Brent L. Mills, Inc. v. Katsamakis

CourtSuperior Court of Delaware
DecidedJanuary 18, 2024
DocketN23C-05-237 MAA CCLD
StatusPublished

This text of Brent L. Mills, Inc. v. Katsamakis (Brent L. Mills, Inc. v. Katsamakis) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brent L. Mills, Inc. v. Katsamakis, (Del. Ct. App. 2024).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

BRENT L. MILLS, INC., ) ) Plaintiff, ) C.A. No. N23C-05-237 MAA CCLD ) v. ) ) BASIL KATSAMAKIS, QUAD ) PARTNERS III-A-LP, and ) REGINALD MOORE, ) ) Defendants. )

Submitted: October 17, 2023 Decided: January 18, 2024

Upon Defendants’ Motion to Dismiss: GRANTED.

MEMORANDUM OPINION

Jonathan M. Stemerman, Esquire (Argued), of ARMSTRONG TEASDALE LLP, Wilmington, Delaware, Attorney for Plaintiff.

Jason C. Jowers, Esquire, and Sarah T. Andrade, Esquire, of BAYARD, P.A., Wilmington, Delaware, and Jordan D. Weiss, Esquire (Argued), of GOODWIN PROCTER LLP, New York, New York, Attorneys for Defendants.

Adams, J.

1 I. INTRODUCTION

This action arises out of a Stock Purchase Agreement between Plaintiff and

Defendants regarding Plaintiff’s acquisition of all the shares in non-party Education

Management, Inc. (the “Company”). The remaining claim in this action is a fraud

claim relating to alleged material representations and omissions about the costs and

timeline of a construction project in connection with Plaintiff’s acquisition of the

Company. Specifically, Plaintiff alleges it only learned after closing that the

construction project was delayed and more expensive than represented.

Defendants move to dismiss, arguing Plaintiff’s remaining claim lacks

particularity, a showing of known falsity, and reasonable reliance. For the following

reasons, the Court finds that Plaintiff fails to state a claim. The Court, therefore,

grants Defendants’ Motion to Dismiss.

II. FACTS1

A. THE AMENDED AND RESTATED STOCK PURCHASE AGREEMENT

On March 3, 2022, Plaintiff Brent L. Mills, Inc. (“BMI” or “Plaintiff”) entered

into an Amended and Restated Stock Purchase Agreement (“the Agreement”)2 with

1 The facts are drawn from the Complaint and the exhibit attached thereto, the Amended and Restated Stock Purchase Agreement (Ex. A). The facts outlined in this opinion are limited to those related to the Fraud in the Inducement claim. 2 The parties originally executed a Stock Purchase Agreement (the “Original Agreement”) on October 27, 2021. Compl. ¶ 11. The transaction outlined in the Original Agreement, however, faced pushback and complications from regulators and accreditors, thereby causing the parties to re-evaluate the structure of the transaction. Id. ¶ 12. 2 Defendants Basil Katsamakis (“Katsamakis”), Reginald Moore (“Moore”), and

Quad Partners III-A-LP (“Quad”) (collectively “the Sellers” or “Defendants”) to

acquire all of the shares in non-party Education Management, Inc. (the

“Company”).3 The Agreement closed on April 26, 2022 (the “Closing”), with BMI

paying $12,342,884 to the Sellers.4

B. ACTIONS AND EVENTS PRIOR TO THE CLOSING

The Company is engaged in operating Blue Cliff College, an accredited career

college that offers education programs in a variety of fields, including massage

therapy, cosmetology, and clinical medical assisting.5 Blue Cliff College offers both

online and in-person classes at several campus locations, including Metairie,

Louisiana; Alexandria, Louisiana; Lafayette, Louisiana; and Gulfport, Mississippi.6

