Brock Bridge Ltd. Partnership, Inc. v. Development Facilitators, Inc.

689 A.2d 622, 114 Md. App. 144, 1997 Md. App. LEXIS 30
CourtCourt of Special Appeals of Maryland
DecidedFebruary 26, 1997
Docket1768, Sept. Term, 1995
StatusPublished
Cited by14 cases

This text of 689 A.2d 622 (Brock Bridge Ltd. Partnership, Inc. v. Development Facilitators, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brock Bridge Ltd. Partnership, Inc. v. Development Facilitators, Inc., 689 A.2d 622, 114 Md. App. 144, 1997 Md. App. LEXIS 30 (Md. Ct. App. 1997).

Opinion

DAVIS, Judge.

Brock Bridge Limited Partnership (BBLP) and Brock Bridge Builders, Inc. (BBBI) appeal from, a judgment of the Circuit Court for Anne Arundel County in favor of Development Facilitators, Inc. (DFI) and Raymond Streib (Streib). Appellants had filed a four-count Amended Complaint on December 23, 1994, alleging breach of a contract to construct roadside improvements in a housing development for the agreed price, malpractice for negligently misrepresenting the costs of construction, malpractice for failure to process an application for a wetlands permit, and intentional misrepresentation.

The court dismissed the intentional misrepresentation claim at the end of the plaintiffs’ case. After a ten-day trial without a jury, the court found that appellants had not carried their *147 burden of proof on the breach of contract claim. The court also found that the breach of a contract would not sustain an action sounding in tort, dismissing the claim for malpractice for negligently estimating the costs of construction. Appellants do not appeal the court’s disposition of the wetlands claim or its dismissal of the intentional misrepresentation claim. They appeal the court’s judgment regarding the breach of contract claim and the negligence claim. 1

Appellants present the following questions for our review, renumbered and restated as follows:

I. Did the circuit court err as a matter of law when it concluded that BBLP was not indebted to BBBI for BBBI’s expenditures for the project?
II. Was the circuit court clearly erroneous in its determination that it could not award damages to appellants based on anything other than pure speculation?
III. Did the circuit court err as a matter of law when it ruled that the evidence did not support a cause of action for negligent misrepresentation against Streib individually?

We answer in the affirmative to all three questions. 2 Consequently, we reverse the judgment as to the first and third issues, and vacate the judgment on the second.

FACTS

The legal relationships of the parties to this case are interwoven with such complexity as to make a detailed explanation unhelpful. Therefore, we shall not attempt to parse out and define every bit player; however, we will provide all of the *148 information necessary to an understanding of the issues underlying this appeal.

BBBI is a Maryland corporation whose principals are George Stone (Stone) and Weston Stone (Weston). In 1988, W.F. Utz Construction Company, Inc. (Utz) contracted to purchase real property in Anne Arundel County from Mary and Lawrence Taylor. Utz retained Streib, an engineer, to provide on-site engineering services through his company, DFI, for a contemplated development on the land, Brock Bridge Estates. 3 Streib is the president of DFI. On June 15, 1990, Utz assigned its interest in the purchase contract to BBBI, including all rights to engineering services rendered with respect to the property. The assignment was intended to cement a relationship by which Utz and Stone would participate in the development project as 50-50 partners.

On March 22, 1991, BBBI, through its principal, Stone, formed BBLP, a limited partnership with BBBI as general partner. At this point, neither Stone nor Utz had committed himself irrevocably to the development project. The latest extension of the purchase contract called for settlement by June 7, 1991. By early 1991, however, bids had been received for most of the project except for the off-site road improvements. Monetary considerations led Stone to inform Streib that the off-site road improvement costs, if too high, could cause Stone to abandon the project as economically unfeasible. Streib assured Stone that, based on an estimate performed in February by his project engineer, Matthew Morgan, the cost of the off-site improvements within the existing right-of-way of Brock Bridge Road would not be more than $1,000 per lot for sixty-seven or sixty-eight lots, which he rounded off to $70,000.

On June 5, 1991, BBBI assigned the purchase contract to BBLP. On that same day, BBLP and Stone executed a letter agreement with DFI. Stone signed individually and on behalf of BBLP, and Streib, the day after receiving the letter, signed *149 on behalf of DFI, in his capacity as president. The agreement read as follows:

Dear Ray:
You have advised me that the County will not sign off on the record plat for “Brock Bridge Estates” until execution and delivery of the Agreement between the Developer and the County requiring (i) design of off-site improvements (for Phases 1 and 2 as defined in the Agreement) within existing rights of way for Brock Bridge Road, for Phases 1 and 2, and (ii) construction of improvements under Phase 1 only.
On behalf of the Developer, I have advised you that we do not intend to go forward with the development of the Project without your assurance that the costs for all work required under the aforementioned Agreement (including costs of engineering, costs of construction of improvements and any and all other out-of-pocket * costs to the Developer) will not exceed $70,000 in the aggregate. You have assured me, in the exercise of your professional judgment and responsibility, that the costs required to meet the conditions of the aforesaid Agreement will not exceed $70,000. In the event costs incurred by Developer to meet the obligations to the County under the Agreement exceed $70,000 in the aggregate, you have further agreed that Development Facilitators, Inc. will be liable to Brock Bridge Limited Partnership (“BBLP”) for the difference and shall reimburse, indemnify and hold BBLP harmless for any such excess.
In reliance on your representations as to costs, we are prepared to go forward by executing the Agreement on behalf of Brock Bridge Limited Partnership. Please sign below acknowledging receipt of this letter, and agreeing to undertake the liability for excess costs as provided above.
' Refer to phone conversation with Mr. Dennis Hoover, the item of out of pocket expenses means payment to third parties (i.e. right of ways) required in order that construction can occur.

At the date of this letter, no final plans or construction drawings for the off-site improvements existed. The “Agreement” referred to in the letter was the agreement between

*150 Anne Arundel County and Utz for the development of the real estate. It defined Phase One improvements as follows:

a. Phase One consists of approximately 2,750 linear feet of road/shoulder widening, with up to 24 feet of Macadam Paving and 8 feet of 4 inches sand asphalt shoulder on both sides of Brock Bridge Road and within the existing right-of-way, and any storm drains and any other appurtenances within the existing right-of-way as shown on the plans attached hereto as Exhibit A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howard R. & D. Corp. v. IMH Columbia
Court of Special Appeals of Maryland, 2025
Maryland Indoor Play v. Snowden Investment
Court of Appeals of Maryland, 2025
Yacoubou v. Wells Fargo Bank, N.A.
901 F. Supp. 2d 623 (D. Maryland, 2012)
Baltimore Line Handling Co. v. Brophy
771 F. Supp. 2d 531 (D. Maryland, 2011)
Adams v. NVR Homes, Inc.
135 F. Supp. 2d 675 (D. Maryland, 2001)
Owens Corning v. Walatka
725 A.2d 579 (Court of Special Appeals of Maryland, 1999)
Doe v. Doe
712 A.2d 132 (Court of Special Appeals of Maryland, 1998)
Lopata v. Miller
712 A.2d 24 (Court of Special Appeals of Maryland, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
689 A.2d 622, 114 Md. App. 144, 1997 Md. App. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brock-bridge-ltd-partnership-inc-v-development-facilitators-inc-mdctspecapp-1997.