Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction

CourtCourt of Appeals of Texas
DecidedMarch 13, 2008
Docket02-07-00002-CV
StatusPublished

This text of Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction (Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction, (Tex. Ct. App. 2008).

Opinion

COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH

NO. 2-07-002-CV

BROCK INDEPENDENT SCHOOL APPELLANT DISTRICT V.

TONY BRIONES D/B/A WEST TEXAS APPELLEES CONCRETE AND METAL BUILDINGS, SAMUEL TREVINO D/B/A SAM’S CONSTRUCTION ------------

FROM THE 415TH DISTRICT COURT OF PARKER COUNTY

------------

MEMORANDUM OPINION 1

I. INTRODUCTION

Appellant Brock Independent School District (“BISD”) sued Appellees

Tony Briones d/b/a West Texas Concrete and Metal Buildings (“Briones”) and

Samuel Trevino d/b/a Sam’s Construction (“Trevino”) (collectively “Appellees”)

1 See T EX. R. A PP. P. 47.4. for damages resulting from Appellees’ installation of a roof in connection with

a school construction project. A jury awarded BISD $519,771.00. In five

issues, BISD argues that the trial court erred by submitting two instructions,

that the jury’s negligence apportionment finding and “No” answer to the

contract-compliance question are against the great weight and preponderance

of the evidence, and that the evidence is factually insufficient to support the

jury’s damages finding. We will affirm.

II. F ACTUAL AND P ROCEDURAL B ACKGROUND

BISD sought to build a new elementary and middle school in late 2001.

It hired D.S.A., Inc. as a construction manager to assist with the bidding

process and oversee the project. BISD hired Stuckey Architects, Inc. as the

architect. Stuckey prepared a project manual for BISD setting forth the general

and supplemental conditions and specifications for the project and instructions

for placing bids on the project. BISD ultimately awarded each phase of the

project to a different subcontractor, who contracted directly with BISD, the

owner, as a trade contractor.

Burton Sandefur, a project manager for DSA, knew Briones from previous

jobs and contacted him about the BISD project. Briones, who performs

concrete and metal building construction, subsequently signed a contract with

BISD in March 2002 to furnish equipment and labor to erect “all pre-engineered

2 metal building components and all structural steel,” which included building new

metal buildings and laying a new roof on an existing gymnasium. Briones’s

crew installed the roof overlay on the old gymnasium, but Briones

subcontracted much of the rest of the work to Trevino, another contractor who

performs metal building erection. The project manual called for a standing seam

metal roof, and it required the manufacturer, RollCOM, to warranty the roof for

weathertightness. BISD did not select RollCOM to furnish the metal roof until

after BISD had entered into its contract with Briones.

Trevino’s crew began constructing their portion of the project sometime

between July and September 2002. Tom Weaver was the job superintendent

at the time, followed by Drew Scott and Rowdy Hutchins. According to

Sandefur, the superintendent was responsible for overall coordination and had

no authority to change the project’s specifications or deviate from the contract

documents. There was evidence, however, that Weaver was “in charge” at the

project site. Although the roof was supposed to be installed by laying and

securing the panels from one end of the roof to the other, Weaver erroneously

instructed Trevino’s crew to install the roof by setting the panels at both ends

of the roof and working towards the middle.

Errors in the installation of the roof installed by Trevino manifested

sometime in the Spring of 2003 when DSA sought to have RollCOM issue its

3 warranty. RollCOM declined to issue the weathertightness warranty after its

representatives inspected the roof and discovered that the roof did not fully

comply with RollCOM’s specifications. RollCOM inspected the roof a second

time and once again found errors in its installation. BISD retained Exterior

Consulting Innovations, Inc. (“ECI”) to independently evaluate the roof. ECI

counted 115 leaks and opined that the roof had not been installed in

accordance with the specifications or the manufacturer’s installation

instructions. Sandefur acknowledged that the plans provided to the trade

contractors in the bidding process did not include the RollCOM installation

instructions, and Frank Trevino, Samuel Trevino’s son, recounted that the “shop

drawings” for the roof that Trevino’s crew had were not as detailed as the

RollCOM instruction manual, which he saw for the first time just two days

before testifying at trial.

