Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction

Court of Appeals of Texas·Decided March 13, 2008·No. 02-07-00002-CV·Published

Opinion

COURT OF APPEALS

SECOND DISTRICT OF TEXAS

FORT WORTH

NO. 2-07-002-CV

BROCK INDEPENDENT SCHOOL APPELLANT DISTRICT V.

TONY BRIONES D/B/A WEST TEXAS APPELLEES CONCRETE AND METAL BUILDINGS, SAMUEL TREVINO D/B/A SAM’S CONSTRUCTION ------------

FROM THE 415TH DISTRICT COURT OF PARKER COUNTY ------------

MEMORANDUM OPINION 1

------------

I. INTRODUCTION

Appellant Brock Independent School District (“BISD”) sued Appellees Tony Briones d/b/a West Texas Concrete and Metal Buildings (“Briones”) and Samuel Trevino d/b/a Sam’s Construction (“Trevino”) (collectively “Appellees”)

1 See T EX. R. A PP. P. 47.4.

for damages resulting from Appellees’ installation of a roof in connection with a school construction project. A jury awarded BISD $519,771.00. In five issues, BISD argues that the trial court erred by submitting two instructions, that the jury’s negligence apportionment finding and “No” answer to the contract-compliance question are against the great weight and preponderance of the evidence, and that the evidence is factually insufficient to support the jury’s damages finding. We will affirm.

II. F ACTUAL AND P ROCEDURAL B ACKGROUND BISD sought to build a new elementary and middle school in late 2001.

It hired D.S.A., Inc. as a construction manager to assist with the bidding process and oversee the project. BISD hired Stuckey Architects, Inc. as the architect. Stuckey prepared a project manual for BISD setting forth the general and supplemental conditions and specifications for the project and instructions for placing bids on the project. BISD ultimately awarded each phase of the project to a different subcontractor, who contracted directly with BISD, the owner, as a trade contractor.

Burton Sandefur, a project manager for DSA, knew Briones from previous jobs and contacted him about the BISD project. Briones, who performs concrete and metal building construction, subsequently signed a contract with BISD in March 2002 to furnish equipment and labor to erect “all pre-engineered

metal building components and all structural steel,” which included building new metal buildings and laying a new roof on an existing gymnasium. Briones’s crew installed the roof overlay on the old gymnasium, but Briones subcontracted much of the rest of the work to Trevino, another contractor who performs metal building erection. The project manual called for a standing seam metal roof, and it required the manufacturer, RollCOM, to warranty the roof for weathertightness. BISD did not select RollCOM to furnish the metal roof until after BISD had entered into its contract with Briones.

Trevino’s crew began constructing their portion of the project sometime between July and September 2002. Tom Weaver was the job superintendent at the time, followed by Drew Scott and Rowdy Hutchins. According to Sandefur, the superintendent was responsible for overall coordination and had no authority to change the project’s specifications or deviate from the contract documents. There was evidence, however, that Weaver was “in charge” at the project site. Although the roof was supposed to be installed by laying and securing the panels from one end of the roof to the other, Weaver erroneously instructed Trevino’s crew to install the roof by setting the panels at both ends of the roof and working towards the middle.

Errors in the installation of the roof installed by Trevino manifested sometime in the Spring of 2003 when DSA sought to have RollCOM issue its

warranty. RollCOM declined to issue the weathertightness warranty after its representatives inspected the roof and discovered that the roof did not fully comply with RollCOM’s specifications. RollCOM inspected the roof a second time and once again found errors in its installation. BISD retained Exterior Consulting Innovations, Inc. (“ECI”) to independently evaluate the roof. ECI counted 115 leaks and opined that the roof had not been installed in accordance with the specifications or the manufacturer’s installation instructions. Sandefur acknowledged that the plans provided to the trade contractors in the bidding process did not include the RollCOM installation instructions, and Frank Trevino, Samuel Trevino’s son, recounted that the “shop drawings” for the roof that Trevino’s crew had were not as detailed as the RollCOM instruction manual, which he saw for the first time just two days before testifying at trial.

DSA gave Briones an opportunity to remedy the defects in the roof, but Briones was ultimately unsuccessful. In March 2004, BISD declared Briones in breach of his contract and terminated his right to complete the project. ECI opined that the roof was beyond repair and that BISD would have to install a new roof to correct the problems. Stuckey opined that a new roof or overlaying the roof with another roof layer would be needed to cure the problems.

