that certain sub-contracts were about to be let through Swinerton & Walbert Co. for the Atomic Energy Commission which a small machine shop might hope successfully to bid on and complete. He had a friend named Weber, an engineer, who in conjunction with a partner, DuHadoway, operated a very small machine shop near Wilmington, known as R. & R. Engineering Co. This shop had but three regular employes, the two partners and one other workman. With one or two exceptions, R. & R. had never had a contract for work in excess of $1,000. Plaintiff told Weber about the subcontracts in question and after some discussion the partners indicated a desire to bid upon them. However, R. & R. was not on the bidders’ list and, moreover, Weber had no knowledge as to how to prepare bids upon government proposals. Accordingly, it was preliminarily agreed that plaintiff would attempt to get R. & R. placed upon the bidders’ list, make a number of essential engineering drawings and assist Weber in preparing estimates or bids in return for which plaintiff would be paid $1,000 for the drawings and either be made a partner or paid a percentage of the gross amount of any contract if and when obtained. From about February 24 to March, 19, 1956, plaintiff and Weber worked every night and week end (altogether about 300 hours) in preparing the bids. Plaintiff, meantime, succeeded in getting R. & R.’s name on the bidders’ list. Their bid on the first contract in the sum of $1,300,000 was too high. Almost immediately, another contract came up and plaintiff and Weber busied themselves in preparing estimates; which were successful. This contract turned into a series of contracts amounting to $284,783 of work. R. & R. immediately had to obtain new capital to-enlarge its facilities and purchase materials in order to perform the contract. Plaintiff spent some time trying to raise capital for Weber but was unsuccessful. Finally, Weber raised the necessary funds. During the intense pressure of work in preparing bids, etc., the question of plaintiff’s compensation had been forced into the background. Now he began to press for a binding agreement. Weber was uncooperative. On April 23,. 1956, R. & R. was incorporated. Meanwhile, R. & R. gradually increased its payroll from three to twenty-seven employes, and Weber and DuHadoway not only doubled their salaries but also caused themselves to be paid large bonuses at the year’s end. Plaintiff seeing himself slowly being frozen out of the situation, renewed his demands and on one or more occasions became angry at Weber’s refusal to enter into what he thought was a fair agreement. Finally, Weber told plaintiff to submit a bill. The bill came to $14,500, or 5% of the gross amount of the contract price. Weber refused to pay this and sent a check for $5,600, of which $1,000 represented the stipulated price for the drawings. Plaintiff received this payment under protest and filed suit for $14,500.

*317 I find that a figure of between 7%% and 10% of the gross contract price would normally represent fair compensation in this locality to a person who not only found the opportunity but, in addition, performed multiple services similar to those rendered by plaintiff in this case. However, while the plaintiff, in submitting a bill for $14,500, was not bound by that amount after Weber refused payment, nevertheless, this bill must be regarded as some evidence of what plaintiff regarded as fair compensation. Under all the circumstances, I find 7%% of the gross contract price to be fair compensation for plaintiff’s work. This sum includes the $1,000 agreed on for the drawings.

Neither the plaintiff nor the defendants had ever heard of Executive Order No. 9001 (hereinafter referred to) 1 and at no time did the plaintiff do any improper act in attempting to procure contracts for the defendants. In fact, all bids were on a competitive basis.

The correct disposition of this case calls for the answer to two questions, (1) should the defendants be permitted to amend their pleadings during trial in order to raise the defense of illegality, and (2) does the public policy of the United States as reflected by Executive Order No. 9001 defeat the plaintiff’s claim ?

Rule 8(c) F.R.C.P., 28 U.S.C.A., requires that all affirmative defenses be specially pleaded. 2 The defense of illegality was not raised in either the defendants’ original or amended answers. On the last day of the trial, the defendants sought leave to introduce Executive Order No. 9001 into the record, thereby for the first time raising the defense of illegality. At my suggestion, the defendants then moved to amend their answers in accordance with Rule 8(c) F.R. C.P. I reserved a ruling on this motion. Inasmuch as the defense raises a matter of law requiring the taking of no further-evidence, and since the plaintiff was-given ample opportunity to file a brief in opposition, no prejudice resulted. Moreover, to deny the motion might result in defeating the national public policy. Compare Oscanyan v. Winchester Repeating Arms Co., 103 U.S. 261 (267),. 26 L.Ed. 539. Accordingly, I think it. better to decide the policy question on the merits. The motion to amend is-granted.

Long before the promulgation of Executive Order No. 9001, the Supreme-Court had taken occasion to condemn as-contrary to public policy the entering into of agreements calling for fees contingent upon the obtaining of government contracts, favorable legislation and' the like. Oscanyan v. Winchester Repeating Arms Co., supra. Hazelton v. Sheckells, 202 U.S. 71, 26 S.Ct. 567, 50 L.Ed. 939; Tool Co. v. Norris, 2 Wall. 45, 69 U.S. 45, 17 L.Ed. 868. In the. latter opinion, Justice Field took occasion to remark:

“It [public policy] has been asserted in cases relating to agreements for compensation to procure legislation. These have been uniformly declared invalid, and the decisions have not turned upon the-questions, whether improper influences were contemplated or used, but upon the corrupting tendency of the agreements.”

*318 Contrary to this view, at least one federal court, before the promulgation of Executive Order No. 9001, refused to strike down a similar contract upon the ground that nothing sinister or improper appeared to have been done in the obtaining of the government contracts. Coyne v. Superior Incinerator Co., 2 Cir., 80 F.2d 844. And a substantial number of state courts have adopted this less exacting yardstick, 3 but as far as my research discloses, no federal court has so held since Executive Order No. 9001 was promulgated. Moreover, the Executive Order establishes a federal public policy having the force of law, Givens v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.E.L. Maduro (Florida), Inc. v. M/V Santa Lucia
116 F.R.D. 289 (D. Massachusetts, 1987)
Overseas Motors, Inc. v. Import Motors Limited, Inc.
375 F. Supp. 499 (E.D. Michigan, 1974)
Deakyne v. Commissioners of Lewes
416 F.2d 290 (Third Circuit, 1969)
Wolff v. Calla
288 F. Supp. 891 (E.D. Pennsylvania, 1968)
United States v. Webber
396 F.2d 381 (Third Circuit, 1968)
United States v. Webber
270 F. Supp. 286 (D. Delaware, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
164 F. Supp. 315, 1 Fed. R. Serv. 2d 199, 1958 U.S. Dist. LEXIS 3808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/browne-v-r-r-engineering-co-ded-1958.