BP Chemicals Inc. v. AEP Texas Company Formerly Known as Central Power and Light Company

CourtCourt of Appeals of Texas
DecidedAugust 3, 2006
Docket13-05-00534-CV
StatusPublished

This text of BP Chemicals Inc. v. AEP Texas Company Formerly Known as Central Power and Light Company (BP Chemicals Inc. v. AEP Texas Company Formerly Known as Central Power and Light Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BP Chemicals Inc. v. AEP Texas Company Formerly Known as Central Power and Light Company, (Tex. Ct. App. 2006).

Opinion



NUMBER 13-05-534-CV



COURT OF APPEALS



THIRTEENTH DISTRICT OF TEXAS



CORPUS CHRISTI - EDINBURG



BP CHEMICALS, INC.

, Appellant,

v.



AEP TEXAS CENTRAL COMPANY FORMERLY KNOWN AS

CENTRAL POWER AND LIGHT COMPANY, Appellee.



On appeal from the 24th District Court

of Calhoun County, Texas.



O P I N I O N


Before Chief Justice Valdez and Justices Yañez and Castillo

Opinion by Justice Castillo



Appellant, BP Chemicals, Inc. ("BP"), appeals from the trial court order denying its motion for summary judgment and granting the motion for summary judgment of appellee, AEP Texas Central Company ("AEP"), formerly known as Central Power and Light Company ("CP&L"). We affirm.

I. Background

BP operates a co-generation facility known as the Green Lake Plant in Calhoun County, Texas. "Co-generation involves the simultaneous production of electrical power and thermal energy, such as heat or steam, usually at an industrial site." Pub. Util. Comm'n v. Gulf States Utils. Co., 809 S.W.2d 201, 203 (Tex.1991). Congress, in order to promote energy conservation, requires electric utilities to purchase co-generated electricity from qualifying facilities, such as the Green Lake Plant, and to provide back-up power to those facilities on a nondiscriminatory basis. See the Public Utility Regulatory Policies Act ("PURPA"), 16 U.S.C.A. § 824a-3 (West 2000).

In 1999, the Texas Legislature passed Senate Bill 7, amending the Public Utility Regulatory Act ("PURA") and deregulating the Texas electricity market. (1) Deregulation required each integrated electric utility to partition itself into three companies: (1) a power generation company, (2) a transmission and distribution provider, and (3) a retail electric provider. (2) The Public Utility Commission of Texas ("PUC") was given jurisdiction over the Texas electricity market, (3) and it closely regulates the transmission component of the industry. (4) Rates for power are now determined by a competitive market. (5)

Texas operates an independent and self-contained electric production and transmission grid; its system operator is the Electric Reliability Council of Texas ("ERCOT"). (6) ERCOT is charged with ensuring system reliability, nondiscriminatory access to the transmission and distribution system, access to market information, and clearance of all market transactions. (7) ERCOT is also required to ensure accurate accounting of electricity production and delivery between generators and wholesale buyers and sellers in the region. (8) In conjunction therewith, "ERCOT Procotols" have been developed which provide the framework for the administration of the Texas electricity market. (9) Utilities are required to abide by the procedures established by ERCOT. See Tex. Util. Code Ann. §39.151(j) (Vernon Supp. 2005); Hammack v. Pub. Util. Comm'n of Tex., 131 S.W.3d 713, 718 (Tex. App.-Austin 2004, pet. denied).

Beginning in 1981, BP and AEP (10) entered into a series of contracts, by which CP&L agreed to take and pay for excess electricity generated at the plant. The parties operated successfully under these contracts until 2001. Because of deregulation, and the need for CP&L to "unbundle" its integrated services into separate companies, notice of cancellation of the contract was provided to BP on November 29, 2001, effective December 21, 2001. CP&L's business was unbundled effective January 1, 2002. Until then, it continued to operate as a utility generating, purchasing, transmitting, and selling electricity to retail customers.