BISD sued Briones and Trevino for breach of contract, breach of warranty, violations of the Deceptive Trade Practices Act (“DTPA”), and negligence. Briones and Trevino sued DSA, but the trial court granted DSA’s no evidence motions for summary judgment as to both Briones’s and Trevino’s claims. In its charge to the jury, the trial court included an instruction that “the actions of DSA, Inc. are those of Brock Independent School District.” The jury found that BISD, Briones, and Trevino were all negligent, apportioning 85% of the negligence to BISD, 10% of the negligence to Briones, and 5% of the negligence to Trevino. The jury answered “No” to the DTPA question and “No” to the question asking whether Briones failed to comply with his contract with BISD. The jury, however, answered “Yes” to the question asking whether Briones failed to comply with a warranty, and it awarded BISD damages in the amount of $519,771.00. BISD filed a motion for new trial, which the trial court denied. This appeal followed.

III. S UFFICIENCY A RGUMENTS In its third issue, BISD argues that the jury’s damages finding of $519,771.00 is “not supported by the evidence” because it was “inadequate, contrary to the evidence, and had no rational basis.” 2 In its fifth issue, BISD

2 Although BISD does not specifically state that the jury’s damages finding is “against the great weight and preponderance of the evidence” (like in its

argues that the jury’s “No” answer to the contract-compliance question is against the great weight and preponderance of the evidence.

A. Standard of Review When a party challenges the factual sufficiency of a finding on an issue on which it had the burden of proof, it must demonstrate that the adverse finding is against the great weight and preponderance of the evidence. Dow Chem. Co. v. Francis, 46 S.W.3d 237, 242 (Tex. 2001). When reviewing an issue asserting that a finding is “against the great weight and preponderance” of the evidence, we must consider and weigh all of the evidence and set aside the finding only if the evidence is so weak or the finding is so contrary to the great weight and preponderance of the evidence as to be clearly wrong and unjust. Id.; In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660, 661 (1951). The trier of fact is the sole judge of the credibility of witnesses and the weight

second and fifth issues), the relief that BISD prays for (that the trial court’s judgment be reversed and that the case be remanded for a new trial) is consistent with the relief accompanying a determination that the evidence is factually insufficient to support a finding. See Glover v. Tex. Gen. Indem. Co., 619 S.W.2d 400, 401–02 (Tex. 1981) (op. refusing writ n.r.e.) (stating that when a court of appeals sustains a point or issue because the evidence is factually insufficient, it must reverse the judgment of the trial court and remand for a new trial). We therefore construe BISD’s third issue as challenging the factual sufficiency of the evidence to support the finding.

Free access — add to your briefcase to read the full text and ask questions with AI

Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction, (Tex. Ct. App. 2008).

Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction (Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
In Re Commitment of Almaguer
117 S.W.3d 500 (Court of Appeals of Texas, 2003)
Potter v. GMP, L.L.C.
141 S.W.3d 698 (Court of Appeals of Texas, 2004)
Mills v. Jackson
711 S.W.2d 427 (Court of Appeals of Texas, 1986)
Glover v. Texas General Indemnity Co.
619 S.W.2d 400 (Texas Supreme Court, 1981)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Union Pacific Railroad v. Williams
85 S.W.3d 162 (Texas Supreme Court, 2002)
M.N. Dannenbaum, Inc. v. Brummerhop
840 S.W.2d 624 (Court of Appeals of Texas, 1992)
In Re King's Estate
244 S.W.2d 660 (Texas Supreme Court, 1951)
Mayberry v. Texas Department of Agriculture
948 S.W.2d 312 (Court of Appeals of Texas, 1997)
Gulf States Utilities Co. v. Low
79 S.W.3d 561 (Texas Supreme Court, 2002)
Walker v. Gutierrez
111 S.W.3d 56 (Texas Supreme Court, 2003)
James v. Kloos
75 S.W.3d 153 (Court of Appeals of Texas, 2002)
State Farm Lloyds v. Nicolau
951 S.W.2d 444 (Texas Supreme Court, 1997)
Clary Corp. v. Smith
949 S.W.2d 452 (Court of Appeals of Texas, 1997)
Wal-Mart Stores, Inc. v. Middleton
982 S.W.2d 468 (Court of Appeals of Texas, 1998)
Bolt v. State
16 S.W.2d 235 (Court of Criminal Appeals of Texas, 1929)
In the Interest of V.L.K.
24 S.W.3d 338 (Texas Supreme Court, 2000)