Broughton Lumber Co. v. United States

30 Fed. Cl. 239, 1994 U.S. Claims LEXIS 6, 1994 WL 6871
CourtUnited States Court of Federal Claims
DecidedJanuary 12, 1994
DocketNo. 91-1402 L
StatusPublished
Cited by3 cases

This text of 30 Fed. Cl. 239 (Broughton Lumber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Broughton Lumber Co. v. United States, 30 Fed. Cl. 239, 1994 U.S. Claims LEXIS 6, 1994 WL 6871 (uscfc 1994).

Opinion

OPINION

WIESE, Judge.

This is a suit to recover just compensation under the Fifth Amendment for the claimed taking, by federal legislation, of the alleged right to apply a state-granted water right to the generation of hydroelectric power for commercial purposes.

Defendant has moved for summary judgment on the ground that plaintiffs planned change in use is subject to numerous state and federal licensing determinations, none of whose requirements have yet been satisfied and all of whose outcomes are uncertain. Thus, defendant maintains that the property interest purportedly taken — an expectation of deriving significant economic value from the water right through its application to a hydroelectric power generator — is at this point too conjectural a usage to qualify as a compensable interest.

Plaintiff opposes defendant’s motion and cross-moves for partial summary judgment in its favor. Oral argument was heard on December 7,1993. We conclude that, in light of the significant obstacles posed by preexisting federal and state regulations, plaintiff possessed no compensable expectancy in the use of its water right for hydroelectric generation. Accordingly, we find no basis upon which to support the claimed taking.

Background

Plaintiff is a logging company that holds a right to appropriate 30 cubic feet per second (efs) of water from the Little White Salmon River for diversion into a flume used in the transportation of rough-cut timber from a sawmill to a down-river planing site. Having decided that the flume was outdated and no longer worth the cost of maintenance, plaintiff discontinued its operation in December of 1986. It was plaintiffs intent to seek licensing approval to convert the water right to what it believed was the only remaining viable economic use: the generation of hydroelectric power.

With that purpose in mind, on July 1,1986, plaintiff filed an application with the Federal Energy Regulatory Commission (FERC), requesting a preliminary permit for a small hydroelectric project.1 This permit was issued on February 10, 1987.

Approximately four months earlier, however, in November of 1987, Congress and the states of Oregon and Washington had passed legislation, known as the Columbia River Gorge National Scenic Area Act (Gorge Act), 16 U.S.C. §§ 544-544p (1988); Or.Rev.Stat. §§ 196.150-.165 (1991); Wash.Rev.Code §§ 43.97.015- 035 (1992), which sought to protect and preserve the Columbia River Gorge against unrestricted industrial devel[241]*241opment.2 It was this Act, or more specifically, the Final Interim Guidelines issued under its authority, which caused the Forest Service — the administering agency — to write plaintiff on November 23,1987, to advise that production of hydroelectric power for commercial purposes in the National Scenic Area represented an “industrial land use” within the meaning of the Final Interim Guidelines.3 “Therefore,” the letter stated, “the Brough-ton hydro-electric project would be an inconsistent land use in the Columbia River Gorge National Scenic Area.”

On the basis of this communication from the Forest Service, plaintiff took no further action in pursuit of a FERC license; the preliminary permit lay idle. Two years later, on November 2, 1989, plaintiff informed FERC that it was surrendering its preliminary permit on the ground that the “this project ... is prohibited by current law and thus the feasibility studies under the existing permit are futile.” Plaintiffs letter to FERC went on to declare that it would pursue litigation against the United States to redress “an unconstitutional taking of a valuable property right as a result of the Columbia Gorge legislation and its implementing regulations.”

Discussion

Plaintiff contends that, at the time the Gorge Act became law, it possessed a reasonable investment-backed expectancy in the use of its water right for the purpose of hydroelectric power generation. The passage of the Gorge Act, plaintiff argues, deprived it of this expectancy and made further efforts to acquire the necessary permits and approvals futile. Thus, plaintiff seeks compensation for its loss.

Plaintiffs argument rests upon the premise that but for passage of the Gorge Act, Broughton would have been able to use its water right for hydroelectric generation. This is a large assumption — one that we cannot endorse. We explain below.

The FERC License Application Process

As has been noted, plaintiffs attempt to obtain FERC approval began and ended at a very early stage of the process — the preliminary permit stage. Thus, one can only speculate as to what would have occurred if, in the absence of the Gorge Act, plaintiff had continued its pursuit of a FERC license. In this connection, we would note at the start that very few of those who enter into the FERC licensing process emerge from the other end with a license to build. At a 1991 congressional hearing, a FERC official testified that “the great majority of project proposals do not ripen into license applications. Of the approximately 150 preliminary permits issued each year to study hydropower development, only about 15 percent — some 23 permits — become license applications.” National Energy Strategy: Hearings on Hy-dropower and Oil Production Regulation Before the Subcomm. on Energy and Power of the House Comm, on Energy and Commerce, 102d Cong., 1st Sess. 512 (1991) [hereinafter Hearings ] (statement of Cynthia A. Marlette, Associate General Counsel, FERC).

Moreover, for the small number of projects that do advance to the license application stage, FERC may not issue a license without weighing “the purposes of energy conservation, the protection, mitigation of damage to, and enhancement of, fish and wildlife (including related spawning grounds and habitat), [242]*242the protection of recreational opportunities, and the preservation of other aspects of environmental quality.” 16 U.S.C. § 797(e) (1988). In recent years, only 7% of applications have led to actual construction. See Hearings at 556 (statement of Wayne L. Rogers, National Hydropower Ass’n) (citing FERC statistics for the period 1980-1990).

It is also important to note here that, even though plaintiffs plans never proceeded beyond the preliminary permit stage, serious concerns were voiced as soon as those plans became known. In 1986, FERC had issued a public notice acknowledging receipt of Broughton’s preliminary permit application. This notice caught the attention of those interested in the welfare of fish populations and the protection of fish hatcheries located on the river. The Washington Department of Fisheries, the Washington Department of Game, and a conservation group called the Friends of the Columbia Gorge each filed a motion to intervene in the FERC process.

In addition, the regional office of the Department of Interior sent a letter to FERC detailing Fish and Wildlife Service concerns.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SDDS, Inc. v. State
1997 SD 114 (South Dakota Supreme Court, 1997)
Avenal v. United States
33 Fed. Cl. 778 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
30 Fed. Cl. 239, 1994 U.S. Claims LEXIS 6, 1994 WL 6871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/broughton-lumber-co-v-united-states-uscfc-1994.