GOLDEN, Justice.

J.W. “Jack” Brebaugh (Brebaugh) received injuries on January 6, 1986, while working on a “splicing” procedure on a conveyor belt in an underground coal mine near Hanna, Wyoming. He was employed by Carbon County Coal Company (CCCC), a Colorado general partnership formed by partners Dravo Coal Company (Dravo), a Delaware corporation, and Rocky Mountain Energy Company (RMEC), a Utah corporation.

Although Brebaugh received an award under the provisions of the Wyoming Worker’s Compensation Act through CCCC’s account as a contributing employer, he filed a tort action against Dravo and four supervisory co-employees, seeking to recover money damages for his personal injuries. He appeals from the district court’s order dismissing Dravo under W.R. C.P. 12(b)(6), and from that court’s order granting summary judgment for three of his co-employees.1

We affirm.

The parties agree that the issues are as Brebaugh has stated them:2

I. Did the district court err in granting summary judgment to the co-employee defendants when there existed a genuine issue of material fact concerning culpable negligence?
II. Did the district court err in failing to allow plaintiff to conduct proper voir dire relative to worker’s compensation benefits?
III. Is a corporation-partner who takes on independent duties under a separate management contract with the partnership to be considered an “employer contributing as required by law” under the Wyoming Constitution and statutes so as to acquire immunity under the Worker’s Compensation Act from suit by an employee of the partnership?

FACTS

In CCCC’s mining operation a main conveyor belt carried the mined coal from underground uphill to the surface. The main conveyor belt consisted of three sections designated as U-l, U-2, and U-3. The U-2 belt, on which Brebaugh was working when injured, was fifty-four inches wide and about 2,000 feet long, weighing at least ten pounds or more per foot. Resembling in general appearance an elongated rubber band, the belt rested on a conveyor frame suspended from the ceiling of the mine shaft. The bottom portion of the belt loop was about six to seven feet above the sloping ground. The belt was a series of sections fastened together by mechanical fasteners. The mechanical fastener was held together by a pin inserted through the fastener.

[1131]*1131On occasion CCCC eliminated a mechanical fastener. To do this, CCCC “spliced” the affected belt section. The objective in the “splicing” procedure was to separate the belt at the designated belt section, cut out the mechanical fastener, add more belt if necessary, overlap the loose ends of the belt, and melt together those loose ends by means of a heating device; this last step is called “vulcanizing.” CCCC had available for use a manual, Royalon Vulcanized Splicing Manual, which contained instructions to keep clamps on the belt at all times while making a splice and to keep tension on all of the belt, except for that part of the belt being spliced. With this general orientation in mind, we turn our attention to the facts and circumstances leading up to and surrounding the accident in question.

The accident happened January 6, 1986, several hours into the “graveyard” shift, 12 midnight to 8:00 a.m., the shift Bre-baugh worked. At the start of that shift, appellee Hales, CCCC’s general foreman in charge of the work, assigned appellee Beis-ner, a section foreman, to work on splicing the U-2 belt at a location previously identified by Paul Kehrer, the foreman on the previous shift. Since Beisner had little or no experience with this procedure, Hales considered his assignment as a training exercise. Hales assigned Brebaugh, Has-sel, Cook, and Schriner as crew members under Beisner. Hales chose these crew members based on their prior experience in the mine and with conveyor belts. Although Brebaugh had no prior experience splicing U-belts, he had prior experience splicing smaller section belts. Although modest about his experience, Brebaugh testified that as a production belt man of five years’ experience he was probably the best trained person at CCCC with respect to operation, repairs, and maintenance of section belts. Hassel had vulcanized U-belts about ten times and had both classroom instruction and on-the-job training on the procedure. Cook had received on-the-job training on vulcanizing or splicing U-belts at CCCC and had performed the procedure about three times. Schriner had also received classroom instruction and on-the-job training on the vulcanizing and splicing procedure; he had performed the procedure on U-belts three or four times.

