Brown v. Federal Surety Co.

8 P.2d 647, 91 Mont. 389, 1932 Mont. LEXIS 41
CourtMontana Supreme Court
DecidedFebruary 8, 1932
DocketNo. 6,866.
StatusPublished
Cited by2 cases

This text of 8 P.2d 647 (Brown v. Federal Surety Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Federal Surety Co., 8 P.2d 647, 91 Mont. 389, 1932 Mont. LEXIS 41 (Mo. 1932).

Opinion

MR. CHIEF JUSTICE CALLAWAY

delivered the opinion of the court.

This is an appeal from a judgment entered upon a verdict directed in favor of defendant.

It appears that Lalonde, Peck and Powers, in September, 1924, entered into a contract with the state highway commission to construct what is known as the Babb-Cardston road in Glacier county, Federal Aid Project No. 208-A. In October, 1924, the contractor entered into a subcontract with C. H. Windsor, whereby the latter agreed to furnish all materials, tools,, machinery and equipment and to do and perform all of the work and labor provided for in the contract between the contractors and the state. On October 27, 1924, as security for the performance of the subcontract, Windsor and the Federal Surety Company, hereafter called the defendant, gave a bond to the contractors. In making application for the bond, Windsor, called the principal therein, gave to the defendant, called the company, a statement of his financial condition, in which he valued the equipment at $38,000. The application contained this provision:

“That for the better protection of the said Company, and as of the date hereof, the said Principal does hereby assign, transfer and convey to the said Company, all right, title and interest in and to all the tools, plant equipment and materials of every nature and description that said Principal may now or hereafter have upon said work, or in or about the site thereof, including as well materials purchased for or chargeable to said contract, which might be in process of construction, or storage elsewhere, or in transportation to said site, hereby assigning and conveying also all rights in and to all subcontracts, which have been, or may hereafter be entered into and the materials embraced therein, and authorizing and empowering said Company, its authorized agents or attorneys, to enter upon and take possession of such tools, plant equip *392 ment, materials and subcontracts, and enforce, use and enjoy such possession upon the following conditions, viz.: This assignment shall be in full force and effect as of the date hereof, should the said Principal fail, or be unable to complete the said work in accordance with the terms of the contract covered by said bond, or in the event of any default on the part of the said Principal under the terms of said contract.”

The bond provided that in case of default by Windsor “the surety shall have the right, at its option, after receipt of such statement, to proceed with, or procure others to proceed with, the performance of such contract and shall thereupon immediately be subrogated to all the rights of the Principal and of the obligee.”

The subcontractor provided that in case of default by Windsor the obligee “shall have the right to enter upon the premises and take possession thereof and complete the work included under this contract, including the furnishing of materials, and for that purpose shall have the right to make use of any materials, tools, equipment and appliances of the party of the second part then upon the ground, and may employ any other person or persons to complete the said work and to provide the materials therefor.”

At this time Windsor was working upon the incomplete “Birch Creek” project as a subcontractor. When Windsor stopped work in the fall of 1924 he left his equipment at Browning or near by in charge of his foreman, Milliken. Of this more later. Windsor returned in the spring of 1925 and continued work on the Birch Creek project, until the last of April, when he proceeded to the Babb-Cardston project, taking the equipment with him and using the same until November, 1925, when he was unable to proceed for lack of money. Plaintiff claims Windsor used the equipment during 1925 upon a rental basis. Defendant took possession of the equipment in November, 1925, and used the same during the year 1926 in completing the Babb-Cardston project. The defendant, upon the completion of the Babb-Cardston project hauled the equipment to Browning and stored it there, laying no further claim thereto. The record does not indicate that *393 plaintiff has sought in any way to reclaim the property thus stored.

In 1929 the plaintiff began this action against the defendant for the sum of $10,165, as rental for the use of the equipment. He alleged that at the special instance and request of the defendant he had furnished to the defendant certain equipment which was used by “the said D. A. Crichton and Company for the crushing of large quantities of gravel used in such construction work and distribution upon the construction work, gravel, steel and construction materials of various kinds, and other materials in connection with the work, in that he furnished for use in the construction a caterpillar, tractors, trucks, and the like; also camp buildings mounted on wagon trucks, including cooking and sleeping outfit for fifty men, all of which equipment was used in the construction work by the defendant, and that the reasonable value of the machinery, trucks, tractors and other equipment and personal property so made by. the defendant was at the time the same was so used, and still is, of the value of $10,165; that the plaintiff is still the owner and holder of the claims arising from the furnishing and use of the equipment and other personal property hereinabove described by said Federal Surety Company, and that the said sums so due as aforesaid are still due to plaintiff, and that no part thereof has been paid.”

Except as to admitting formal matters alleged in the complaint, that the defendant gave the bond, and that the defendant took over and completed the construction work under the contract and bond, the answer is a general denial of the allegations of the complaint.

To make out his ease plaintiff testified that he became the owner of the property described in the complaint, hereafter referred to as the equipment, in virtue of a bill of sale dated January 27, 1925, wherein Windsor appears as vendor and plaintiff and one Korthoff as vendees. This document purported to convey the equipment for a consideration of $15,000. Plaintiff contends that this sum was a credit allowed Windsor upon an indebtedness of $22,000 owed him by Windsor. When the purported bill of sale came into plaintiff’s possession is *394 not clear. It appears that he sent it to Mr. McDonald of Browning in March, 1925, with instructions to file it with the county clerk. Plaintiff said he bought Korthoff’s interest in the equipment within two or three weeks.

Plaintiff had been the financial backer of Windsor in South Dakota and upon the Birch Creek project. He had kept books for Windsor on the Birch Creek project in 1924, and had assisted him otherwise considerably, taking care to apprise the people generally that he was Windsor’s employee, not his partner. Plaintiff says Windsor was indebted to him for $22,000 in December, 1924, and the two had discussed a sale of the property by Windsor to plaintiff.

In late January, 1925, plaintiff went from Minneapolis to Browning where he found the equipment in charge of Milliken. At that time some of the machinery was stored in Browning while other was along the highway. Plaintiff, so he testified, brought in all that he could through the snow, stored it in a kind of a garage in Browning, and set mechanics to work repairing it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reagan v. Armstrong
165 P.2d 1004 (Montana Supreme Court, 1946)
Claypool v. Malta Standard Garage
30 P.2d 89 (Montana Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
8 P.2d 647, 91 Mont. 389, 1932 Mont. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-federal-surety-co-mont-1932.