DSA gave Briones an opportunity to remedy the defects in the roof, but

Briones was ultimately unsuccessful. In March 2004, BISD declared Briones in

breach of his contract and terminated his right to complete the project. ECI

opined that the roof was beyond repair and that BISD would have to install a

new roof to correct the problems. Stuckey opined that a new roof or overlaying

the roof with another roof layer would be needed to cure the problems.

4 BISD sued Briones and Trevino for breach of contract, breach of

warranty, violations of the Deceptive Trade Practices Act (“DTPA”), and

negligence. Briones and Trevino sued DSA, but the trial court granted DSA’s

no evidence motions for summary judgment as to both Briones’s and Trevino’s

claims. In its charge to the jury, the trial court included an instruction that “the

actions of DSA, Inc. are those of Brock Independent School District.” The jury

found that BISD, Briones, and Trevino were all negligent, apportioning 85% of

the negligence to BISD, 10% of the negligence to Briones, and 5% of the

negligence to Trevino. The jury answered “No” to the DTPA question and “No”

to the question asking whether Briones failed to comply with his contract with

BISD. The jury, however, answered “Yes” to the question asking whether

Briones failed to comply with a warranty, and it awarded BISD damages in the

amount of $519,771.00. BISD filed a motion for new trial, which the trial

court denied. This appeal followed.

III. S UFFICIENCY A RGUMENTS

In its third issue, BISD argues that the jury’s damages finding of

$519,771.00 is “not supported by the evidence” because it was “inadequate,

contrary to the evidence, and had no rational basis.” 2 In its fifth issue, BISD

2 Although BISD does not specifically state that the jury’s damages finding is “against the great weight and preponderance of the evidence” (like in its

5 argues that the jury’s “No” answer to the contract-compliance question is

against the great weight and preponderance of the evidence.

A. Standard of Review

When a party challenges the factual sufficiency of a finding on an issue

on which it had the burden of proof, it must demonstrate that the adverse

finding is against the great weight and preponderance of the evidence. Dow

Chem. Co. v. Francis, 46 S.W.3d 237, 242 (Tex. 2001). When reviewing an

issue asserting that a finding is “against the great weight and preponderance”

of the evidence, we must consider and weigh all of the evidence and set aside

the finding only if the evidence is so weak or the finding is so contrary to the

great weight and preponderance of the evidence as to be clearly wrong and

unjust. Id.; In re King’s Estate, 150 Tex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
In Re Commitment of Almaguer
117 S.W.3d 500 (Court of Appeals of Texas, 2003)
Potter v. GMP, L.L.C.
141 S.W.3d 698 (Court of Appeals of Texas, 2004)
Mills v. Jackson
711 S.W.2d 427 (Court of Appeals of Texas, 1986)
Glover v. Texas General Indemnity Co.
619 S.W.2d 400 (Texas Supreme Court, 1981)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Union Pacific Railroad v. Williams
85 S.W.3d 162 (Texas Supreme Court, 2002)
M.N. Dannenbaum, Inc. v. Brummerhop
840 S.W.2d 624 (Court of Appeals of Texas, 1992)
In Re King's Estate
244 S.W.2d 660 (Texas Supreme Court, 1951)
Mayberry v. Texas Department of Agriculture
948 S.W.2d 312 (Court of Appeals of Texas, 1997)
Gulf States Utilities Co. v. Low
79 S.W.3d 561 (Texas Supreme Court, 2002)
Walker v. Gutierrez
111 S.W.3d 56 (Texas Supreme Court, 2003)
James v. Kloos
75 S.W.3d 153 (Court of Appeals of Texas, 2002)
State Farm Lloyds v. Nicolau
951 S.W.2d 444 (Texas Supreme Court, 1997)
Clary Corp. v. Smith
949 S.W.2d 452 (Court of Appeals of Texas, 1997)
Wal-Mart Stores, Inc. v. Middleton
982 S.W.2d 468 (Court of Appeals of Texas, 1998)
Bolt v. State
16 S.W.2d 235 (Court of Criminal Appeals of Texas, 1929)
In the Interest of V.L.K.
24 S.W.3d 338 (Texas Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Brock Independent School District v. Tony Briones D/B/A West Texas Concrete and Metal Buildings, Samuel Trevino D/B/A Sam's Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brock-independent-school-district-v-tony-briones-d-texapp-2008.