Bridge Gap Engineering, LLC v. American Pfeiffer Corp.

CourtCourt of Appeals of Iowa
DecidedOctober 1, 2025
Docket24-0524
StatusPublished

This text of Bridge Gap Engineering, LLC v. American Pfeiffer Corp. (Bridge Gap Engineering, LLC v. American Pfeiffer Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridge Gap Engineering, LLC v. American Pfeiffer Corp., (iowactapp 2025).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 24-0524 Filed October 1, 2025

BRIDGE GAP ENGINEERING, LLC, a Pennsylvania limited liability company, on its own behalf and as assignee of MISSOURI CEMENT, L.L.C. d/b/a CONTINENTAL CEMENT COMPANY, L.L.C., Plaintiff-Appellant,

vs.

AMERICAN PFEIFFER CORPORATION, a Pennsylvania corporation d/b/a CHRISTIAN PFEIFFER AMERICA and CHRISTIAN PFEIFFER MASCHINENFABRIK, GMBH, Defendants-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Scott County, John D. Telleen,

Judge.

An engineering firm appeals the district court’s award of damages on

remand from a summary judgment ruling. AFFIRMED.

James S. Zmuda (argued) and Keisha N. Douglas of Califf & Harper, P.C.,

Moline, Illinois, for appellant.

Ian J. Russell (argued), Grace E. Mangieri, and Jenny L. Juehring of Lane

& Waterman, LLP, Davenport, for appellees.

Heard at oral argument by Greer, P.J., and Badding and Chicchelly, JJ.

Telleen, S.J., takes no part. 2

BADDING, Judge.

When this case was first before our court on appeal, the district court had

awarded Bridge Gap Engineering $6,635,617.62 in damages from an uncontested

motion for summary judgment in its suit against Christian Pfeiffer for breach of

contract, negligent misrepresentation, and fraud.1 In that appeal, we reversed the

court’s denial of Christian Pfeiffer’s motion to reconsider the damage award and

remanded for the court to decide whether a “liquidated-damages provision applies

to Bridge Gap’s causes of action and to enter a summary judgment order with the

appropriate award of damages.” Bridge Gap Eng., LLC v. Am. Pfeiffer Corp.,

No. 21-1966, 2022 WL 3053290 (Iowa Ct. App. Aug. 3, 2022).

Consistent with that direction, the district court issued a remand decision

finding the liquidated-damage provision applied and reducing Bridge Gap’s

damage award to $114,750. Bridge Gap appeals, claiming the provision does not

apply and, even if it does, the court miscalculated its damages. Finding no error

of law, we affirm.

I. Background Facts and Proceedings

As we explained in the first appeal, in February 2018, Bridge Gap

contracted with Continental Cement Company, L.L.C. to upgrade the company’s

Davenport cement plant by installing a new high-efficiency separator from

Christian Pfeiffer. The total contract price that Continental owed Bridge Gap was

$6,453,500, later increased through a change order to $6,770,935. The next

1 Bridge Gap sued both American Pfeiffer Corporation, which is based in Pennsylvania, and its manufacturing parent company in Germany—Christian Pfieffer Maschinenfabrik GmbH. As we did in the first appeal, we will refer to these defendants collectively as Christian Pfeiffer. 3

month, Bridge Gap submitted a purchase order to Christian Pfeiffer to buy the

separator for $765,000. There were three attachments to the purchase order: (1) a

fine-print “terms and conditions for purchase of goods and services”; (2) Exhibit A,

a “Document List for HES Project in Davenport IA” from Bridge Gap’s underlying

contract with Continental; and (3) Exhibit B, titled “Performance Guarantee,” which

was also from the Bridge Gap–Continental contract.

The first page of the purchase order stated, “Equipment performance to

comply with previously agreed guarantees which are part of the final contract

included as ‘Exhibit B.’” Section a.3 of Exhibit B set out the required performance

guarantees,2 while section a.4 laid out “damages for deficient performance.”

Paragraph 6 of section a.4, titled “Total Damages,” provided the following damage

limitations:

NEITHER THE CONTRACTOR NOR OWNER SHALL BE LIABLE UNDER THE CONTRACT OR UNDER ANY CAUSE OF ACTION RELATED TO THE SUBJECT MATTER OF THIS CONTRACT, WHETHER IN CONTRACT, WARRANTY, TORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, PRODUCTS LIABILITY, PROFESSIONAL LIABILITY, INDEMNITY, CONTRIBUTION OR ANY OTHER CAUSE OF ACTION, FOR AMOUNTS IN EXCESS OF THIRTY PERCENT (30%) OF THE CONTRACT PRICE (AS MAY BE ADJUSTED BY CHANGE ORDER); PROVIDED, HOWEVER, NOTWITHSTANDING THE FOREGOING, THE LIMITATION OF LIABILITY SET FORTH IN THIS SECTION (A) SHALL NOT: (i) APPLY IN THE EVENT OF THE CONTACTOR’S OR OWNER’S WILLFUL MISCONDUCT OR GROSS NEGLIGENCE; OR (ii) INCLUDE THE PAYMENT OF PROCEEDS UNDER ANY INSURANCE POLICY SPECIFIED IN THE CONTRACT.

