Bristol Metals, LLC v. Messer, LLC

CourtDistrict Court, E.D. Virginia
DecidedNovember 2, 2020
Docket3:20-cv-00203
StatusUnknown

This text of Bristol Metals, LLC v. Messer, LLC (Bristol Metals, LLC v. Messer, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bristol Metals, LLC v. Messer, LLC, (E.D. Va. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Richmond Division BRISTOL METALS, LLC, Plaintiff, v. Civil No. 3:20cv203 (DJN) MESSER, LLC, Defendant. MEMORANDUM OPINION Plaintiff Bristol Metals, LLC (“Plaintiff”) brings this action against Messer LLC (“Defendant”), alleging that Defendant breached its contract (the “Product Agreement”) with Plaintiff by increasing prices for the gasses that Defendant sold to Plaintiff by more than 2% per year. Plaintiff seeks damages for the overcharges and a declaratory judgment declaring that the Product Agreement limits yearly price increases to 2% and/or allows Plaintiff to terminate the parties’ relationship immediately. This matter comes before the Court on the parties’ cross Motions for Summary Judgment (ECF Nos. 15, 17), moving the Court to grant summary judgment in favor of each party on their respective interpretations of the Product Agreement and a subsequent addendum to it (the “2008 Addendum” or the “Addendum”’). For the reasons set forth below, the Court GRANTS IN PART and DENIES IN PART the Motions for Summary Judgment (ECF Nos. 15, 17). The Court GRANTS Plaintiff's Motion on the issue of whether the Product Agreement limits Defendant’s ability to increase gas prices to 2% per year beyond January 24, 2020, but DENIES Plaintiff’s Motion to the extent it seeks damages from before January 24, 2020, and a declaration that Plaintiff may terminate the parties’ relationship immediately. Likewise, the Court GRANTS Defendant’s Motion on the issue that

Plaintiff waived the right to enforce the 2% price-escalation provision before January 24, 2020, but DENIES Defendant’s Motion on the issue of whether the 2008 Addendum effected a permanent change to the Product Agreement. In short, the Court finds that Plaintiff may only enforce the 2% price-escalation term as of January 24, 2020. I. BACKGROUND For purposes of factual background, the Court recites the basic allegations in Plaintiff's Complaint, the parties’ agreed Stipulations and the undisputed fact sections of the parties’ memoranda. Except as otherwise indicated, the parties do not dispute the facts stated below. A. Factual Allegations Plaintiff filed its Complaint against Defendant on March 25, 2020. (Compl. (ECF No. 1).) Plaintiff manufactures steel pipe for various industrial uses and sells its products to customers around the world. (Compl. § 1.) In 1998, Defendant’s predecessor-in-interest entered into a Product Agreement with Plaintiff's predecessor-in-interest whereby Defendant’s predecessor agreed to sell and deliver certain industrial gases to Plaintiff's predecessor at a facility in Munhall, Pennsylvania.' (Stip. ff 1-3 (ECF No. 14).) Relevant here, the Product Agreement contained a price-escalation clause that limited annual price increases to 2%. (Stip. Ex. 1, at 3.) Further, the Product Agreement allowed the parties to negotiate individual price increases by affording Plaintiff the opportunity to solicit a bona fide offer from a third party. (Stip. Ex. 1, at 2.) If Defendant matched the offer, the Product Agreement would extend by another seven years. (Stip. Ex. 1, at 2.) If Defendant did not match the offer, Plaintiff could

I The parties agree that each company assumed the rights and obligations under the Product Agreement from their respective predecessors-in-interest. (Stip. [] 2, 3.) Accordingly, the Court will hereafter refer to the parties simply as “Plaintiff? and “Defendant” without reference to the predecessor companies.

cancel the contract. (Stip. Ex. 1, at 2.) By its terms, the Product Agreement contemplated a continuing relationship that governed the parties’ relationship for the next ten years. (Stip. Ex. 1, at 1.) Additionally, the Product Agreement would automatically renew for another ten years unless terminated by either party with at least twelve months’ advance notice. (Stip. Ex. 1, at 1.) The Product Agreement would also renew for ten years after the first delivery to the last storage tank that Defendant installed at the Munhall facility. (Stip. Ex. 1, at 1.) In September 2008, on the eve of the Product Agreement’s ten-year renewal, the parties executed an addendum to the Product Agreement (the “2008 Addendum” or “the Addendum”). (Stip. Ex. 2.) The 2008 Addendum extended the Product Agreement by five years and set forth a new price-escalation schedule that allowed Defendant to increase prices by up to 9% in year two and 8% in years three through five. (Stip. Ex. 2, at 1.) The 2008 Addendum says nothing about price caps beyond year five, nor does it say anything about the Product Agreement’s automatic renewal provisions. (Stip. Ex. 2, at 1.) Plaintiff alleges that it first learned of the 2008 Addendum in January 2020.2 (Compl. 4 19.) Neither party gave written notice of their intent to terminate the Product Agreement as of September 1, 2013. (Stip. J 5.) On June 23, 2017, Plaintiff sent Defendant a letter giving Defendant notice of Plaintiff's intent to terminate the Product Agreement. (Stip. Ex. 3, at 1.) Plaintiff apparently believed that the Product Agreement would expire in September 2018. (Stip. Ex. 3, at 1.) On June 30, 2017, Defendant responded to the letter with a rejection of Plaintiff's notice to terminate, asserting that the Product Agreement did not expire until December 19, 2023. (Stip. Ex. 4, at 1.) According to Defendant, the Product Agreement had renewed for another ten-year

