Bostick v. Wood

620 So. 2d 297, 1993 La. App. LEXIS 1499, 1993 WL 124576
CourtLouisiana Court of Appeal
DecidedApril 14, 1993
DocketNo. 92-CA-982
StatusPublished

This text of 620 So. 2d 297 (Bostick v. Wood) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bostick v. Wood, 620 So. 2d 297, 1993 La. App. LEXIS 1499, 1993 WL 124576 (La. Ct. App. 1993).

Opinion

WICKER, Judge.

This appeal arises from a suit filed on behalf of Marie D. Bostick (Bostick), plaintiff/appellee, against Glenn D. Wood (Wood) and GW Contractors, Inc. (GW) as successors in interest to Point Landing, Inc., defendants/appellants. Bostick sought to collect damages as a result of Wood’s and GW’s cancellation of a lease. Wood and GW leased batture property from Bostick for a barge fleeting operation. Wood and GW rely on a lease provision for cancellation due to governmental interference; Bostick asserts she was not given the opportunity to correct any condition triggering termination. The trial judge ruled in favor of Bostick and awarded her $110,000.00. Wood and GW have appealed. We reverse.

These parties entered into a lease agreement March 1, 1978. That agreement was for five years with two five-year options for renewal. These renewal options were exercised and the lease expired February 28, 1993. GW by letters dated October 13, 1982 and November 26, 1982 exercised its option to renew the first and second five-year periods. The purpose of the lease is stated in the lease agreement as follows:

Lessee desires to lease certain premises owned by Lessor fronting on the Mississippi River in the Parish of Jefferson for the purpose of mooring, fleeting and making up tows of barges along with towboats and floating equipment[.]

By letter dated March 22, 1988 Wood was informed by the U.S. Army Corps, of Engineers (Corps) that revetment construction would begin. That letter stated in part:

[298]*298It is not possible to give you a definite schedule for the revetment construction but placement of concrete mattress on the Mississippi River is tentatively scheduled to commence about September 1, 1988. A firmer schedule will be available about July 15, 1988.

That letter also informed Wood that the Corps would interfere with his use of the premises as follows:

Our work in the vicinity of your barge mooring facilities may require modifications to these facilities. The concrete mattress will be placed as close to your anchor piles as practicable. Stone will be placed on those areas where complete coverage of the underwater slope cannot be accomplished with the concrete mattress. It will be necessary for your buoys within our construction limits to be free of vessels for two non-eonsecu-tive periods of 1 to 2 days each during which construction will take place. Resumption of barge fleeting activities after completion of revetment construction will be allowed provided the mooring systems prevent the barges from contacting the revetted bank at all river stages. In the event that a new mooring system is required, submission of a standard navigation permit application, channeled through the appropriate agencies will be necessary.

The lease provides lessee the option to terminate the lease on the following ground:

If ... any governmental agency interferes with the Lessee’s use of the premises as contemplated by this Lease Agreement, then Lessee may, at its option, terminate the Lease Agreement or any part thereof and receive a prorata refund of any rental payment hereunder.

It was stipulated that the first notification by Wood to Bostick that he intended to cancel the lease was by letter dated July 25, 1988. At trial Wood admitted he had not used the batture for fleeting operations for approximately 18 months prior to the revetment and did not foresee using it in the future due to the poor economy. The trial judge evidently concluded there had been no governmental interference with Wood’s fleeting operation since he was not using the property.

On appeal, the appellants raised several specifications of error. These include the alleged error that the trial judge failed to acknowledge the right to cancel and that it applied an erroneous duty on the part of appellants to give Bostick the opportunity to comply with the new requirements.

Gerard J. Brantley, a U.S. Corps, of Engineers Chief of the Channel Stabilization section for Engineering, identified a letter written by the Corps’ Chief of Construction dated July 27, 1988. That letter was introduced into evidence. It was written to GW and outlines the revetment construction. It states in part:

Reference your July 25, 1988 phone conversation with Mr. Roth of my office concerning construction of Luling Revetment. The work consists of extending the revetment 7,100 linear feet downstream in the vicinity of river mile 116 on the right descending bank. Clearing and grubbing began on July 17, 1988 and was completed July 22, 1988 and is scheduled to be completed on July 29, 1988. Articulated Concrete Mattress (ACM) is scheduled to be placed between August 17 and 23, 1988. Placement of stone on the upper portions of the bank will be done within two months after ACM placement is complete.

Timothy J. Roth, a Corps’ employee, testified he was familiar with the revetment of the batture property at issue. After the March, 1988 letter was sent to Wood he received a call in late July from Wood. Wood never requested of him what the Corps’ requirements would be for him to continue his barge fleeting operation. Pri- or to July 25, 1988 Jim Ducote, a Corps’ field representative, met with Wood. Du-cote obtained permission from Wood to disconnect a buoy and pull it on the bank.

Roth stated that once the revetment was done GW had to apply for a permit and conform with one of the following provisions required by the Corps and outlined in a memorandum dated August 5, 1985 and introduced into evidence:

[299]*299c. Modification to Permitted Mooring Systems for Revetment Construction.
(1) Mooring systems using dolphins or anchor piles with buoys will not require any major alterations for revetment construction. Suspension of the mooring and fleeting operation will be required during revetment construction.
(2) Mooring systems using land ties that secure the moored barges against the bank will require major modifications. The mooring and fleeting activity will be suspended during revetment construction. Upon completion of revetment work mooring and fleeting operations can be resumed provided the permit holder obtains an approved permit for a mooring system which will prevent the moored barges from resting against the articulated concrete mattress at all river stages. The acceptable alternate designs for this type system in order of preference are:
(a) Mooring dolphins.
(b) Anchor piles with mooring buoys.
(c) Continuation of the land tie system with the government changing the standard revetment design. The design change would consist of placing a heavy layer of stone along the upper bank in lieu of concrete mattress and allow barges to breast against the stone. This would be contingent upon the permit holder contributing funds to the government to cover the additional cost of constructing revetment as described above.

Wood testified that he installed deadmen at the beginning of the Bostick lease for mooring purposes. After the revetment construction by the Corps he was unable to pay the cost for the new requirements.

Wood stated he exercised his option to cancel the lease in July, 1988. He had not been fleeting barges approximately 18 months prior to July, 1988 because he had no customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mennella v. Kurt E. Schon E.A.I., Ltd.
979 F.2d 357 (Fifth Circuit, 1992)
General Leasing Co. v. Leda Towing Co., Inc.
286 So. 2d 802 (Louisiana Court of Appeal, 1974)
Tassin v. Slidell Mini-Storage, Inc.
396 So. 2d 1261 (Supreme Court of Louisiana, 1981)
Brunies v. Police Jury of Parish of Jefferson
110 So. 2d 732 (Supreme Court of Louisiana, 1959)
Henry Rose Mercantile & Mfg. Co. v. Smith
71 So. 487 (Supreme Court of Louisiana, 1916)
Dean v. Beck
46 La. Ann. 1168 (Supreme Court of Louisiana, 1894)
Pace v. Loyal Order of Moose, Metairie Lodge 2195
538 So. 2d 299 (Louisiana Court of Appeal, 1989)
Texas & P. Ry. Co. v. Mengel Co.
62 F. Supp. 752 (E.D. Louisiana, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
620 So. 2d 297, 1993 La. App. LEXIS 1499, 1993 WL 124576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bostick-v-wood-lactapp-1993.