Hales asked appellee Freeman, a shift foreman, who had regularly assigned duties in another section' of the mine, to take Brebaugh’s crew to the designated work area, determine whether enough slack in the belt existed to permit a splice, and report his finding to Hales. Freeman took the crew to the area where the vulcanizing station was set up. They found that the U-2 belt was not centered properly. They worked for several hours trying to pull down slack in the belt using three-ton chain come-alongs. They were not able to pull down any slack. Freeman called Hales and told him they did not have enough slack to make the splice.

Hales told Freeman to go uphill to a fifty-foot section of belt located above the belt drive mechanism and add that section to the belt. Freeman passed that information on to Beisner. According to Hales, that fifty-foot section had been placed there some time previously in expectation of having to add it into the belt at a later date. Hales believed that in late 1984 sections of belt had been added to the U-2 belt at that same location. He believed that three supervisors had been in that area during that operation. The crew then moved their equipment, including come-alongs and clamps, uphill to the location designated by Hales. Freeman told them they were to put the clamps on the belt, pull the pin, and insert the fifty-foot section of belt. Freeman then left to perform his regularly assigned duties in another section of the mine.

At the designated location the crew put clamps on each side of the belt. Hassel and Brebaugh worked on one side of the belt; Cook and Schriner worked on the other. Working on the bottom loop portion of the belt, the crew put clamps both downhill and uphill from the spot on the belt section where the splice was to be made. Attaching the come-alongs to the clamps, they took up the slack until the belt dropped a little where they could remove the pins. After they removed the pins, [1132]*1132they loosened the come-alongs on the downhill side of the splice. They removed the downhill side come-alongs' and clamp, allowing the downhill section of the belt to drop to the ground.

At this point in the operation, Hassel and Brebaugh discussed the substantial tension remaining on the uphill section of belt. According to Brebaugh, Hassel was in charge. As they were discussing what to do, Hales arrived at their work area.- He asked them if they needed belt pins, and Brebaugh answered they needed two. Then Brebaugh asked Hales, “What are we going to do about that upper belt?” Hales replied, “Well, you can take the clamp off and it’ll drop to the ground.” That was the substance of their conversation. Hales was there only a minute or so and he left. Hales testified that he left to attend to another work matter but intended to return to the splicing operation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. William Winney, Jr. v. Michael Troy Jerup
2023 WY 113 (Wyoming Supreme Court, 2023)
Shepherd of the Valley Care Center v. Fulmer
2012 WY 12 (Wyoming Supreme Court, 2012)
Birt v. Wells Fargo Home Mortgage, Inc.
2003 WY 102 (Wyoming Supreme Court, 2003)
Williams v. Mammoth of Alaska, Inc.
890 P.2d 581 (Alaska Supreme Court, 1995)
Huf v. Arctic Alaska Drilling Co.
890 P.2d 579 (Alaska Supreme Court, 1995)
Amrein v. Wyoming Livestock Board
851 P.2d 769 (Wyoming Supreme Court, 1993)
McKennan v. Newman
843 P.2d 602 (Wyoming Supreme Court, 1992)
Morris v. Smith
837 P.2d 679 (Wyoming Supreme Court, 1992)
Stalkup v. State Department of Environmental Quality
838 P.2d 705 (Wyoming Supreme Court, 1992)
Allmaras v. Mudge
820 P.2d 533 (Wyoming Supreme Court, 1991)
Rhoades v. State
813 P.2d 234 (Wyoming Supreme Court, 1991)
Mills v. Reynolds
807 P.2d 383 (Wyoming Supreme Court, 1991)
STATE EX REL. WORKERS'COMP. v. Brown
805 P.2d 830 (Wyoming Supreme Court, 1991)
State ex rel. Wyoming Workers' Compensation Division v. Brown
805 P.2d 830 (Wyoming Supreme Court, 1991)
Cockburn v. Terra Resources, Inc.
794 P.2d 1334 (Wyoming Supreme Court, 1990)
Pool v. Dravo Coal Co.
788 P.2d 1146 (Wyoming Supreme Court, 1990)
Brebaugh v. Hales
788 P.2d 1128 (Wyoming Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
788 P.2d 1128, 1990 Wyo. LEXIS 28, 1990 WL 26958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brebaugh-v-hales-wyo-1990.