Bosworth v. Whitmore

37 Cal. Rptr. 3d 560, 135 Cal. App. 4th 536, 2006 Cal. Daily Op. Serv. 168, 2006 Daily Journal DAR 235, 2006 Cal. App. LEXIS 6
CourtCalifornia Court of Appeal
DecidedJanuary 6, 2006
DocketB163771
StatusPublished
Cited by6 cases

This text of 37 Cal. Rptr. 3d 560 (Bosworth v. Whitmore) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bosworth v. Whitmore, 37 Cal. Rptr. 3d 560, 135 Cal. App. 4th 536, 2006 Cal. Daily Op. Serv. 168, 2006 Daily Journal DAR 235, 2006 Cal. App. LEXIS 6 (Cal. Ct. App. 2006).

Opinion

Opinion

WILLHITE, J.

INTRODUCTION

Robert S. Whitmore, chapter 7 trustee for the estate of defendant Grover Joseph Harvey McCoy, prosecutes this appeal from a judgment confirming an arbitration award against McCoy and codefendant McCoy Creative Contractors and Interiors, Inc. 1 The judgment found McCoy and the corporation liable to plaintiffs Brian K. and Katherine Bosworth for damages of $2,067,860.43, and attorney fees and costs of $494,829.43.

*539 We hold that absent a completion date set by agreement, Code of Civil Procedure section 1283.8 gives the trial court the authority, on petition by a party to the arbitration, to set a date by which the arbitration proceeding must be concluded. 2 Although the better practice is to set the date when the case is first ordered to arbitration, the court has discretion to entertain a petition to set a completion date while the arbitration is in progress. To the extent the decisions in Titan/Value Equities Group, Inc. v. Superior Court (1994) 29 Cal.App.4th 482 [35 Cal.Rptr.2d 4] (Titan/Value), and Blake v. Ecker (2001) 93 Cal.App.4th 728 [113 Cal.Rptr.2d 422] (Blake), disapproved on another ground in Le Francois v. Goel (2005) 35 Cal.4th 1094, 1107, footnote 5 [29 Cal.Rptr.3d 249, 112 P.3d 636], suggest that the trial court cannot set an arbitration deadline, we respectfully disagree. Neither decision discusses the authority granted by section 1283.8.

In the instant case, although the trial court properly set a completion date, we conclude that the court abused its discretion when it later removed the arbitrator who had been handling the case for almost two years. On the record presented, the arbitrator’s reluctance to promise completion by the court’s deadline did not constitute a “failfure] to act” under section 1281.6 so as to justify his removal. Therefore, the court’s appointment of a successor arbitrator was unauthorized, and the successor arbitrator’s award was void. Consequently, we reverse the judgment.

FACTUAL AND PROCEDURAL BACKGROUND

1. The Contract and Its Arbitration Clause

In May 1998, plaintiffs Brian and Katherine Bosworth entered a contract with defendant McCoy Creative Contractors and Interiors, Inc. to construct a home in Malibu, California, for approximately $1,670,000. As president, defendant Joseph McCoy signed the agreement on behalf of the corporation. The contract contained an arbitration clause that provided in relevant part: “Any controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by arbitration in accordance with Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the Arbitrator(s) may be entered in any Court having jurisdiction thereof.”

In December 1998, the parties retained Builders Disbursements, Inc. (BDI) to distribute the proceeds from the Bosworths’ $1.8 million loan as the work *540 progressed. The parties’ contract with BDI also contained an arbitration clause requiring any disputes to be arbitrated in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (AAA).

2. The Lawsuit

In November 1999, the Bosworths filed suit against McCoy and his corporation for, inter alia, breach of contract and fraud, and alleged that McCoy was the alter ego of the corporation. The Bosworths claimed that the unfinished home had not been constructed in accord with the plans and specifications and that McCoy had breached the contract by accepting disbursement of funds before the work was completed. The Bosworths further alleged that McCoy had failed to refund money to the Bosworths that they had paid him before the funding of their construction loan.

In January 2000, McCoy and the corporation filed a petition to compel arbitration and stay the lawsuit. (§§ 1281.2 & 1281.4.) At a hearing conducted on February 17, 2000, the parties stipulated to submit “all substantive claims” to binding arbitration (except for the alter ego issue) pursuant to the arbitration agreement, and also stipulated to a stay of the Bosworths’ action. McCoy reserved the right to seek to compel arbitration of the alter ego claim. Based on the stipulation, the court placed the petition to compel arbitration off calendar as moot.

3. Commencement of Arbitration Proceedings

On March 6, 2000, the Bosworths submitted an arbitration demand to the AAA. They later amended their demand to add BDI as a party to the arbitration, claiming that BDI had negligently disbursed the loan proceeds to McCoy. In the meantime, on May 24, 2000, the AAA appointed Alan Dymond as arbitrator. On June 16, 2000, Dymond conducted a telephonic preliminary hearing in which he directed the Bosworths to complete a list of construction defects and damages “as soon as possible.”

Approximately three months thereafter, on September 21, 2000, Dymond held a hearing at which he issued several orders. He directed the Bosworths to provide their final defect list, damage estimate, and expert reports by October 15, 2000. He also ordered them to permit McCoy to inspect the home. He directed McCoy to serve demands on any additional parties by October 30, and to produce various documents.

*541 Despite the October 15, 2000 deadline, the Bosworths did not provide the required defect list, damage estimate, and expert reports until February 28, 2001. By April 16, 2001, McCoy and the corporation filed counterclaims against various subcontractors allegedly responsible for the Bosworths’ claimed defects in construction.

Approximately one month later (May 18, 2001), Dymond scheduled the arbitration to begin on September 4, 2001. However, although the subcontractors were required to appear on or before June 25, 2001, the AAA failed to properly notify them. Consequently, on August 10, 2001, Dymond vacated the September 4th hearing date, and continued the arbitration to November 8, 2001, to allow proper notice to the subcontractors. The Bosworths, McCoy and the corporation consented to the continuance.

On November 6, 2001, Dymond cancelled the hearing because McCoy, the corporation, and several of its subcontractors did not pay their arbitration fees. By the first week of January 2002, however, the fees were paid.

4. The Bosworths Seek Judicial Intervention to Set a Completion Date

On January 14, 2002, the Bosworths moved ex parte for an order requiring the case “to be arbitrated or tried before March 31, 2002.” In their motion, the Bosworths alleged that their lender had already twice extended the due date on their construction loan, and the delay in completing the arbitration jeopardized their ability to finance construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rajaee v. Weinberg Gonser Frost CA2/7
California Court of Appeal, 2026
Bagnarol v. Bagnarol CA1/3
California Court of Appeal, 2023
Reddy v. National University CA4/2
California Court of Appeal, 2021
Watson v. Knorr CA6
California Court of Appeal, 2013
People v. Clytus
209 Cal. App. 4th 1001 (California Court of Appeal, 2012)
Briggs v. Resolution Remedies
168 Cal. App. 4th 1395 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cal. Rptr. 3d 560, 135 Cal. App. 4th 536, 2006 Cal. Daily Op. Serv. 168, 2006 Daily Journal DAR 235, 2006 Cal. App. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bosworth-v-whitmore-calctapp-2006.