Brazos Presbyterian Homes, Inc. v. Thompson Hancock Witte & Associates, Inc.Case remanded to the 80th District Court of Harris County, Texas.

CourtDistrict Court, S.D. Texas
DecidedSeptember 27, 2022
Docket4:21-cv-03387
StatusUnknown

This text of Brazos Presbyterian Homes, Inc. v. Thompson Hancock Witte & Associates, Inc.Case remanded to the 80th District Court of Harris County, Texas. (Brazos Presbyterian Homes, Inc. v. Thompson Hancock Witte & Associates, Inc.Case remanded to the 80th District Court of Harris County, Texas.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brazos Presbyterian Homes, Inc. v. Thompson Hancock Witte & Associates, Inc.Case remanded to the 80th District Court of Harris County, Texas., (S.D. Tex. 2022).

Opinion

September 27, 2022 Nathan Ochsner, Clerk UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION

BRAZOS § CIVIL ACTION NO. PRESBYTERIAN § 4:21-cv-03387 HOMES INC, § Plaintiff, § § § vs. § JUDGE CHARLES ESKRIDGE § § THOMAS HANCOCK § WITTE & ASSOCIATES, § Defendant. § OPINION AND ORDER GRANTING REMAND The motion by Plaintiff Brazos Presbyterian Homes Inc to remand is granted. Dkt 11. 1. Background This is an action for breach of contract and negligence by Plaintiff Brazos Presbyterian Homes Inc against Defendant Thompson Hancock Witte & Associates Inc. Also involved in a related action is Lendlease US Construction. These parties are referred to as BPH, THW, and Lendlease. BPH is a Texas corporation that owns and operates a senior-living community in Houston, Texas. Dkt 1-3 at 2– 3. It contracted with THW and Lendlease for design and construction on its campus to renovate an existing building and add an additional tower. THW is a Georgia corporation. Dkt 1 at 3. Lendlease appears to be a corporation in North Carolina and Florida. Dkt 14 at 3 n 2; see also Dkt 11-2 (referenced as “foreign” to Texas). BPH eventually brought two actions in state court with respect to the subject project. The original action remains pending in state court. This action spun off from the original and was removed only as to one particular claim against THW. The amounts in controversy in each action plainly exceeds $75,000. BPH and TWH don’t dispute the above. But they hotly contest how the following procedural history impacts THW’s right to remove the action here. November 22, 2016. As the project neared completion, BPH brought action in state court against Lendlease asserting (among other things) failure by Lendlease to construct the project as specified. See Dkt 11 at 2. October 17, 2018. BPH amended its petition to assert flood-related claims against Lendlease, while adding THW to assert a claim for a defective design that allegedly caused the project to flood during Hurricane Harvey in August 2017. Dkt 13-2; see also Dkt 11 at 2–3. THW didn’t exercise its then-available right to remove the action. October 5, 2020. BPH obtained leave to further amend the petition after discovering alleged design-related latent defects in the project. Dkt 11-1. January 1, 2021. BPH filed a third amended petition asserting claims against THW for design-related latent defects. But it didn’t include a Chapter 150 Certificate of Merit as required under Texas law. Dkt 11-2; see also Texas Civil Practices & Remedies Code § 150.002. January 19, 2021. THW moved to dismiss the design- related latent defect claims on the basis that BPH failed to include the required certificate of merit. Dkt 11-4 at 7–8. February 10, 2021. BPH sought to include the required certificate of merit when filing a fourth amended petition. Dkt 11-3. May 17, 2021. The state court heard argument on THW’s motion to dismiss. See Dkt 11 at 5. September 23, 2021. The state court granted THW’s motion and dismissed the design-related latent defect claims asserted by BPH without prejudice. All other claims asserted against THW remained, being the earlier- asserted claims for flood damage due to defective design. Dkt 13-3; see also Dkt 11 at 5. October 13, 2021. BPH initiated this action in state court to reassert the dismissed design-related latent defect claims against THW. This time, it included the required certificate of merit. Dkt 1-3 at 1–7, 47–69. BPH that same day also moved to consolidate this action with the original action. Dkt 11-7 at 1–10. October 15, 2021. THW removed this action. Dkt 1. November 10, 2021. After removal, THW asserted third-party claims in this action against two of its subcontractors, Uzun & Case LLC (a Georgia corporation) and Barrett, Woodyard & Associates Inc (a Georgia corporation). Dkts 9 & 10. November 12, 2021. BPH filed a motion to remand. Dkt 11. BPH and THW provided a joint notice of settled claims on August 18, 2022. Dkt 26. They advise that: o As to settlements in the state court action, all remaining claims between BPH and THW were resolved in mediation. o As to settlements in this action, (i) BPH, THW, and Uzun & Case resolved certain claims regarding foundation and a brick façade, and (ii) THW resolved all claims against Uzun & Case, who has been dismissed from this action. o As to claims remaining in the state court action, there are (i) a breach-of-contract claim for construction defects between BPH and Lendlease, as specified in a supporting chart; (ii) third-party claims for indemnity and defense by Lendlease against its various subcontractors for such construction defects; (iii) claims related to Lendlease’s lien on the project; and (iv) Lendlease’s counterclaims, including the Texas Prompt Pay Act and quantum meruit. o As to claims remaining in this action, there are (i) claims by BPH against THW for breach of contract and professional negligence, and (ii) though unstated in the notice, third-party claims by THW against Barrett Woodyard. 2. Legal standard A case may be removed to federal court “if there is complete diversity of citizenship and the amount in controversy is greater than $75,000 exclusive of interests and costs.” Allen v Walmart Stores LLC, 907 F3d 170, 183 (5th Cir 2018), citing 28 USC §§ 1332, 1441. The process by which a defendant may properly remove an action from state court is governed by 28 USC § 1446. Section 1446(b)(1) provides, with emphasis added: The notice of removal of a civil action or proceeding shall be filed within 30 days after the receipt by the defendant, through service or otherwise, of a copy of the initial pleading setting forth the claim for relief upon which such action or proceeding is based, or within 30 days after the service of summons upon the defendant if such initial pleading has then been filed in court and is not required to be served on the defendant, whichever period is shorter. The removing party bears the burden of showing that subject-matter jurisdiction exists, and that the removal procedure was properly followed. Manguno v Prudential Property & Casualty Insurance Co, 276 F3d 720, 723 (5th Cir 2002). “If at any time before final judgment it appears that the district court lacks subject matter jurisdiction, the case shall be remanded.” 28 USC § 1447(c). The Fifth Circuit holds, “Because removal raises significant federalism concerns, the removal statute is strictly construed ‘and any doubt as to the propriety of removal should be resolved in favor of remand.’” Gutierrez v Flores, 543 F3d 248, 251 (5th Cir 2008), quoting In re Hot-Hed Inc, 477 F3d 320, 323 (5th Cir 2007); see also Hicks v Martinrea Automotive Structures (USA) Inc, 12 F4th 511, 515 (5th Cir 2021). 3. Analysis BPH contends that remand is proper on its design- related latent defect claims against THW because (i) removal was untimely as measured from BPH’s first assertion of the claims in its original action; (ii) THW waived its right to removal by seeking dismissal of the claims in state court; and (iii) THW destroyed any potential for complete diversity when it added the third-party defendants. Dkt 11. THW asserts to the contrary that (i) removal was timely, as it occurred only two days after BPH initiated its second action; (ii) any waiver of the right to remove due to litigation conduct occurred only in the original action; and (iii) only diversity as between THW and BPH is relevant to subject matter jurisdiction. Dkt 13. a. Timeliness of removal BPH contends that THW should have removed this action (if at all) within thirty days of service of BPH’s third amended petition in the original state-court action on January 1, 2021. Dkt 11 at 7. THW contends that the third amended petition isn’t the relevant initial pleading for removal purposes, arguing instead in favor of the one that began this action ten months after the design-related latent defect claims were dismissed without prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Heublein Inc.
227 F.3d 236 (Fifth Circuit, 2000)
Manguno v. Prudential Property & Casualty Insurance
276 F.3d 720 (Fifth Circuit, 2002)
State National Insurance v. Yates
391 F.3d 577 (Fifth Circuit, 2004)
Gutierrez v. Flores
543 F.3d 248 (Fifth Circuit, 2008)
Shamrock Oil & Gas Corp. v. Sheets
313 U.S. 100 (Supreme Court, 1941)
Caterpillar Inc. v. Lewis
519 U.S. 61 (Supreme Court, 1996)
In Re Hot-Hed Inc.
477 F.3d 320 (Fifth Circuit, 2007)
Gore v. Stenson
616 F. Supp. 895 (S.D. Texas, 1984)
Landry v. Cross Country Bank
431 F. Supp. 2d 682 (S.D. Texas, 2003)
Korzinski v. Jackson
326 F. Supp. 2d 704 (E.D. North Carolina, 2004)
Jacko v. Thorn Americas, Inc.
121 F. Supp. 2d 574 (E.D. Texas, 2000)
Deleese Allen v. Walmart Stores, L.L.C.
907 F.3d 170 (Fifth Circuit, 2018)
Lindsey Hoyt v. Lane Construction Corporati
927 F.3d 287 (Fifth Circuit, 2019)
Price v. Food Lion, Inc.
768 F. Supp. 181 (E.D. Virginia, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Brazos Presbyterian Homes, Inc. v. Thompson Hancock Witte & Associates, Inc.Case remanded to the 80th District Court of Harris County, Texas., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brazos-presbyterian-homes-inc-v-thompson-hancock-witte-associates-txsd-2022.