SUBJECT TO SECTION a.4 OF EXHIBIT B, THE CONTRACTOR’S MAXIMUM LIABILITY TO THE OWNER FOR PERFORMANCE LIQUIDATED DAMAGES IS 15% OF THE CONTRACT PRICE IN THE AGGREGATE.

2 One guarantee promised to increase cement production by 17.4 percent, while

the other promised to decrease power consumption by 10.7 percent. 4

REGARDLESS OF ANY OTHER PROVISION OF THE CONTRACT, THE CONTRACTOR AND OWNER SHALL NOT BE RESPONSIBLE OR HELD LIABLE TO THE OTHER PARTY FOR ANY LIABILITY FOR LOSS OF PROFITS, LOSS OF REVENUE, LOSS OF PRODUCT, LOSS OF CUSTOMERS, UNABSORBED OVERHEAD, HOME OFFICE OVERHEAD, ADDITIONAL INTEREST OR FINANCE CHARG[E]S OR BUSINESS INTERRUPTION OR FOR ANY TYPE OF CONSEQUENTIAL, PUNITIVE, SPECIAL, EXEMPLARY OR INCIDENTAL DAMAGES, ARISING FROM ANY CAUSE WHATSOEVER, WHETHER OR NOT SUCH LOSS OR DAMAGE IS BASED IN CONTRACT, WARRANTY, TORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, INDEMNITY OR OTHERWISE.

After the separator was installed, Bridge Gap alleged the finish mill system

at Continental’s plant failed to conform to the required performance guarantees set

out in Exhibit B to the purchase order. So Bridge Gap, on its own behalf and as

assignee of Continental, sued Christian Pfeiffer for breach of contract, negligent

misrepresentation, and fraud, with a demand for $7,000,000 in damages.

Bridge Gap moved for summary judgment on all three of its claims in

August 2021. Christian Pfeiffer failed to file a resistance. The district court

accordingly set a hearing on the motion, noting that Bridge Gap had not alleged “a

sum certain for judgment.” At the unreported hearing in November, Bridge Gap

submitted several exhibits on damages, including a breakdown of its requested

damages, totaling $6,635,617.62. The breakdown did not state whether the

damages sought were for breach of contract, negligent misrepresentation, or fraud.

After the hearing, the court entered a ruling for Bridge Gap:

On the issue of damages for Plaintiff’s Motion for Summary judgment, the court received affidavits and exhibits into evidence without objection from Defendants. The court finds Plaintiff is entitled to damages in the total amount of $6,635,617.62 as detailed in Exhibit 4. Judgment is entered granting Plaintiff’s Motion for 5

Summary judgment as Defendants never resisted the motion and still have not done so.

Christian Pfeiffer filed a motion under Iowa Rule of Civil Procedure 1.904(2), asking

the court to reconsider the damage award and arguing that the liquidated-damages

provision in Exhibit B to the purchase order applied to limit Bridge Gap’s recovery

to fifteen percent of the total contract price. The court denied the motion, finding it

was “improper now for Defendants to claim there is additional evidence supporting

a different amount of damages.”

On Christian Pfeiffer’s appeal from that ruling, we determined the provision

was not new evidence, reasoning:

Indeed, a contract cannot be new evidence if it underlies the dispute. Here, the district court relied on the performance guarantees when entering judgment in Bridge Gap’s favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGough v. Gabus
526 N.W.2d 328 (Supreme Court of Iowa, 1995)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Hofmeyer v. Iowa District Court for Fayette County
640 N.W.2d 225 (Supreme Court of Iowa, 2001)
Revere Transducers, Inc. v. Deere & Co.
595 N.W.2d 751 (Supreme Court of Iowa, 1999)
Iowa Fuel & Minerals, Inc. v. Iowa State Board of Regents
471 N.W.2d 859 (Supreme Court of Iowa, 1991)
Holcomb v. Hoffschneider
297 N.W.2d 210 (Supreme Court of Iowa, 1980)
Mark Peak v. Ellis Adams and Rachel Adams
799 N.W.2d 535 (Supreme Court of Iowa, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Bridge Gap Engineering, LLC v. American Pfeiffer Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridge-gap-engineering-llc-v-american-pfeiffer-corp-iowactapp-2025.