Brown v. United States

51 Ct. Cl. 22, 1915 U.S. Ct. Cl. LEXIS 13, 1915 WL 1078
CourtUnited States Court of Claims
DecidedDecember 6, 1915
DocketNo. 29,949
StatusPublished

This text of 51 Ct. Cl. 22 (Brown v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. United States, 51 Ct. Cl. 22, 1915 U.S. Ct. Cl. LEXIS 13, 1915 WL 1078 (cc 1915).

Opinion

Barnet, Judge,

reviewing the facts found to be established, delivered the opinion of the court:

On the 18th of May, 1898, the plaintiff entered into a contract with the Government to manufacture for the use of the Ordnance Department of the Army 50 segmental, tube wire-bound rapid-fire guns, of which the claimant, Brown, was the inventor, together with Navy rapid-fire gun mounts for the same. Twenty-five of these guns were to be of 5-inch and 25 of 6-inch caliber. The twenty-five 5-inch guns were to be paid for at $9,175 each, and the twenty-five 6-inch guns at $10,950 each, making a total contract price of $503,125.

The contract was subsequently annulled by the Government before any of the guns had been delivered. This suit is brought to recover the sum of $140,502.95, the amount alleged to have been expended toward the performance of the contract before its annulment. Of this sum $42,578.18 is [29]*29alleged to have been expended by the plaintiff, and the remainder by the Diamond Drill & Machine Co., the subcontractor at whose works the guns were to be manufactured for the fulfillment of the contract.

None of the guns ever having been delivered under this contract, as before stated, the question for decision in this case is whether the contract was ever legally annulled by the Government.

The contract provided that a sample gun of both calibers should be furnished by the plaintiffs and submitted to test, and that the acceptance of the guns by the Government would depend upon such test proving satisfactory. The clauses of the contract relating to this subject are as follows:

“ The first gun manufactured will be fired with full service charges of powder, such as that used in testing other rapid-fire guns of similar caliber, and with not more than the regular service pressures for endurance, and the gun must be fired for endurance 300 rounds or less as rapidly as practicable at the proving grounds of the manufacturers, commencing as soon as the gun is completed and continue firing as the department may require, 5 rounds to be fired with pressures of about 45,000 pounds, and shall not exceed 50,000 pounds, these to be included in but at close of the test, and the acceptance of the remainder of the same caliber will depend upon the type gun passing its test satisfactorily.,
“ The first gun made of the other caliber to be tested at the same place and passed upon in the same manner, without any unnecessary delay, and the acceptance of the remainder of the same caliber will depend upon the type gun passing its test satisfactorily.
“ Both gun and carriage must endure these tests in all- respects satisfactorily, both as to the strength of material and facility of operation.
í{; í{í «{•»{• íjí íj»
“ The work must pass the required inspection at all stages of its progress, and shall be inspected and passed upon at all times without any unnecessary delay, and be approved by the officers of the Ordnance Department before being accepted and paid for by the United States.”

The first complete gun with mount, etc., was to be deliv: ered for test within three months from the date of the contract, but several delays had been granted by the Government, so that the first gun was not tested till March 8, 1899. [30]*30The test was made under the inspection of Capt. Ira MaeNutt, of the Ordnance Office, on proving grounds provided by said Diamond Drill & Machine Co., near the company’s plant at Birdsboro, Pa. It is considered unnecessary to state here in detail just what occurred during this test, and it is only necessary to say that the findings show that while the gun passed some of the requirements satisfactorily, in others it did not. The breech bushing and jacket of the gun were cracked, the diameter of the gun fluctuated, there being both increases and decreases, changes in the cross-section of the bore from a round to an elliptical form, and other defects were disclosed as shown particularly in the findings.

These features disclosed by the test created an apprehension on the part of the ordnance officers of danger of rupture, and the Chief of Ordnance and the Secretary of War refused to accept the gun unless it was subjected to and would satisfactorily pass a further test of 100 rounds. In October, 1899, the claimants had a conversation with Maj. Smith, who had immediate charge of matters under this contract, in which he informed them that the gun appeared to have passed the test, and that they could go on with the completion of the contract. Shortly after the plaintiffs wrote the Chief of Ordnance, informing him of this conversation and requesting an official letter to the same effect. No response was made to this request. November 9, 1899. the Chief of Ordnance submitted to the Secretary of War the report of Capt. MacNutt on the test of the gun with an official indorsement thereon, stating in substance that while the gun apparently had met the contract requirements certain defects had developed during the test which should be remedied before acceptance, and suggesting that the gun be submitted to 100 additional rounds, and that the guns be modified so as to remedy these and any further defects which might be developed in these additional firings. This indorsement was approved by the Secretary of War November 30, 1899, and, pursuant thereto, on February 6, 1900, the plaintiffs were notified of this action. On February 9, 1900, the claimants wrote the Secretary of War asking that further action in the premises be suspended until they could be [31]*31heard, and stating that they had not assented to any modifications of the gun and objecting to the further test recommended, as above stated.

On May 16, 1899, while the construction of the type gun was in progress the plaintiffs had been requested by the Chief of Ordnance to present to him some mathematical calculations in reference to the qualities of the gun. Nothing was done in the matter by the plaintiffs until after the receipt by them of the above notification of February 6, 1900; but on February 17, 1900, they wrote the Chief of Ordnance, apparently in response to the above request, requesting the selection of a board to make the calculations requested, naming two members themselves and suggesting the name of Maj. Ingalls, of the War Department, as the third member of the board. The War Department acceded to this request, and Maj. Ingalls was assigned to said duty. The said board was practically a year in making their investigations, at the close of which they'made their report to the claimants, but not until after the annulment of the contract, as hereinafter stated. This report was, on the whole, favorable to the gun, but material defects were pointed out and modifications suggested.

On January 11, 1901, the Chief of Ordnance returned Capt. MacNutt’s report on the test of the gun to the Secretary of War with an indorsement recommending that his office be authorized to declare the claimants’ contract null and void because of the claimants having failed “ to comply with the requirements of the Secretary of War and in further accordance with the provisions of the contract.” This recommendation was approved by the Secretary of War, and the contract was annulled. The claimants appealed from this decision to the Secretary of War, but he refused to revoke this annulment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fechteler v. Whittemore
91 N.E. 155 (Massachusetts Supreme Judicial Court, 1910)
Electric Lighting Co. of Mobile v. Elder Bros.
115 Ala. 138 (Supreme Court of Alabama, 1896)
Greenberg v. Lumb
129 N.Y.S. 182 (Appellate Terms of the Supreme Court of New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
51 Ct. Cl. 22, 1915 U.S. Ct. Cl. LEXIS 13, 1915 WL 1078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-united-states-cc-1915.