Brothers Building Co. of Nantucket v. Yankow

779 N.E.2d 991, 56 Mass. App. Ct. 688
CourtMassachusetts Appeals Court
DecidedDecember 11, 2002
DocketNo. 01-P-526
StatusPublished
Cited by4 cases

This text of 779 N.E.2d 991 (Brothers Building Co. of Nantucket v. Yankow) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brothers Building Co. of Nantucket v. Yankow, 779 N.E.2d 991, 56 Mass. App. Ct. 688 (Mass. Ct. App. 2002).

Opinion

Mason, J.

The plaintiffs, Brothers Building Co. of Nantucket, Inc. (Brothers Nantucket), and Brothers Building Co., Inc. (Brothers Vermont), brought this action pursuant to G. L. c. 251, §§ 12 and 13, to vacate or modify an arbitration award. The award found the plaintiffs jointly liable to the defendants, Keith and Robin Yankow, for damages in the amount of $49,900 that the Yankows had suffered as a result of the plaintiffs’ failure to perform certain renovation work in accordance with an agreement between Brothers Nantucket and the Yankows. A Superior Court judge (motion judge) denied the plaintiffs’ motion to vacate or modify the award and allowed a motion by the Yankows to confirm the award. Following a subsequent bench trial, a different Superior Court judge (trial judge) dismissed various counterclaims and a third-party complaint that the Yankows had brought.

On appeal, the plaintiffs claim that the motion judge erred in confirming the arbitrator’s award because, among other things, it imposed liability on Brothers Vermont even though it was not a party to the agreement. The Yankows also appeal, claiming that the trial judge erred in dismissing their counterclaims and third-party complaint.

We conclude that the arbitrator was without authority to impose liability on the nonparty, Brothers Vermont. We therefore vacate the judgment confirming the award and direct that a new judgment shall be entered confirming the award only to the extent that it imposes liability on Brothers Nantucket. We affirm the judgment dismissing the Yankows’ counterclaims and third-party complaint.

Background. We summarize the facts as found by the motion judge and by the trial judge, supplemented by uncontroverted testimony and other materials in the record.

The Yankows own and operate an inn known as the Cobblestone Inn in Nantucket, where they also reside. On January 7, 1997, the Yankows entered into a standard form agreement (agreement)3 with Brothers Nantucket for the performance of certain renovations to the inn. The agreement listed Brothers [690]*690Nantucket as the contractor and was signed by David Brookes on behalf of Brothers Nantucket. Section 4.5.1 of the general conditions to the agreement provided that any “controversy or [c]laim arising out of or related to the [agreement], or the breach thereof” would be submitted to binding arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (AAA).

At the time the parties entered into the agreement, Brothers Nantucket was a Massachusetts corporation having its usual place of business in Nantucket. Brothers Vermont was a Vermont Corporation with its usual place of business in Waitsfield, Vermont. Brothers Vermont had formed Brothers Nantucket in August, 1996, in order to compete for local Nantucket building contracts and to employ local Nantucket workers. Richard C. Brothers was president of both Brothers Nantucket and Brothers Vermont.

A dispute arose with respect to the work performed at the inn and payment for that work. Accordingly, on November 12, 1997, Brothers Nantucket filed a demand for arbitration with the AAA, claiming unpaid bills in the amount of $78,414. On December 12, 1997, the Yankows filed an answer and counterclaim for $49,900 which denied that the Yankows owed Brothers Nantucket any money and further stated that:

“Respondent in counterclaim (Brothers Building Co.) substantially breached the contract in many ways, including but not limited to failing to comply with many of its terms and failing to deliver substantial completion in a timely fashion. Respondent in counterclaim also committed many acts that constitute unfair or deceptive acts or practices within the purview of [G. L. c.] 93A.”

On December 15, 1997, counsel for Brothers Nantucket sent a reply to the AAA, denying that it was liable on the counterclaim. In an accompanying cover letter, counsel also asserted that the counterclaim had been directed not against Brothers Nantucket, the claimant in the action, but rather against Brothers Vermont, an entity that was not a party to the proceeding and, hence, should be dismissed. More specifically, counsel stated:

[691]*691“It appears that Respondent’s Counterclaim is directed against only Brothers Building Co., Inc., an entity not a party to this proceeding. As Brothers Building Co., Inc., of Waitsfield, Vermont has not filed a claim against Respondents, no ‘counterclaim’ can be filed against it. If I am incorrect, please notify me immediately.”

The AAA did not respond to this letter, but did schedule the matter for hearing. At the hearing, counsel for Brothers Nantucket, consistent with his prior letter, made a motion to dismiss the counterclaim on the ground that it had been asserted only against Brothers Vermont. The arbitrator did not allow this motion but proceeded to hold four days of hearings with respect to the claim and counterclaim. He also conducted a site inspection. Thereafter, on April 8, 1998, the arbitrator issued an award finding that Brothers Nantucket was not entitled to recover anything on its claim against the Yankows and, further, that both Brothers Nantucket and Brothers Vermont were liable to the Yankows on their counterclaim for failure to perform or complete work in accordance with the agreement. More specifically, the arbitrator found:

“Testimony given by [Brothers Building Co. of Nantucket, Inc.,] and by Brothers Building Co. of Waitsfield, Vermont, Inc., indicate both companies were responsible for supervision of the project, supplying the labor force, office duties, and sharing of profits. Therefore, I find that Brothers Building Co. of Nantucket, Inc.[,] and Brothers Building Co. of Waitsfield, Vermont, Inc.[,] are jointly liable for claims made by the Respondent.”

The arbitrator awarded the Yankows $12,000 for “Costs due to late completion,” $15,000 for “Cost[s] to complete [the project],” and $22,900 for “Repairs due to substandard work including code violation.” The arbitrator made no mention of the G. L. c. 93A claim and stated that: “This award is in full settlement of all claims and/or counterclaims submitted to this arbitration.”

After this award was made, the plaintiffs commenced the instant lawsuit pursuant to G. L. c. 251, §§ 12 and 13, to vacate or modify the award on the grounds that the arbitrator had [692]*692exceeded his authority in imposing liability on Brothers Vermont and also in including in his award an amount for purported code violations. The Yankows filed an answer and counterclaims as well as a third-party complaint against Richard C. Brothers (Brothers). The Yankows alleged in their counterclaims and third-party complaint that the plaintiffs had breached their duty of good faith and fair dealing and had also violated G. L. c. 93A in asserting a “separate corporate identity” defense in the arbitration proceeding and in subsequently commencing the instant proceeding to vacate or modify the arbitration award; further, the Yankows alleged that Brothers was personally liable for these actions. After the plaintiffs had filed a motion to vacate or modify the award and the Yankows had filed a cross motion to confirm the award, a Superior Court judge caused a judgment to enter on June 1, 1999, confirming the award in its entirety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bedard v. Brewer Financial Services, LLC
30 Mass. L. Rptr. 315 (Massachusetts Superior Court, 2012)
Constantino v. Frechette
897 N.E.2d 1262 (Massachusetts Appeals Court, 2008)
Town of Hull v. Massachusetts Commission Against Discrimination
893 N.E.2d 66 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
779 N.E.2d 991, 56 Mass. App. Ct. 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brothers-building-co-of-nantucket-v-yankow-massappct-2002.