2 Plaintiff assumed its rights and obligations under the Product Agreement in March 2017, _ when it acquired predecessor-in-interest Marcegaglia, USA, Inc. (Stip. 3.)

term on December 19, 2013, when Defendant installed a vertical hydrogen storage tank at the Munhall facility. (Stip. Ex. 4, at 1.) Plaintiff later sent a letter noting its intent to terminate the Product Agreement upon its expiration on December 19, 2023. (Stip. Ex. 5, at 1.) On January 24, 2020, Plaintiff sent a letter to Defendant advising that Plaintiff recently learned of the 2008 Addendum. (Stip. Ex. 7, at 1-2.) In that letter, Plaintiff staked out its belief that the Addendum’s silence with respect to price escalation after year five meant that the original 2% price-escalation limit in the Product Agreement took effect after September 2013. (Stip. Ex. 7, at 1-2.) Plaintiff now alleges that Defendant has and continues to overcharge Plaintiff by failing to comply with the 2% price-escalation cap. (Compl. { 24-26.) On February 3, 2020, Defendant responded to Plaintiff with its own letter, arguing that Defendant consistently charged prices in excess of the 2% cap since 2013, and that Plaintiff never complained about the charges. (Stip. Ex. 8, at 2.) The parties do not dispute that Defendant has increased its prices beyond the 2% cap for each year since 2014, and that Plaintiff paid the invoiced costs each year without complaint until January 24, 2020. (Stip. §{ 8, 16, Ex. 9, at 1; Def.s’ Mem. in Supp. of Summ. J. (“Def.s’ Mem”) (ECF No. 18) at 9, 10.) Plaintiff alleges that Defendant breached the Product Agreement by escalating its prices more than 2% each year since 2017. (Compl. {J 33-40.) Accordingly, Plaintiff brings two causes of action against Defendant for breach of contract and declaratory judgment, respectively. (Compl. { 33-48.) In its request for declaratory judgment, Plaintiff asks the Court to declare that the 2% price escalation-limit binds Defendant for the remainder of the contract. (Compl. ff 42- 48.) Alternatively, Plaintiff seeks a declaration that the 2008 Addendum expired on September 1, 2013, meaning that the parties have been operating under an at-will relationship since that time. (Compl. 42-48.)

B. Motions for Summary Judgment As mentioned, both parties have moved the Court for summary judgment based on their respective interpretations of the 1998 Product Agreement and its 2008 Addendum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Wilton v. Seven Falls Co.
515 U.S. 277 (Supreme Court, 1995)
Philip Morris Inc. v. Harshbarger
122 F.3d 58 (First Circuit, 1997)
Artman v. International Harvester Company
355 F. Supp. 482 (W.D. Pennsylvania, 1973)
Greene v. Oliver Realty, Inc.
526 A.2d 1192 (Supreme Court of Pennsylvania, 1987)
Regscan, Inc. v. Con-Way Transportation Services, Inc.
875 A.2d 332 (Superior Court of Pennsylvania, 2005)
W.I. Snyder Corp. v. Caracciolo
541 A.2d 775 (Supreme Court of Pennsylvania, 1988)
J. W. Goodliffe & Son v. Odzer
423 A.2d 1032 (Superior Court of Pennsylvania, 1980)
Betz v. Erie Insurance Exchange
957 A.2d 1244 (Superior Court of Pennsylvania, 2008)
Steuart v. McChesney
444 A.2d 659 (Supreme Court of Pennsylvania, 1982)
Lewis v. CITY OF VIRGINIA BEACH SHERIFF'S OFFICE
409 F. Supp. 2d 696 (E.D. Virginia, 2006)
Lenau, N. v. Co-Exprise, Inc.
102 A.3d 423 (Superior Court of Pennsylvania, 2014)
Rossignol v. Voorhaar
316 F.3d 516 (Fourth Circuit, 2003)
Trustgard Insurance Company v. Sharon Collins
942 F.3d 195 (Fourth Circuit, 2019)
Mun. Auth. of Westmoreland Cnty. v. CNX Gas Co.
380 F. Supp. 3d 464 (W.D. Pennsylvania, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Bristol Metals, LLC v. Messer, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bristol-metals-llc-v-messer-llc-vaed-2020.