Brown-Crummer Investment Co. v. City of Arkansas City

266 P. 60, 125 Kan. 768, 1928 Kan. LEXIS 443
Supreme Court of Kansas·Decided April 7, 1928·No. No. 28,019·Published·Cited by 5 cases

Opinions

The opinion of the court was delivered by

Johnston, C. J.:

The Brown-Crummer Investment Company sued Arkansas City to recover $18,878.51, as damages for its failure to deliver certain bonds of the city in compliance with an alleged agreement. The cause was submitted on pleadings, opening state[770] ments and admissions made in open court. It was adjudged by the court that the plaintiff was not entitled to recover on its claim, and gave judgment against it for the costs of the action. Plaintiff appeals. /

The record discloses that Arkansas City created a sewer district designated as sewer district number six and advertised for bids for the sewer’s construction. A bid made by C. H. Everett was accepted, and on July 1,1921, a contract was entered into between the city and Everett, that he would construct the sewer at stipulated price for work actually done, the total price of which was later found to be $116,232. Among other things the contract provided that at the end of each month the engineer would make an estimate of the material delivered and work done, which would show the amount due to the contractor under the estimate. It was provided also that a final estimate should be made on the completion of the improvement giving the total contract price for the work done. When a maintenance bond was given and receipts for material were shown, or in lieu of them a list of unpaid bills should be produced, and when the contract was completed and the work had passed a city test, the contractor, Everett, should be paid the total of the final estimate or as much as remained due after deducting the .total of all unpaid bills. As to payment under the contract it was provided that “payment shall be made in bonds with accrued interest or cash at the option of the city.” Everett arranged with plaintiff to finance the project. By their arrangement the plaintiff was to advance money to meet the bills for labor and material as the work progressed, upon notes to be given by Everett drawing interest at eight per cent-per annum, he to assign to plaintiff the estimates given by the city as security for the payment of the notes.

On September 15, 1921, the plaintiff proposed to Everett that he should assign all his rights to purchase sewer bonds on the condition that they would amount to approximately $115,000, bearing interest at the rate of six per cent per annum, and that they should be delivered to plaintiff at par value and accrued interest to date of payment, and that if not delivered to plaintiff by January 15, 1922, plaintiff should have the benefit of accrued interest from that date to the date of payment. Plaintiff also proposed to cash and carry the estimates to be delivered to Everett in part payment of the improvement, these to be assigned to plaintiff with proper recogni[771] tion by the city, Everett to affix thereunto his personal notes bearing eight per cent per annum interest for money advanced by plaintiff' from time to time, it being understood that the amount of advancements should be approximately $50,000. On September 19, 1921, the first estimate was made for $23,433.37, and Everett made an assignment of it and of the bonds due or to become due to him from the city to plaintiff. The city through its board of commissioners accepted notice of the assignment on that date, and agreed to deliver bonds to the plaintiff as soon as the same are legally deliverable under its contract with Everett. On October 10, 1921, a second estimate was made amounting to $36,497.90, which was likewise assigned to plaintiff, and notice of the assignment was accepted by the city, and it agreed to deliver bonds in payment of the estimate in terms similar to that made on the first estimate. On January 3, 1922, a further assignment was made by Everett to plaintiff of all bonds issued to pay for the improvement. The assignment was recognized by the city, and it agreed to deliver all bonds covered by the assignment, subject, however, to the full performance of all the agreements on the part of Everett in his contract with the city for the construction of the sewer. The same day the city adopted the following resolution:

“Whereas, The city of Arkansas City, Kan,, has entered into a contract with C. H. Everett for the construction of sewer improvements in sewer district No. 6 of said city; and
“Whereas, The city of Arkansas City has agreed to deliver to said C. H. Everett its negotiable, bonds for the payment of such wotIc; and
“Whereas, Said C. H. Everett has made an assignment of all his right, title and interest in and to said bonds to the Brown-Crummer Investment Company, of Wichita, Kan.:
“Now, therefore, be it resolved by the board of commissioners of Arkansas City, Kan/., That said city shall pay said C. H. Everett, the contractor, in bonds, for all work in sewer improvement district No. 6, and that it accepts the terms of said assignment and agrees to deliver the bonds to be issued in full payment of such work, to the Brown-Crummer Investment Company of Wichita, Kan., as soon as the same can legally be issued, subject to the full performance of the terms and conditions in the contract for said sewer improvements entered into between said Everett and city of Arkansas City, and all. the terms and conditions of said assignment and indorsements thereon.”

The plaintiff alleged that relying on the resolution quoted and the agreement of the city to deliver the bonds, it advanced to Everett the further sum of $35,000. Later, and on January 23,1922, when the sewer was completed, 'the city claimed that it still had the [772] option to determine whether it should pay for the improvement in money or bonds, and it claimed to have exercised its option to pay in money and declined to deliver bonds to the plaintiff as recited in the resolution. On February 16, 1922, the city passed an ordinance purporting to repeal the resolution passed on January 3,1922, and later it issued and sold the bonds to another bond dealer, bearing interest at the rate of five and one-half per cent per annum, and out of the proceeds it paid to the plaintiff $116,372.27, the contract price of the improvement; but the payments were received upon an express agreement that the plaintiff’s right to damages for the failure to deliver the bonds mentioned should not be prejudiced by the acceptance of the cash payment. The plaintiff procured the printing of blank bonds at a cost of $110, and this sum was included in its claim for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Brown-Crummer Investment Co. v. City of Arkansas City, 266 P. 60, 125 Kan. 768, 1928 Kan. LEXIS 443 (kan 1928).

266 P. 60 (Brown-Crummer Investment Co. v. City of Arkansas City) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jayhawk Racing Properties v. City of Topeka
Supreme Court of Kansas, 2021
Jayhawk Racing Props., LLC v. City of Topeka
432 P.3d 678 (Court of Appeals of Kansas, 2018)
Maxine Devlin Moore v. John C. Jones
215 F.2d 719 (Tenth Circuit, 1954)
Shelley v. Sentinel Life Insurance
69 P.2d 737 (Supreme Court of Kansas, 1937)
Marsh v. Brown-Crummer Investment Co.
23 P.2d 465 (Supreme Court of Kansas, 1933)