Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co.

CourtCourt of Appeals of Texas
DecidedApril 21, 2020
Docket05-18-00820-CV
StatusPublished

This text of Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co. (Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co., (Tex. Ct. App. 2020).

Opinion

Affirmed and Opinion Filed April 21, 2020

In The Court of Appeals Fifth District of Texas at Dallas No. 05-18-00820-CV

BRIGHT EXCAVATION, INC., Appellant V. POGUE CONSTRUCTION CO., LP AND HARTFORD FIRE INSURANCE CO., Appellees

On Appeal from the 191st Judicial District Court Dallas County, Texas Trial Court Cause No. DC-17-00591

MEMORANDUM OPINION Before Justices Myers, Osborne, and Nowell Opinion by Justice Nowell This is an appeal from a final take-nothing judgment following the granting

of a traditional and no-evidence motion for summary judgment and a motion for

attorney’s fees. Bright Excavation, Inc., a subcontractor, sued the general contractor,

Pogue Construction Co., LP, and its surety, Hartford Fire Insurance Co., for breach

of contract and other causes of action seeking additional payment for excavation

work Bright claims was beyond the scope of its contract. In seven issues, Bright

argues the trial court erred by granting summary judgment because the subcontract

is ambiguous and the evidence raised fact issues: on waiver and excuse defenses to the contractual time limits for submitting change orders; on Bright’s causes of action

for quantum meruit, promissory estoppel; and on the bond claim against Hartford.

We conclude the subcontract is not ambiguous, the work performed was within the

scope of work, and Bright was not entitled to additional compensation. We also

conclude Bright’s other causes of action fail because there is an express contract

covering the subject matter and no breach of the subcontract to support the bond

claim. We affirm the trial court’s judgment.

Background

Lancaster Independent School District hired Pogue as the general contractor

on a project to build two new elementary schools. This dispute concerns only the

Pleasant Run school. Bright was invited to bid on the earthwork portion of the project

and received a bid package from Pogue containing the plans and specifications and

other relevant documents. Attached to the specifications was a geotechnical report

of the subsurface conditions at the site. Section 00 31 32 of the specifications

instructed, “Report and log of borings are available for Contractor’s information but

is not a warranty of subsurface conditions, nor is it a part of the Contract

Documents.” Section S1.0 of the plans, regarding treatment of the soil beneath the

building, specified: “Perform any cut operations to expose to the top of the limestone

strata. For proposal purposes, contractor shall assume 6 ft of remove and replace

–2– shall be necessary. The geotechnical engineer or a representative of the geotechnical

engineer shall verify the top of the tan limestone.”1

The geotechnical report contained an analysis of subsurface materials at the

selected locations for purposes of formulating appropriate geotechnical design

parameters for the new construction. Attached to the report were logs of widely-

spaced borings taken at the site. The report indicated the recommendations were

developed from borings depicting the subsurface conditions only at the specific

boring locations and at the times designated in the boring logs. It stated that

subsurface conditions at other locations may differ from those observed at the boring

locations and the subsurface conditions at the boring locations may vary at different

times of the year. The report warned that the scope of work “may not fully define

the variability of subsurface material and conditions that are present on the site.”

Bright reviewed the bid package and noted the instruction to assume six feet

of remove and replace would be necessary. However, based on its employees’

experience, Bright concluded it would not be economically feasible to excavate and

replace six feet of material. Rather, Bright interpreted the boring logs to reflect that

the top of tan limestone was expected to be encountered between two and four feet

below ground level. Bright based its bid on the shallower depth for the top of tan

limestone. According to Bright’s witnesses, it disclosed its bidding process to Pogue

1 The documents in the record refer to this strata variously as “tan shaly limestone,” “tan limestone,” or “shale limestone.” For simplicity we use the term tan limestone. –3– in a scope review prior to the final acceptance of the bid. Pogue’s witnesses deny

that these discussions took place.

Bright’s bid for the earthwork was accepted by Pogue. Prior to execution of

the subcontract, Pogue sent a notice to proceed, which contained a listing of the

earthwork as described in the plans and specifications, to Bright on May 10, 2016.

Line item 57 in the initial notice to proceed stated, “Building Pad Subgrade

preparation- overexcavation to limestone, moisture condition in 8” lifts with 1’ select

fill cap or flex base.” Later that day, Pogue sent a revised notice to proceed changing

line item 57 to read, “Building Pad Subgrade preparation- overexcavation to

limestone, prep for ½” movement per Geotechnical Report with select fill of

flexbase.” Bright contends this change in the notice to proceed reflected Pogue’s

agreement that Bright would excavate to the top of tan limestone in accordance with

the geotechnical report.

Bright and Pogue executed the subcontract on June 1, 2016 and June 21, 2016

respectively. Bright agreed to furnish all labor, material, equipment, services and

supplies required for a complete job of Earthwork, as specifically described in the

exhibit A.1, “in strict accordance with the project plans, specifications, notes, codes,

ordinances, manufacturers’ recommendations and all applicable local, state and

federal regulations.” Pogue agreed to pay Bright for described work and materials,

and Bright agreed to accept, the sum of $945,000.00. Exhibit A.1 included section

31A, which referenced the earthwork sections of the plans and specifications. Line –4– item 57 had the same language as item 57 in the revised notice to proceed. The

subcontract represented “the entire and integrated Agreement between the parties

and supersede[d] all prior negotiations, representations, or agreements, whether

written or oral.”

Bright began its work in June 2016. Mike Lipka, Bright’s field superintendent,

testified that on June 21, Lee Johnson, the testing engineer onsite, instructed them to

dig through a thin layer of hardpan to get to hard shale. Hardpan is a mix of clay and

shale that is softer than actual shale limestone. Bright contends the geotechnical

report did not accurately reflect the depth of the top of limestone and it was required

to excavate an additional two feet or more beyond the depths it anticipated based on

the boring logs. Bright claims this was beyond the scope of work reflected in item

57 and caused Bright to incur over $325,000 in expenses.

On July 14, 2016, Bright’s senior estimator, Ken Swayze, e-mailed Pogue’s

project manager, Landon Kids, requesting a meeting to discuss overages on the

project. Swayze stated that Bright had “gone over roughly 35% on both haul off and

select fill due to rock being deeper than indicated on borings.” After reviewing the

plans and specifications, Kids determined that the work Bright performed was within

its scope of work under the contract and a change order was not warranted. Pogue

also claimed that a request for a change order was not timely because Bright

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
David J. Sacks, P.C. v. Haden
266 S.W.3d 447 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Dealers Electrical Supply Co. v. Scoggins Construction Co.
292 S.W.3d 650 (Texas Supreme Court, 2009)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd.
940 S.W.2d 587 (Texas Supreme Court, 1996)
Guaranty Bank v. Lone Star Life Insurance Co.
568 S.W.2d 431 (Court of Appeals of Texas, 1978)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)
Sun Oil Co. (Delaware) v. Madeley
626 S.W.2d 726 (Texas Supreme Court, 1981)
Pain Control Institute, Inc. v. Geico General Insurance Company
447 S.W.3d 893 (Court of Appeals of Texas, 2014)
Lewis v. East Texas Finance Co.
146 S.W.2d 977 (Texas Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bright-excavation-inc-v-pogue-construction-co-lp-and-hartford-fire-texapp-2020.