Brown v. Forrester Construction Co.

125 N.W.2d 315, 372 Mich. 204, 1963 Mich. LEXIS 278
Michigan Supreme Court·Decided December 27, 1963·No. Calendar 94, 95, Docket 48,004, 48,005·Published·Cited by 6 cases

Opinions

Smith, J.

Plaintiff heating company entered into a subcontract with defendant, April 28, 1952, to furnish plumbing and heating according to specifications in a contract 761, between defendant and the department of army. The heating company also entered into another subcontract with defendant, July 2,1952, for excavating and trenching according to specifications in a contract 884 between defendant and the army. Plaintiff heating company instituted suit in assumpsit for $29,407.40. It claimed, among other things, that during the course of work, defendant “requested and ordered plaintiffs to do certain extra and additional work which was not provided” in the written contract, including labor and materials and especially certain “additional unnecessary overtime” which the heating company allegedly paid its employees. Defendant answered admitting owing plaintiff heating company $3,747.54, balance under contract 884, and denying all other liability. Somewhat later, defendant filed an amended answer claiming set-off and recoupment in the amount of $30,000. Therein, it was alleged that defendant was required to pay additional sums because of delays occasioned [208] by plaintiff beating company. Upon its motion, the indemnity company was permitted to intervene as a party plaintiff. It had previously become surety to the heating company on a performance bond in 'connection with contract 761. Prior to suit, “a part ■of the claim” of the heating company as to contract 761 had been assigned to the indemnity company. A verdict was rendered in favor of plaintiffs for $4,696.54, on contract 884, and $21,188.83, on contract 761. Defendant appeals from an order denying new trial.

] After claim of appeal was filed October 10, 1958, defendant experienced difficulty in securing a transcript of testimony from a court reporter who took testimony for 3 days of the trial which lasted approximately 2 weeks. The reporter obviously was unable to transcribe his notes without assistance, despite the encouragement of a contempt citation. Finally, he did transcribe with assistance and a separate motion for new trial made in this Court and referred to the trial court was denied by the trial court May 22, 1961. The trial court ruled “the court having been advised by counsel for plaintiffs and defendant that the transcript * * * has been completed, certified and filed with the * * * clerk * * * motion * * * is denied.”*

Defendant contends that the verdict was against the great weight of evidence and contrary to law. Defendant says the verdict was contrary to law because there was a misjoinder, of parties-plaintiff and of causes of action; and because the trial judge erred in that the “interpretation of the contract was left to the jury.”.

[209] Defendant argnes also that the tardy transcript,coming from a “stenographer, not an officer of the court” and “uncertified” should he grounds for a new trial. It also argued that the verdict by the jury disallowing defendant’s claim by way of set-off and recoupment is contrary to the great weight of evidence. Finally, it is urged that in the event judgment against defendant is affirmed, interest on the judgment should not run from date of entry because delay in obtaining the transcript was not the fault of defendant but of the court reporter.

■Defendant’s contention of misjoinder of parties and causes is untenable. The real reason for uniting the parties and causes in this lawsuit is because the “convenient administration of justice,” based upon sufficient grounds, is best served. Alles v. Polk Manor Co., 339 Mich 509; CL 1948, § 608.1 (Stat Ann § 27.591). In the instant case, Hartford and the heating company are joint owners of the cause of' action under contract 761, Hartford-being assigneeof part of the heating company’s claim against defendant. Both 761 and 884 involve nearly contemporaneous work on the same project location. Parties to the original contracts are the same. Proofs as to alleged oral agreements for extras are made and contested by approximately the same witnesses in each instance. In Gilmer v. Miller, 319 Mich 136, the dismissal of 2 counts on the grounds of misjoinder. was reversed, this Court holding that while such dismissal might have been warranted under common law, the language of the statute is broad and goes far beyond the previous practice. The action was originally instituted in assumpsit for moneys had and received by a real-estate broker who had allegedly breached his fiduciary duty by nondisclosure of self-interest. The problem arose-upon the assignment of- the land contract upon which the broker’s commission was based. In reversing [210] the trial court’s dismissal of the action by the assignee this Court held at pp 143, 144:

“While each case of this nature must be determined largely on its own facts (Torrent v. Hamilton, 95 Mich 159), we think that the ends of justice in the case at bar will properly be served by permitting the plaintiffs to proceed to trial on the declaration as filed. It does not appear that defendant will in any way be thereby prejudiced. In fact, it would seem to be to his advantage to have the issues involved tried in 1 proceeding rather than in 2 or 3 separate suits. # * * The rights of the parties may and should be determined in a single action. The facts clearly indicate that the ‘convenient administration of justice’ will thereby be promoted.”

Defendant further contends that the trial court erred by allowing contracts 761 and 884 to be interpreted by the jury rather than the court. Plaintiffs’ position is most nearly summed up in the opening statement of plaintiffs’ attorney. He said: “The big argument is whether Johnson and Brown are entitled to this money as extras or whether under their contract they were supposed to do all this work.” It is necessary to examine each item separately to settle this question.

Regarding contract 884, defendant concedes that the contract was fully performed and acknowledges owing a balance of $3,747.54, contending nonpayment was due to outstanding claims of plaintiffs’ creditors. Defendant denies liability for an additional amount of $949 claimed for graveling a parking lot. Neither party claims that graveling of the lot was included in contract 884, however, there exists a conflict as to why it was done. The testimony of plaintiff Brown indicates that the parking area was graveled by order of Hamilton who was acting project engineer at the time, and also by order of McKay, de[211] fendant’s construction .superintendent' on'' the joh. This was denied by defendant. Obviously, the trial court properly submitted to the jury this dispute as to whether or not there was an oral agreement for extra work. 6 MLP, Contracts, § 193, p 438. See, also, Wenzel v. Kieruj, 168 Mich 92.

Free access — add to your briefcase to read the full text and ask questions with AI

Brown v. Forrester Construction Co., 125 N.W.2d 315, 372 Mich. 204, 1963 Mich. LEXIS 278 (Mich. 1963).

125 N.W.2d 315 (Brown v. Forrester Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Turner Associates, Inc. v. Small Parts, Inc.
59 F. Supp. 2d 674 (E.D. Michigan, 1999)
People v. Rowan
255 N.W.2d 791 (Michigan Court of Appeals, 1977)
People v. Drake
236 N.W.2d 537 (Michigan Court of Appeals, 1975)
Fredal v. Forster
156 N.W.2d 606 (Michigan Court of Appeals, 1967)
Brown v. Forrester Construction Co.
125 N.W.2d 315 (Michigan Supreme Court, 1963)