Boston Edison Company v. Great Lakes Dredge & Dock Company

423 F.2d 891, 1970 A.M.C. 1696, 1970 U.S. App. LEXIS 10137
CourtCourt of Appeals for the First Circuit
DecidedMarch 25, 1970
Docket7385
StatusPublished
Cited by16 cases

This text of 423 F.2d 891 (Boston Edison Company v. Great Lakes Dredge & Dock Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Company v. Great Lakes Dredge & Dock Company, 423 F.2d 891, 1970 A.M.C. 1696, 1970 U.S. App. LEXIS 10137 (1st Cir. 1970).

Opinion

CAFFREY, District Judge.

This is an appeal from a judgment entered in the district court granting a motion for summary judgment in favor of the United States, co-defendant in an action brought by Boston Edison Company, (hereafter Edison), against the United States and Great Lakes Dredge & Dock Company (hereafter Great Lakes). Great Lakes was an independent contractor employed by the United States to conduct dredging operations to improve the navigability of the Chelsea River. The Chelsea River is a navigable stream flowing between Chelsea and East Boston, Massachusetts, and as a navigable stream it comes under the jurisdiction of the Secretary of the Army.

The facts which gave rise to this litigation may be summarized as follows: On January 3, 1949, Edison made a written request to the Secretary of the Army for permission to install and maintain seven submarine electric power *893 cables under the Chelsea River. On March 3, 1949, pursuant to that request, the Secretary of the Army, acting by the Corps of Engineers, issued a permit to Edison for the installation of the cables at a point about 280 feet downstream from the Chelsea Street bridge. The cables, running from Chelsea to East Boston, were to be installed 15 feet below the then river bottom. The permit as issued contained ten specific conditions spelled out therein and one. of the principal issues in the case is the validity of Clause (g) contained in the permit which provides as follows:

“(g) That the United States shall in no case be liable for any damage or injury to the structure or work herein authorized which may be caused by or result from future operations undertaken by the Government for the conservation or improvement of navigation, or for other purposes, and no claim or right to compensation shall accrue from any such damage.”

Clause (g) was inserted in the permit as one of the standard conditions required to be contained in the standard form permit ordinarily used for the letter of authorization, pursuant to the provisions of 33 C.F.R. 209.130(c) (2). Soon after the issuance of the permit the seven submarine cables were installed by Edison under the Chelsea River bottom where they have since remained at all material times.

On July 21, 1964, the Corps of Engineers notified Edison of its intention to dredge the Chelsea River in the vicinity of these electric cables. On July 31, 1964, Edison replied to this notice by requesting that “the utmost care must be exercised to prevent damage.” Edison also requested that it be notified by the Engineers as to the identity of the contractor selected to conduct the dredging operations for the Government “in order that we may coordinate activities to prevent damage.” On June 25, 1965, the United States entered into its contract with Great Lakes, and on the same day Great Lakes informed Edison that it was the contractor selected to perform the operations under the supervision of the Corps of Engineers. Various conferences ensued between representatives of Edison, Great Lakes, and the Army Engineers. There also was a substantial amount of correspondence between the parties concerning the conduct of the dredging operation.

On April 4, 1966, in the course of carrying out the dredging operation Great Lakes allegedly caused damage to Edison’s submarine cables and on April 2, 1968 the instant suit was filed against both the United States and Great Lakes. Jurisdiction of the district court in the suit against the United States was based upon the Suits in Admiralty Act of March 9, 1920, 46 U.S.C. sec. 741 et seq. The complaint against the United States alleged (1) that the United States was negligent in planning, supervising, and conducting the dredging, and (2) that the United States was involved in an inherently dangerous and ultra-hazardous activity. The complaint sought recovery against Great Lakes in two counts, one on a negligence theory and the other on the theory that Edison was a third party beneficiary of the contract between Great Lakes and the United States and, as such, entitled to recover from Great Lakes by reason of its breach of the contract.

In its answer, among other defenses the United States relied on the exculpatory provisions of Clause (g) of the permit, contending that the clause precluded any liability to Edison on its part. The United States also counter-claimed against Edison for its costs of the litigation and reasonable attorney’s fee. Edison’s answer to the counterclaim challenged the constitutionality and legality of Clause (g) and also claimed that in any event the clause had been waived by the United States. Thereafter, a motion for summary judgment was filed by the United States and granted by the district court, which, however, made no ruling on the Government’s counterclaim which is still pending, as are the counts against Great Lakes which did not file a motion for *894 summary judgment. The matter is properly before this court because the district court made the appropriate findings for the existence of appellate jurisdiction under Rule 54(b), Federal Rules of Civil Procedure, in a situation where the judgment entered dealt with fewer than all of the claims or parties.

The thrust of Edison’s argument on appeal is an attack on various aspects of Clause (g) in the permit. Edison argues both that the clause as a matter of construction was not intended to cover liability in negligence and, alternatively, that the insertion of the clause in the permit was beyond the powers exercisable by the Secretary of the Army at the time of the issuance of the permit. The latter contention is premised largely on the dual facts that prior to the Secretary’s issuance of the permit, Congress had enacted the Suits in Admiralty Act, 46 U.S.C. sec. 741 et seq., and the Federal Tort Claims Act, 28 U.S.C. sec. 2671 et seq., both of which waive sovereign immunity of the United States to suits premised on the negligent actions of its agents.

Edison first argues that Clause (g) does not purport to establish governmental exemption from liability for negligence primarily because of the failure of that clause to contain the word “negligent” or any synonym therefor. An examination of the language in Clause (g) indicates that it contains the words “The United States shall in no case be liable for any damage or injury.” Broader language for a complete disclaimer of financial responsibility in any and all events is difficult for this court to imagine. Nevertheless, Edison argues that because the Federal Tort Claims Act had not been enacted in 1943, the first time the language of Clause (g) was used in a permit, the repetition of this language in the permit in issue herein, which was issued in 1949, should be construed in the light of the intent the draftsman had in first constructing Clause (g) in 1943. Edison then says that because the Federal Tort Claims Act was not in existence in 1943, the draftsman acting on behalf of the Government, knowing of its then sovereign immunity, did not attempt or intend to draft an exculpatory clause which would preclude governmental liability for negligence. The answer to this argument is that well prior to 1943 Congress had waived sovereign immunity in the area of maritime negligence by its enactment of the Suits in Admiralty Act on March 9, 1920.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
423 F.2d 891, 1970 A.M.C. 1696, 1970 U.S. App. LEXIS 10137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-company-v-great-lakes-dredge-dock-company-ca1-1970.