Bowen v. Foust

925 S.W.2d 211, 29 U.C.C. Rep. Serv. 2d (West) 825, 1996 Mo. App. LEXIS 776, 1996 WL 220693
CourtMissouri Court of Appeals
DecidedMay 2, 1996
Docket20320
StatusPublished
Cited by6 cases

This text of 925 S.W.2d 211 (Bowen v. Foust) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowen v. Foust, 925 S.W.2d 211, 29 U.C.C. Rep. Serv. 2d (West) 825, 1996 Mo. App. LEXIS 776, 1996 WL 220693 (Mo. Ct. App. 1996).

Opinion

*212 CROW, Judge.

Plaintiffs, Joe A. Bowen and Mary Bowen, sued Defendant, Bob Foust (doing business as Foust Plumbing, Heating & Cooling), for breach of contract. 1 The contract was made when Plaintiffs accepted Defendant’s bid to sell and install certain heating and cooling equipment at Plaintiffs’ home.

Defendant’s bid specified four “RHEEM 3½ TON HEAT PUMP SYSTEMS” with a “SEER RATING OF 12.” The bid price was $8,159, to be paid “WHEN INSTALLATION IS COMPLETE.”

Plaintiffs pled that after paying Defendant the agreed sum, they discovered the equipment Defendant installed was not the equipment specified in the bid and was “incompatible with the existing system and [did] not operate properly.”

The trial court heard the case without a jury and awarded Plaintiffs a judgment for $8,159, the specified price.

Defendant appeals, insisting the trial court erroneously ruled for Plaintiffs in that: (1) Plaintiffs failed to meet their burden of proof as to damages in that they “offered no evidence of the cost of repairing the defective work, or the diminution in the value of the home,” and (2) Defendant was denied a reasonable opportunity to correct the defects under § 400.2-508, RSMo 1986, a provision of Missouri’s “Uniform Commercial Code— Sales.”

Our review is governed by Rule 73.01(c), Missouri Rules of Civil Procedure (1996), as construed by Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976). The judgment of the trial court will be sustained unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law. Id. at 32[1]. We view the evidence and permissible inferences therefrom in the light most favorable to the judgment, disregarding all contrary evidence and inferences, Mehra v. Mehra, 819 S.W.2d 351, 353[2] (Mo. banc 1991), mindful that credibility of the witnesses and the weight to be given their testimony were matters for the trial court, which was free to believe none, part or all of the testimony of any witness. Herbert v. Hart, 757 S.W.2d 585, 587[1] (Mo. banc 1988).

So viewed, the evidence demonstrates that in early 1993, Plaintiffs’ home had a Carrier heating and cooling system consisting of four outside units and four inside units. Plaintiffs decided to upgrade the system with equipment having a “12 seer rating” to “get more efficiency [so] the house [would] cool and heat better.” Plaintiffs solicited and received bids on the project.

After Defendant’s bid (dated March 24, 1993) was accepted by Plaintiffs, Defendant replaced the four outside units with Rheem units and replaced the coils in the four inside units. Plaintiffs’ daughter, Karen Bowen, a realtor, acted as agent and overseer for Plaintiffs on the project. Karen’s testimony included this:

“Q. Was there any discussion at that time as to whether or not the Rheem units were compatible with the Carrier unit that was inside?
A. Yes, ma’am.
Q. What did [Defendant] say?

A He said they were compatible.”

The record does not reveal when Defendant completed the project. However, Plaintiff Mary Bowen testified that around mid-July, 1993, “the compressor went out.” Defendant removed it and ordered a replacement. Mary’s testimony continued:

“Q. How long did it take you to get another compressor?
A. It took four to six weeks, which was— was the hottest part of the time.
Q. So most of the summer you were without air there?
A. Yes. Uh-huh.
Q. Were there ... any other problems?
*213 A. Yes. The units leaked water all the time, and they frosted up like a Frigidaire would frost up in the house.
[[Image here]]
Q. ... Were there problems with odors in the house?
A. Yes. Uh-huh.
Q.' Dust?
A. Yes.
Q. During this period of time, did ... someone contact Mr. Foust? Did — Did someone come out there?
A. Yes, we called him all the time.
Q. And—
A. Probably about four or five months there and he kept telling us that he didn’t understand ... why the pipes were freezing—
Q. He didn’t know what to do to correct it?
A. Right.”

Sometime that fall (1993) another compressor faded. According to Karen Bowen, the compressor was required for both cooling and heating.

In October, when Plaintiffs began needing heat, they discovered the system generated none. At that point, Defendant had not replaced the second compressor that failed.

In an effort to make the system produce heat, Defendant replaced the four inside units and presented Plaintiffs a bill for $1,400. However, according to Karen Bowen: “[W]e still didn’t have any heat.” Defendant then said “it was [Plaintiffs’] breakers.” Karen testified Plaintiffs engaged an electrician to replace the breakers, which cost “200 and some odd dollars.” Plaintiffs also installed new thermostats. Those measures also proved futile.

Around November 11, 1993, Defendant told Plaintiffs he had the compressor to replace the second one that had faded. However, he warned Plaintiffs it would not be under Rheem’s warranty “if Rheem saw those [units].” Plaintiffs forbade Defendant from installing the compressor.

A few days later, at Karen Bowen’s request, one Mike Johnson, a “heat and air man,” examined the system installed by Defendant. Johnson’s inspection revealed the system “did not have the 12 seer rating.” Karen testified that upon learning this: “I called [Defendant] on the telephone and told him we wanted our money back and for him to come and get his units.”

Asked how cold it was in the house that winter (1993-94), Karen recounted:

“It was cold enough that we put electric heaters in that house, and we heated the bathrooms with those water heaters. We heated — I brought every electric heater I had from my office and — and that I use in rental property and stuff like that for spares. And my dad wore his coat all the time. We stayed covered up with a blanket all the time. And we hauled wood to place in the fireplaces; it was that cold in that house.”

In the spring of 1994, at Karen’s request, Stanley Ray Buffington, a heating and cooling ventilation contractor and Carrier dealer, inspected the equipment installed by Defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Accettura v. Vacationland, Inc.
2019 IL 124285 (Illinois Supreme Court, 2019)
Car Transportation Brokerage Co. v. Blue Bird Body Co.
322 F. App'x 891 (Eleventh Circuit, 2009)
Far East Services Corp. v. Tracker Marine, L.L.C.
246 S.W.3d 486 (Missouri Court of Appeals, 2007)
Cooper v. Bluff City Mobile Home Sales, Inc.
78 S.W.3d 157 (Missouri Court of Appeals, 2002)
Inauen Packaging Equipment Corp. v. Integrated Industrial Services, Inc.
970 S.W.2d 360 (Missouri Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
925 S.W.2d 211, 29 U.C.C. Rep. Serv. 2d (West) 825, 1996 Mo. App. LEXIS 776, 1996 WL 220693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowen-v-foust-moctapp-1996.