Broadkill Beach Builders, LLC v. Frampton

Superior Court of Delaware·Decided June 30, 2025·No. S23L-09-009 RHR·Published

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

BROADKILL BEACH BUILDERS, LLC, ) A Delaware Limited Liability Company, )

Plaintiff, )

)

v. ) C.A. No.: S23L-09-009 RHR )

WILSON FRAMPTON and ) CAROL FRAMPTON, )

Defendants. )

Submitted: March 24, 2025 Decided: June 30, 2025

MEMORANDUM OPINION

Upon Consideration of Plaintiff Broadkill Beach Builders, LLC’s Motion for Summary Judgment,

GRANTED,

Defendants Wilson Frampton and Carol Frampton’s Motion in Limine, MOOT.

Dean A. Campbell, Esq., LAW OFFICE OF DEAN CAMPBELL, P.A., Milton, Delaware, Attorney for Plaintiff Broadkill Beach Builders, LLC.

Richard E. Berl, Jr., Esq. and Angelica Mamani, Esq., HUDSON JONES JAYWORK & FISHER, LLC, Lewes, Delaware, Attorneys for Defendants Wilson Frampton and Carol Frampton.

Robinson, J.

Wilson and Carol Frampton (collectively, the “Framptons”) hired Broadkill Beach Builders, LLC (“Broadkill”) to make repairs to a rental house they owned in Broadkill Beach, Delaware. Upon receiving their final bill, the Framptons refused to pay the 20% management fee called for in the contract due to their mistaken belief that the fee had been applied to their previous invoices, and because they believed Broadkill overcharged them. Broadkill filed a complaint seeking a mechanic’s lien and asserting claims of breach of contract and unjust enrichment. The Framptons filed counterclaims for breach of contract, consumer fraud, and deceptive trade practices. Broadkill also filed a motion in limine seeking to exclude an expert report that the Framptons obtained. Broadkill now moves for summary judgment. This court finds that Broadkill is entitled to summary judgment, and that the Framptons’ counterclaims fail, both on their individual merits and because they are barred by the voluntary payment doctrine to the extent that they seek recovery of previous payments. This decision renders the motion in limine moot.

I. FACTUAL AND PROCEDURAL BACKGROUND Broadkill is a general contractor that primarily serves the community of Broadkill Beach. After noticing some water damage to soffits on the house, the Framptons hired Broadkill to repair the damage. Wilson Frampton signed a letter prepared by Broadkill that states, in its entirety:

Dear Mr. Frampton,

We do hereby propose to repair a rotten roof, fascia[,] and soffit as needed on a time and material [basis] [p]lus 20%. Cost will be $50.00 per man hour. A lift will be provided as [a] major percentage of work is high, this is at the owners[’] cost. Dumpster will be provided at owners[’] cost. Owner will be invoiced every two weeks.

Thank you, Allen S. Davis1 Broadkill began making repairs on October 31, 2022 and soon discovered additional damage. The water damage extended from the roof to the first floor. The parties agreed that the terms of the contract would govern the costs of further repairs. Broadkill eventually removed and replaced the siding, repaired two decks, and installed a new roof. Between August 3, 2022 and March 29, 2023, Broadkill sent the Framptons six invoices for material and labor costs, ranging from $13,457.47 to $39,500.00. None of the invoices contained the 20% markup fee. After the work was “substantially complete” (the parties’ briefings are inconsistent as to the exact date), Broadkill sent an invoice with the 20% markup fee totaling $30,153.58.2 The Framptons, only then realizing that the markup had not been included in their previous invoices, refused to pay.3 Broadkill filed its complaint and statement for mechanic’s lien on September 12, 2023, asserting that the Framptons’ refusal

1 D.I. 29, Mot. for Summ. J., Ex. C. 2 The parties both refer to this amount being due, but the invoice attached to the motion for summary judgment appears to state that 20% is $29,867.08. 3 D.I. 29, Mot. for Summ. J., Ex. D at 60.

amounted to a breach of contract and that they were unjustly enriched as a result.4 Broadkill asks this court to enter judgment in its favor for $30,153.58 plus pre- and post-judgment interest, costs, and attorneys’ fees. In response, the Framptons argue that they were overbilled and are therefore entitled to set-offs for money that was improperly collected.5 The Framptons brought counterclaims for breach of contract, prohibited trade practices/consumer fraud, and deceptive trade practices. Broadkill moved for summary judgment.6 At an office conference, the court suggested that the parties attempt to settle this dispute—pointing out that both parties seemed unaware that the repairs would be so extensive when they entered into a time and materials contract—but they were unable to reach an agreement.

II. THE PARTIES’ CONTENTIONS In support of their breach of contract counterclaim, the Framptons allege that Broadkill breached the contract by (1) overcharging, (2) failing to keep and provide a more detailed accounting of its costs, and (3) improperly calculating the management fee based on materials and labor “not utilized in construction.”7 In support of their counterclaims for consumer fraud and deceptive trade practices, the

4 D.I. 1, Compl. 5 D.I. 8, Def.’s Answer & Countercl. at 5. 6 Broadkill subsequently filed a motion in limine which is rendered moot by this opinion. Summary judgment is appropriate irrespective of the admissibility of the discovery contested therein. 7 D.I. 8, Def’s Answer & Countercl. at 5.

Framptons assert that Broadkill intentionally concealed its management fee and repeat the allegations made in their breach of contract counterclaim.

In its motion for summary judgment, Broadkill contends that there is no dispute that the Framptons breached the contract and that each of the Framptons’ counterclaims are meritless. In support of their first argument, Broadkill explains that the Framptons’ failure to pay the final invoice clearly satisfied each of the elements of breach of contract: (1) an obligation, (2) a breach of the obligation, and (3) resulting damages.8 Broadkill claims that the Framptons agreed to pay for “time and material plus 20%,” and breached when they refused to pay the 20%.9 In support of its second argument, Broadkill explains that the Framptons’ counterclaims must fail for two reasons: (1) the counterclaims are insufficient on their individual merits, and (2) the Framptons failed to produce evidence supporting their overarching theory that they were overcharged (which is a prerequisite for each counterclaim). Broadkill argues that the Framptons’ breach of contract counterclaim is meritless because their voluntary payments prevent them from recovering payments already made in the absence of fraud. For the deceptive trade practices counterclaim, Broadkill asserts that the Framptons lack standing because the Deceptive Trade Practices Act (“DTPA”) extends only to claimants with “competing business

8 D.I. 30, Pl.’s Opening Br. in Supp. of its Mot. for Summ. J. at 8 (citing River Valley Ingredients LLC v. American Proteins, Inc., 2021 WL 598539 (Del. Super. 2021)). 9 Id.

interests,” rather than consumers.10 Finally, for the consumer fraud claim, Broadkill argues that (1) there is no evidence of fraud; (2) the Framptons’ belief that they overpaid does not give rise to a claim for fraud; and (3) the voluntary payment doctrine is dispositive of subsequent attempts to assert fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Broadkill Beach Builders, LLC v. Frampton, (Del. Ct. App. 2025).

Broadkill Beach Builders, LLC v. Frampton (Broadkill Beach Builders, LLC v. Frampton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Nemec v. Shrader
991 A.2d 1120 (Supreme Court of Delaware, 2010)
Grand Ventures, Inc. v. Whaley
632 A.2d 63 (Supreme Court of Delaware, 1993)