Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC

CourtDistrict Court, S.D. New York
DecidedMarch 31, 2021
Docket7:19-cv-09764
StatusUnknown

This text of Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC (Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC, (S.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK

BRIAN TREMATORE PLUMBING & HEATING, INC.,

Plaintiff, No. 19-CV-9764 (KMK) v. OPINION & ORDER WALSH CONSTRUCTION GROUP, LLC, et al.,

Defendants.

Appearances:

David Russell Wise, Esq. Mackey Butts & Wise Millbrook, NY Counsel for Plaintiff

Joshua E. MacKey, Esq. Rivkin Radler LLP Poughkeepsie, NY Counsel for Plaintiff

James Joseph Barriere, Esq. Chad Justin Caplan, Esq. Hinckley Allen Snyder, LLP Albany, NY Counsel for Defendants

KENNETH M. KARAS, District Judge:

Brian Trematore Plumbing & Heating, Inc. (“Plaintiff”) brings this Action against Walsh Construction Group, LLC and Consigli Construction Co., Inc. (“Defendants”), alleging breach of a construction subcontract, quantum meruit, negligent misrepresentation, trust fund diversion, cardinal change, and constructive contract rescission. (Second Am. Compl. (“SAC”) (Dkt. No. 16).) Before the Court is Defendants’ Motion To Dismiss (the “Motion”) pursuant to Federal Rule of Civil Procedure 12(b)(6). (Not. of Mot. (Dkt. No. 19).) For the reasons that follow, the Motion is granted in part and denied in part. I. Background A. Factual Background The following facts are taken from Plaintiff’s Second Amended Complaint (“SAC”).

They are assumed to be true for purposes of adjudicating the instant Motion. This dispute relates to the construction of a medical center in Poughkeepsie, NY (the “Project”). (SAC ¶¶ 1, 10.) Defendants have contracted to be construction managers of the Project (pursuant to the “Prime Contract”), which is owned by Nuvance Health Inc. (the “Owner”). (Id. ¶ 9.) On January 13, 2017, Plaintiff subcontracted with Defendants (pursuant to the “Subcontract”) to install plumbing at the Project for $17,895,000, excluding amounts related to change work orders. (Id. ¶¶ 8, 13.)1 Plaintiff alleges seven causes of action. (See generally id.) Defendants move to dismiss only three of them: breach of contract due to defective design, quantum meruit, and negligent

misrepresentation. With regard to its defective design claim, Plaintiff alleges that CallisonRTKL (“CRTKL”) designed the project. (Id. ¶ 22.) CRTKL provided its design to the Owner, which provided the design to Defendants. (Id. ¶¶ 18, 22.)2 Per the Subcontract, the Project design was to be a certain level of development known as LOD300. (Id. ¶ 20.) “From the very outset of

1 The scope of Plaintiff’s work increased after the Owner announced on February 7, 2018 that it planned to build an eight-floor building rather than a seven-floor building. (SAC ¶¶ 12, 14.)

2 Defendants did not provide this design to Plaintiff until after Plaintiff had signed the Subcontract. (Id. ¶ 19.) work on the Project,” Plaintiff realized that the level of development for the design “was not as promised in the Subcontract,” and an independent expert confirmed this view. (Id. ¶¶ 21, 28– 30.) The design was riddled with defects. For example, water and medical gas piping did not fit in the allocated space for large sections of the Project, (id. ¶ 31); the sanitary pipe outlet at the base of each of the 284 patient room toilets was directly above structural steel framing, (id.

¶¶ 32–33); the design had no ionization system to prevent legionella, (id. ¶¶ 37–39); HVAC systems and electrical components were improperly located, (id. ¶ 54); and other mechanical, electrical, and carpentry work interfered with installing headwalls and gas service outlet boxes and panels in patient rooms, (id. ¶¶ 56, 58). In addition, water was not on site until after August 9, 2019, requiring Plaintiff to perform smoke rather than water testing on the plumbing system, which caused delay and further expense. (Id. ¶¶ 41, 55.) Plaintiff further alleges that Defendants wastefully instructed it to use an unnecessarily difficult route for canopy drains. (Id. ¶¶ 49–51.) It further alleges that Defendants failed to adequately respond to Plaintiff’s notice of design defects, including the toilet outlets located above the structural steel framing, (id. ¶ 35), and the

interference of mechanical, electrical, and carpentry work with installing headwalls and gas service outlet boxes and panels, (id. ¶ 57). With regard to its quantum meruit claim, Plaintiff alleges that, due to the Project’s defective design, Plaintiff submitted 109 change orders. (Id. ¶¶ 42–43.) Defendants failed to approve many of these change orders. (Id. ¶ 44.) Plaintiff lists five unapproved change orders related to supply piping clarifications, damage to the framing podium and framing tower, relocation of 2-inch waste risers and other piping and fittings, and other changes. (Id. ¶¶ 45, 79.) Plaintiff performed this work, which it values at $363,332.93, even though the change orders are unapproved and unresolved, and thus not incorporated into the Subcontract. (Id. ¶¶ 77–78, 80– 81.)3 With regard to its negligent misrepresentation claim, Plaintiff alleges that Defendants negligently misrepresented the Project’s design, sequencing, scheduling, and coordination, causing Plaintiff damage. (Id. ¶ 92.)