However, beginning in August 2001, CP&L failed to pay BP for power transferred to CP&L by BP at the Green Lake Plant meter (the point of delivery). BP delivered 7,505 megawatt hours ("Mwh") of electricity through the CP&L meters at the Green Lake Plant during August 2001. From September 1 through September 25, 2001, BP delivered 5,591 Mwh of electricity to the meters. The total adjusted avoided energy cost for these two months was $314,920.63 ($206,620.16 plus $108,300.47). (11)

When AEP did not pay for the power delivered during August and September, BP registered with the ERCOT transmission grid to sell its excess power to third parties. BP registered with ERCOT on September 1, 2001, and designated a Qualified Scheduling Entity on September 17, 2001. ERCOT first recognized deliveries from the Green Lake Plant beginning September 26, 2001. On October 1, 2001, BP executed a resource agreement with ERCOT. The difference between the monies BP received for the sale of its power between September 26, 2001, and December 31, 2001, and the monies that would have been due from AEP pursuant to the contracts totals $118, 541.73.

On August 4, 2003, BP brought suit against AEP for breach of contract based on nonpayment for electrical Mwh delivered during August and September, and the additional loss when BP was forced to mitigate its damages and seek alternative purchasers during the remainder of the year 2001. BP included an alternative cause of action for unjust enrichment or assumpsit. AEP's answer to the suit includes the affirmative defenses of failure of consideration (12) and excuse from performance as a result of commercial impracticability, impossibility of performance, and/or frustration of purpose. (13)

The basic facts are undisputed between the parties. BP filed a motion for summary judgment on March 30, 2005, for breach of contract and principal damages in the amount of $433,462.36, plus attorneys fees and pre- and post-judgment interest.

On May 10, 2005, AEP filed its response to BP's motion and its own motion for summary judgment. AEP alleged that BP had failed to timely comply with ERCOT Protocols, including registration and designation of a Qualified Scheduling Entity, and that failure to do so prohibited AEP from either recognizing deliveries from, or transmitting any power from BP's plant on the ERCOT grid for the benefit of either BP or AEP. AEP alleged that while all unbundling did not have to be accomplished until January 1, 2002, the ERCOT Protocols requiring registration and scheduling became effective July 6, 2001.

BP responded to AEP's motion on May 24, 2005, arguing the following: (1) utilities were not required to and CP&L did not unbundle its business activities until January 1, 2002; (2) nothing made it impossible or impractical for BP's deliveries to be received or compensated; and (3) BP's deliveries, being directly through meters at exit of the Green Lake Plant, did not require any "transmission" on the ERCOT grid and, therefore, no ERCOT Protocols were triggered or violated.

A hearing on the motions for summary judgment was held June 1, 2005. (14)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas Commercial Energy v. TXU Energy, Inc.
413 F.3d 503 (Fifth Circuit, 2005)
Mitchell v. Ceazan Tires, Ltd.
153 P.2d 53 (California Supreme Court, 1944)
Reliant Energy, Inc. v. Public Utility Commission of Texas
62 S.W.3d 833 (Court of Appeals of Texas, 2001)
FM Properties Operating Co. v. City of Austin
22 S.W.3d 868 (Texas Supreme Court, 2000)
Branton v. Wood
100 S.W.3d 645 (Court of Appeals of Texas, 2003)
City of Austin v. L.S. Ranch, Ltd.
970 S.W.2d 750 (Court of Appeals of Texas, 1998)
State v. Public Utility Com'n of Texas
883 S.W.2d 190 (Texas Supreme Court, 1994)
Phillips Petroleum Co. v. Texas Commission on Environmental Quality
121 S.W.3d 502 (Court of Appeals of Texas, 2003)
Centex Corp. v. Dalton
840 S.W.2d 952 (Texas Supreme Court, 1992)
TXU Generation Co. v. Public Utility Commission
165 S.W.3d 821 (Court of Appeals of Texas, 2005)
State Farm Fire & Casualty Co. v. S.S.
858 S.W.2d 374 (Texas Supreme Court, 1993)
Southwestern Public Service Co. v. Public Utility Commission of Texas
962 S.W.2d 207 (Court of Appeals of Texas, 1998)
Casso v. Brand
776 S.W.2d 551 (Texas Supreme Court, 1989)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
Hammack v. Public Utility Com'n of Texas
131 S.W.3d 713 (Court of Appeals of Texas, 2004)
Alaniz v. Hoyt
105 S.W.3d 330 (Court of Appeals of Texas, 2003)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
BP Chemicals Inc. v. AEP Texas Company Formerly Known as Central Power and Light Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bp-chemicals-inc-v-aep-texas-company-formerly-know-texapp-2006.