At the time of the Agreement’s negotiation and execution, all Parties

understood that Blue Cliff College was “in the process of planning for and

performing” a construction project for the building of the Blue Cliff College’s

Metairie, Louisiana campus (the “Campus construction”).7 The Sellers “repeatedly

made representations to BMI regarding the timeline and cost for the Campus

construction.”8 Moore and Katsamakis “represented to BMI that the Campus

3 Id. ¶¶ 7, 10, 13. 4 Id. ¶ 15. 5 Id. ¶ 8. 6 Id. ¶ 9. 7 Id. ¶ 17. 8 Id. ¶ 18. 3 construction would be completed for a total cost of $900,000 and that the landlord

for the Campus property had agreed to provide $900,000 in tenant improvement

credits, resulting in a zero-dollar net spend” for the Campus construction.9

Additionally, Sellers represented that the Campus construction would be complete

and ready for use by July 2022.10

BMI alleges that Sellers’ representations were “known to be false prior to

Closing” and the Sellers “failed to share that information with BMI” so the Campus

construction costs were “far different” than represented.11 As evidence of falsity,

BMI points to an undated verbal estimate of $900,000 from a contractor with whom

Moore and Katsamakis had previously worked.12 This contractor allegedly “insisted

on providing no written estimates or billing records, instead electing to be paid

weekly in cash sums always totaling less than $10,000—a dubious practice to which

Defendants acquiesced.”13

By February 4, 2022, Moore and Katsamakis were aware that “reputable and

professional contractors were estimating—in writing—that the Campus construction

work could cost $1,645,257.”14 By March 15, 2022, the original contractor became

“unresponsive and was having difficulty in securing workers and/or permits needed

9 Id. ¶ 19. 10 Id. ¶ 20. 11 Id. ¶¶ 23–24. 12 Id. ¶ 25. 13 Id. 14 Id. ¶ 26. 4 to perform even basic demolition work at the Campus[.]”15 Moore and Katsamakis

were aware of these issues and began seeking additional contractors to complete the

Campus construction.16 On April 11, 2022, Moore and Katsamakis received another

written estimate for $1,728,146.17 In the weeks leading up to Closing, internal e-

mails “reveal[ed] that the timing for the Campus construction was significantly

behind—and in fact that no meaningful progress on the construction had even

occurred as of the date of Closing.”18 BMI alleges it was not informed of the

unreliability of the original estimate, the newer and higher estimates, nor that there

were construction delays prior to Closing.19

C. ALLEGED DAMAGES

BMI asserts that as a result of “Sellers’ misrepresentations and omissions,”

Buyer has incurred a minimum of the following losses: (1) “$1,900,000 in additional

construction costs;” (2) “$400,000 in tenancy costs due to the construction delay;”

and (3) “$3,000,000 in lost contribution margin at the Campus location due to lower

student count caused by construction delays.”20 BMI alleges that “it would not have

15 Id. ¶ 27. 16 Id. 17 Id. ¶ 28. 18 Id. ¶ 29. 19 Id. ¶ 30. 20 Id. ¶ 33. 5 proceeded to Closing based upon the financial terms set out in the Agreement” had

it “known the truth regarding the Campus construction cost and timeline.”21

III. PROCEDURAL HISTORY

On May 24, 2023, Plaintiff filed a complaint alleging three counts: (1) Fraud

in the Inducement;22 (2) Unjust Enrichment;23 and (3) Breach of Contract (In the

Alternative).24

On July 18, 2023, Defendants filed a Motion to Dismiss all claims. Briefing

concluded on September 8, 2023. The Court held oral argument on October 17,

2023. On the record, the Court granted the Motion to Dismiss as to Plaintiff’s Unjust

Enrichment claim (Count II) and the Breach of Contract claim (Count III), and

reserved decision on the Fraud in the Inducement claim (Count I).25

IV. STANDARD OF REVIEW

On a motion to dismiss pursuant to Superior Court Civil Rule 12(b)(6), the

Court must: “(1) accept all well pleaded factual allegations as true, (2) accept even

vague allegations as ‘well-pleaded’ if they give the opposing party notice of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re General Motors (Hughes) Shareholder Litigation
897 A.2d 162 (Supreme Court of Delaware, 2006)
Trenwick America Litigation Trust v. Billett
931 A.2d 438 (Supreme Court of Delaware, 2007)
Abry Partners V, L.P. v. F & W Acquisition LLC
891 A.2d 1032 (Court of Chancery of Delaware, 2006)
Trenwick America Litigation Trust v. Ernst & Young, L.L.P.
906 A.2d 168 (Court of Chancery of Delaware, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Brent L. Mills, Inc. v. Katsamakis, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brent-l-mills-inc-v-katsamakis-delsuperct-2024.