Brinich v. Jencka

757 A.2d 388, 2000 Pa. Super. 209, 2000 Pa. Super. LEXIS 1591
CourtSuperior Court of Pennsylvania
DecidedJuly 28, 2000
StatusPublished
Cited by77 cases

This text of 757 A.2d 388 (Brinich v. Jencka) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brinich v. Jencka, 757 A.2d 388, 2000 Pa. Super. 209, 2000 Pa. Super. LEXIS 1591 (Pa. Ct. App. 2000).

Opinion

MONTEMURO, J.:

¶ 1 This is an appeal from the judgment entered March 16, 1999 in the Washington County Court of Common Pleas in favor of Appellee, John Brinich d/b/a Brinich Builders, and against Appellants, Timothy and Rachel Jencka, for breach of contract, defamation and unjust enrichment. For the reasons set forth below, we affirm.

¶ 2 In July 1993, the Jenckas met with Brinich to discuss construction of their new home. 1 The Jenckas had previously purchased land and obtained architectural plans for the design. After several meetings that summer, the parties finally agreed on a contract price of $173,000. 2 The parties signed an agreement, dated August 10, 1993, which provided for the work to be “substantially completed” by December 31. (Complaint, Exhibit A, Agreement, dated 8/10/93, at Article II).

¶ 3 The Jenckas’ first application for a construction loan, with Mortgage Network Corporation, was denied. They subsequently submitted an application to Integ-ra Bank which ultimately approved the loan after the construction price was once again reduced, this time to $170,000; closing occurred on October 8, 1993. The resulting Construction Loan Agreement (CLA), signed by all the parties, provided for improvements to be completed within 270 days of the date of the Agreement, and specifically “supersede^] any other completion date that may appear in the Contract Documents[,]” including the parties’ August 10th Agreement. 3 (Complaint, Exhibit B, CLA, dated 10/8/93, at ¶2). At closing, Brinich was informed that he could not break ground until he received written notice from Integra.

¶ 4 Despite the delay in securing a construction loan and the revised completion date listed in the CLA, the Jenckas contend that Brinich assured them that the house would be completed by December 31, 1993. Mr. Jencka testified that time was of the essence as his wife was expecting their first child in February, 1994; he claims they informed Brinich that they wanted to be in their house by the time the baby was born. Brinich, however, contends that although the parties did discuss completing the home in five months when they first met in July, he never promised that the house could still be completed by December 31st when closing did not occur *393 until October, and that the Jenckas never insisted on being in the house by February, 1994.

¶ 5 Brinieh received written approval to begin construction on October 13th or 14th However, the excavator was behind schedule and unable to break ground on the Jencka lot until November 3rd. Over the next 8 months, Brinieh encountered numerous problems which impeded his ability to complete construction in a timely manner. First, shortly after the trenching began, the excavator encountered an underground spring that continually filled the foundation with water. To correct the problem, Brinieh had to extend the foundation and install a sump pump. In the meantime, the bloeklayer with whom Bri-nieh subcontracted for the job began work on' another project; therefore, Brinieh was forced to find a replacement at a higher price. In January 1994, construction was delayed by extremely cold weather.

¶ 6 In addition to these problems, Bri-nieh testified that the Jenckas continually requested additions and/or modifications to the home. These changes not only involved additional costs, but also delayed construction. 4 Although Brinieh testified that these changes were requested and approved by the Jenckas, Mr. Jencka claims that he was unaware they would result in additional costs; indeed, he believed some of the modifications would actually result in cost savings. 5 Only one addition, an extension to the garage, was covered by a written agreement signed by the parties. It is undisputed that none of the modifications were submitted to Integ-ra in writing as required by the CLA, see CLA at ¶ 4, and, with one exception, Bri-nieh failed to invoice the Jenckas for these modifications at the time they were completed. 6

