Boston Blower Co. v. Brown

21 N.E. 883, 149 Mass. 421, 1889 Mass. LEXIS 198
CourtMassachusetts Supreme Judicial Court
DecidedJune 20, 1889
StatusPublished
Cited by11 cases

This text of 21 N.E. 883 (Boston Blower Co. v. Brown) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Blower Co. v. Brown, 21 N.E. 883, 149 Mass. 421, 1889 Mass. LEXIS 198 (Mass. 1889).

Opinion

Devens, J.

This was an action in three counts, brought against the defendants, doing business under the name of the Brown Quadrieycle Company. The first count of the declaration is upon a contract in writing. By this contract the plaintiff agreed to make for the defendants one hundred quadricycles, according to working drawings furnished it, “ in all respects well constructed, of good material, and in good workmanlike manner.” The defendants were to furnish the necessary working drawings therefor, complete in all details, and agreed that they would “ accept and pay for all machines constructed according to the terms of this agreement,” conformably to a list of specified prices, “ upon being notified that they are ready for delivery,” in cash, or in certain described notes.

The first count of the plaintiff’s declaration is upon the last clause of this contract, which is as follows: “ The Brown Quadricycle Company agrees that, within ninety days after the delivery of the last machines of the number hereby contracted for, it will make with the Boston Blower Company a new contract, which shall be mutually satisfactory in all details, for not less [423]*423than one hundred machines; and if said Quadricycle Company fails to do so, that it will take and pay to the Boston Blower Company, in cash, the agreed value of all patterns, jigs, and special tools, according to the schedule marked B, hereto annexed, which may have been made or purchased by the Boston Blower Company for building quadricycles agreeably to this contract, and which remain in good serviceable condition, ordinary wear and tear excepted, as per said schedule marked B.” In this schedule, each tool was carried out at a separate price.

By the facts as found by the auditor it appears that the plaintiff constructed the first mentioned one hundred quadricycles, completing them on November 18, 1884, when they were delivered to and accepted by the defendants, who gave the notes therefor as provided in the contract, which notes the plaintiff subsequently collected.

The defendants have never made any new contract with the plaintiff, nor have they paid for the special tools enumerated in schedule B, the value of which has been found by the auditor, and by the justice of the Superior Court, sitting without a jury, to be $1,846.45. The ninety days within which the defendants were to make a new contract, or pay for the tools, began to run on November 18, 1884, if ever, and terminated on February 16, 1885. In May, 1885, the defendants claiming to have discovered that the machines furnished and received by them were imperfectly constructed, brought an action against the plaintiff, for damages thus sustained, in the Superior Court. The declaration included counts for other alleged damages, but a verdict was recovered by the present defendants in the sum of $1,250 on the count alone which alleged the damages sustained by the improper and faulty construction of the machines by the plaintiff. This verdict was put in evidence by the defendants, contending that it disposed of the whole subject matter in controversy, and that no action could now be maintained to enforce any obligation of the defendants to make a new contract, or to take and pay for the specified tools.

No judgment has been rendered upon the verdict of the jury in the prior action, and it might be questioned whether, until this is done, the verdict would be sufficient to estop the plaintiff from maintaining this suit, even if it would be if it had passed [424]*424into a judgment. It is the verdict with the judgment upon it which constitutes an estoppel of the party against whom it is rendered, and makes a res judicata of any fact without the existence, proof, or admission of which it could not have been rendered. Hawks v. Truesdell, 99 Mass. 557 Burlen v. Shannon, 99 Mass. 200. In a suit at common law, judgment on a verdict is the necessary and immediate result, unless it be set aside, or unless some motion in arrest thereof be filed. No suggestion has been made that judgment cannot at once be entered, and both parties in argument have dealt with the case at bar as if their rights were respectively determined by the verdict. We do not think it necessary, therefore, to consider whether, to be available for the purpose for which the defendants seek to use it, judgment should properly have been- rendered thereon.

In the prior action, no attempt was made on the part of the then plaintiffs, the present defendants, to avail themselves of the claims which form the subject of the present action, either by way of set-off, recoupment, or otherwise. It was, however, ruled by the auditor, which ruling was affirmed by the Superior Court, that the verdict in the former action was a bar to the plaintiff’s recovery upon its first count, being that for the recovery of the value of the specified tools, which we are now considering.

It is the contention of the defendants, that the completion of the machines originally contracted for in strict compliance with all the contract requirements was a condition precedent to the obligation to pay for the tools; and that if, in the first action, it had recovered but a single dollar, it would be released from any further performance .under the contract.

It is evident, from the-character of the contract, that it required from the plaintiff, in order to make the machines desired by the defendants, expensive preparations in the way of peculiar tools, comparatively valueless for any other purpose than the construction of these machines; that it was seen by both that it would not be compensated unless more than a hundred machines should be made; and that therefore the defendants agreed to pay for the same, unless a new contract should be made for at least a hundred more at a price which [425]*425should be satisfactory to the plaintiff. Of course it could not be expected that such a contract would be entered into unless in some form the plaintiff could obtain payment for the tools, as it would by making the new contract at such a rate that it could afford to disregard the expenditure bestowed upon them.

It is said, that, if in any respect the plaintiff failed to perform its original contract, it could not be expected that the defendants would be ready to make a new contract with the party thus failing. An agreement to make a new contract, mutually satisfactory, is evidently one which could never be enforced, as it depends on the will, or even the caprice, of either. Brown v. Foster, 113 Mass. 136. The intent of the original contract was obviously to provide for the payment for the tools although a new contract might be substituted for this, and such is its effect. The inquiry is, therefore, whether this agreement is available only upon the exact completion of the machines as they are described in the contract, and whether, if they failed in any detail to meet its requirements, the obligation of the defendants was discharged. There is certainly no express condition that this shall be so, and a provision so onerous in its character should appear in clear terms. The defendants deduce an argument from the fact, that, as the defendants agree to make a new contract, or, failing to do so, to pay for the tools “ within ninety days after the delivery of the last machines of the number hereby contracted for,” the word “ delivery ” must be delivery in strict accordance with the terms of the contract, and, there having been no such delivery, no obligation exists to pay for the tools.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minot v. Minot
66 N.E.2d 5 (Massachusetts Supreme Judicial Court, 1946)
Lander v. Samuel Heller Leather Co.
50 N.E.2d 962 (Massachusetts Supreme Judicial Court, 1943)
United States ex rel. Larkin v. Maryland Casualty Co.
45 F. Supp. 286 (D. Massachusetts, 1942)
Morin v. Clark
6 N.E.2d 830 (Massachusetts Supreme Judicial Court, 1937)
McNeal-Edwards Co. v. Frank L. Young Co.
51 F.2d 699 (First Circuit, 1931)
Lynch v. Culhane
135 N.E. 119 (Massachusetts Supreme Judicial Court, 1922)
Cox v. Wiley
67 N.E. 367 (Massachusetts Supreme Judicial Court, 1903)
Eastern Forge Co. v. Corbin
66 N.E. 419 (Massachusetts Supreme Judicial Court, 1903)
Stone v. Commonwealth
63 N.E. 1074 (Massachusetts Supreme Judicial Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
21 N.E. 883, 149 Mass. 421, 1889 Mass. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-blower-co-v-brown-mass-1889.