Plaintiff alleges four other causes of action. It alleges breach of contract due to improper back charges and cuts of $13,278,432. (Id. ¶ 66.) For example, Defendants inappropriately cut an invoice submitted by Plaintiff for hardware, including shower diverters, (id. ¶¶ 67–68), and back charged Plaintiff for fireproofing, (id. ¶ 69). These back charges were caused by Defendants’ poor project planning and management, including their failure to timely reply to the 390 requests for information (“RFIs”) submitted by Plaintiff to Defendants. (Id. ¶¶ 62, 64–65.) This failure threw off the sequencing of Plaintiff’s work, and prevented it from completing certain work. (Id. ¶¶ 70, 73–74.) Plaintiff alleges that Defendants diverted $5,469,126.07 of funds owed to it, in violation of the New York State Lien Law, (id. ¶¶ 93–111), that Defendants’

unanswered work orders and the inadequate level of design amounted to a cardinal change, (id. ¶¶ 112–22), and that the Subcontract was constructively rescinded in part because Plaintiff never received a LOD300 level of design as it required, (id. ¶¶ 123–40). Plaintiff seeks damages, costs, and attorneys’ fees, additional relief related to its cause of action pursuant to the New York State Lien Law, and interest. (Id. at 21–23.)4

3 Plaintiff alleges that Defendants have failed to approve several additional change orders, including related to an ionization system, (id. ¶ 37), and a triple reinstallation of pipe hangers, (id. ¶ 53). It is not clear whether these unapproved change orders are among the five included in those mentioned previously. (See id. ¶¶ 45, 79.)

4 Here the Court refers to the ECF-generated page numbers in the upper right-hand corner of the page. B. Procedural Background While Plaintiff’s initial Complaint is dated October 22, 2019, it was filed on October 23, 2019. (Dkt. No. 1.) Plaintiff filed its First Amended Complaint a month later, on November 22, 2019. (Dkt. No. 9.) On December 17, 2019, Defendants submitted a pre-motion letter seeking leave to file a motion to dismiss Plaintiff’s defective design, quantum meruit, and negligent

misrepresentation claims. (Dkt. No. 10.) Plaintiff responded by letter dated December 19, 2019, (Dkt. No. 13), and the Court ordered a pre-motion conference, (Dkt. No. 15). At the February 6, 2020, pre-motion conference, the Court provided Plaintiff one week to file a second amended complaint. (See Dkt. (minute entry for Feb. 6, 2020).) Plaintiff complied, filing its SAC on February 13, 2020. (SAC.) On February 19, 2020, Defendants filed a letter requesting that the SAC be struck or, in the alternative, that the Court order a briefing schedule on their Motion To Dismiss. (Dkt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Halebian v. Berv
644 F.3d 122 (Second Circuit, 2011)
Parker Realty Group, Inc. v. Petigny
929 N.E.2d 387 (New York Court of Appeals, 2010)
Air Atlanta Aero Engineering Ltd. v. SP Aircraft Owner I, LLC
637 F. Supp. 2d 185 (S.D. New York, 2009)
Triangle Sheet Metal Works, Inc. v. JAMES H. MERRITT & CO.
588 N.E.2d 69 (New York Court of Appeals, 1991)
Crawford v. Franklin Credit Management Corp.
758 F.3d 473 (Second Circuit, 2014)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Beach v. Touradji Capital Management L.P.
85 A.D.3d 674 (Appellate Division of the Supreme Court of New York, 2011)
Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.
219 A.D.2d 467 (Appellate Division of the Supreme Court of New York, 1995)
Aviv Construction, Inc. v. Antiquarium, Ltd.
259 A.D.2d 445 (Appellate Division of the Supreme Court of New York, 1999)
Duane Thomas LLC v. 62 Thomas Partners, LLC
300 A.D.2d 52 (Appellate Division of the Supreme Court of New York, 2002)
Marshall v. Hyundai Motor America
51 F. Supp. 3d 451 (S.D. New York, 2014)
Nielsen v. Rabin
746 F.3d 58 (Second Circuit, 2014)
Lenard v. Design Studio
889 F. Supp. 2d 518 (S.D. New York, 2012)
Sikhs for Justice v. Nath
893 F. Supp. 2d 598 (S.D. New York, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brian-trematore-plumbing-heating-inc-v-walsh-construction-group-llc-nysd-2021.