¶ 7 Construction continued into the spring of 1994. Brinieh testified that he found notes from the Jenckas almost every morning on the job site requesting he change or move something, or inquiring why a project was not complete. 7 Brinieh received the first three draws in early 1994. Draw #4 for $34,000 was due to be paid in May. The parties submitted a Request for Payment which instructed In-tegra to supply two checks, one to the Jenckas for $11,631,69 “for monies [they] disbursed for lighting & appliances (plumbing,)” and one to Brinieh for the remaining. $22,368.31. 8 (Answer to *394 Amended Complaint, New Matter and Counterclaim Filed on Behalf of the Jenc-kas, Exhibit 3, Request for Payment). Although Brinich disputed this payment, he testified that he felt compelled to sign the disbursement request because “[i]f I didn’t sign this and send it to [Integra], I wasn’t getting any check.... I’ll take $22,000.00 over nothing any day of the week.” (N.T., 9/14-25/98, at 779).

¶ 8 As the deadline under the CLA approached, the parties realized that the house would not be completed on time. Therefore, on June 29, 1994, with the approval of Integra, the parties executed an agreement extending the time for completion of the home until July 21, 1994. See Answer to Amended Complaint, New Matter and Counterclaim Filed on Behalf of the Jenckas, Exhibit 5, Agreement, dated 6/29/94. Attached to the Agreement was a list of uncompleted projects. The Agreement also contained a liquidated damages clause in the event that construction was not completed by the extension deadline.

¶ 9 In late July, Brinich and his family took a week-long vacation. Brinich testified that he left work for his laborers to do during that time and called almost every day. When he returned, however, he learned that his subcontractors had been told by Mr. Jencka to leave the job site because they were not going to be paid.

¶ 10 In early August, at a meeting with the Jenckas to discuss the progress of construction, Brinich explained that he was quickly running out of money because of the many additions and modifications the Jenckas had requested. By the end of September, construction was still not complete and Brinich was completely out of funds. Although he still intended to finish construction, the Jenckas refused to allow Brinich on the property after they obtained an occupancy permit and moved into the house in early October. 9 In addition, the Jenckas refused to authorize disbursement of the final $25,500 draw.

¶ 11 Brinich commenced suit against the Jenckas on December 22, 1994. An Amended Complaint, alleging breach of written and oral contracts, unjust enrichment, tortious interference with contractual relations, and defamation, was filed on May 18, 1995. The Jenckas subsequently filed an Answer and Counterclaim alleging breach of contract, misappropriation of funds and conversion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hernandez, J. v. Independence Constr. Corp.
Superior Court of Pennsylvania, 2025
Joyner, V. v. Thomas Jefferson University Hospital
Superior Court of Pennsylvania, 2025
Peterson, A. v. Stacy's Pizza
Superior Court of Pennsylvania, 2025
Heldring, J. v. Lundy, Beldecos and Milby
Superior Court of Pennsylvania, 2024
Hefferan, R. v. Forbes, M.
Superior Court of Pennsylvania, 2024
M. Mazur v. J. Cuthbert
Commonwealth Court of Pennsylvania, 2024
Burke, C. v. Kubicek, J.
Superior Court of Pennsylvania, 2021
Mitchell, R. v. Megill Homes, Inc
Superior Court of Pennsylvania, 2021
Witherspoon, W. v. Wright, D.
2020 Pa. Super. 254 (Superior Court of Pennsylvania, 2020)
Camiolo, P. v. Erie Insurance Exchange
Superior Court of Pennsylvania, 2019
CKSJB Holdings, LLC v. Epam Sys., Inc.
379 F. Supp. 3d 388 (E.D. Pennsylvania, 2019)
Pittsburgh Logistics Systems v. The Asset Store
Superior Court of Pennsylvania, 2019
Glasgow, A. v. Ducan, I.
Superior Court of Pennsylvania, 2018
Savage, S. v. Jacobson, A.
Superior Court of Pennsylvania, 2018
Romano, B. v. Waffenschmidt, T.
Superior Court of Pennsylvania, 2018
JRW Services Group v. Camp, G.
Superior Court of Pennsylvania, 2017

Cite This Page — Counsel Stack

Bluebook (online)
757 A.2d 388, 2000 Pa. Super. 209, 2000 Pa. Super. LEXIS 1591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brinich-v-jencka-pasuperct-2000.