Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc.

Louisiana Court of Appeal·Decided February 25, 2026·No. 56,765-CA·Published·Robinson

Opinion

Judgment rendered February 25, 2026.

Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 56,765-CA

COURT OF APPEAL

SECOND CIRCUIT

STATE OF LOUISIANA

*****

BOSSIER PARISH BY AND THROUGH Plaintiff-Appellee THE BOSSIER PARISH POLICE JURY

versus

BOGGS & POOLE CONTRACTING Defendant-Appellant GROUP, INC.

*****

Appealed from the

Twenty-Sixth Judicial District Court for the Parish of Bossier, Louisiana Trial Court No. 172,938

Honorable Charles A. Smith, Judge

*****

SINCLAIR LAW FIRM, LLC Counsel for Appellant By: Scott C. Sinclair

WIENER, WEISS & MADISON, APC Counsel for Appellee, By: Geoffrey D. Westmoreland Bossier Parish by and Reid Allen Jones through the Bossier Parish Police Jury

PATRICK R. JACKSON Counsel for Appellee, Bossier Parish

LONG LAW FIRM, LLP Counsel for Appellees, By: Albert Dale Clary Prevot Design Services Alec Brendan Keane and Civil Design Group

DONOHUE, PATRICK & SCOTT, PLLC Counsel for Appellee, By: Leigh F. Groves Estes, McClure & Associates, Inc. D/B/A

EMA Engineers &

Consultants

*****

Before ROBINSON, MARCOTTE, and ELLENDER, JJ.

ROBINSON, J.

Boggs & Poole Contracting Group, Inc. (“B&P”), which was awarded a contract to build a new central branch public library in Bossier Parish, appeals a judgment denying its petition for a writ of mandamus under La. R.S. 38:2191 to order the Bossier Parish Police Jury (“Bossier”) to make the final payment under the construction contract.

Concluding that mandamus was not available because the final payment was not due under the construction contract when the project architect had not approved the final payment, we affirm the judgment.

FACTS

B&P agreed to construct the library for $9,267,001. Substantial completion was to be reached within 365 days from the start of the work. B&P agreed to pay $2,500 in liquidated damages for each calendar day that the project was inexcusably delayed in meeting substantial completion. B&P provided a performance bond executed by Travelers Casualty and Surety Company. The contract was awarded to B&P on October 6, 2021.

The official start date of the project was October 25, 2021. After B&P requested extensions, Bossier agreed to move the deadline for substantial completion to July 5, 2023.

The project architect, Prevot Design Services, issued a certificate of substantial completion on December 4, 2023. On January 10, 2024, Bossier voted to accept the certificate of substantial completion, which was recorded in the Bossier Parish mortgage records on January 11, 2024. The clerk of court issued a clear lien certificate on February 27, 2024. The library opened to the public on March 11, 2024.

Change orders had increased the construction cost to $9,342,355.87.

Bossier has paid $8,715,977 to B&P, leaving an unpaid balance of $626,378.87.

The construction contract provides in Section 5.2.1 that final payment shall be made to B&P when (1) B&P has fully performed the contract except for B&P’s responsibility to correct work and to satisfy other requirements, if any, which extend beyond final payment, and (2) a final certificate of payment has been issued by the architect.

Section 9.5.1 of the contract states:

The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner, if in the Architect’s opinion the representations to the Owner required by Section 9.4.2 cannot be made. . . . The Architect may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to such extend as may be necessary in the Architect’s opinion to protect the Owner from loss for which the Contractor is responsible, including loss resulting from acts and omissions described in Section 3.3.2. . . .

The contract also provides in Section 9.10.1 that when the architect finds the work acceptable under the contract documents and the contract fully performed, the architect will promptly issue a final certificate for payment stating to the best of the architect’s knowledge, information, and belief, and on the basis of the architect’s onsite visits and inspections, the work was completed in accordance with the contract and the entire balance found to be due to the contractor and noted in the final certificate was due and payable.

Section 9.10.2 of the contract states that neither final payment nor any remaining retained percentage shall become due until B&P submits to the

architect: (1) an affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the work for which Bossier or Bossier’s property might be responsible or encumbered (less amounts withheld by Bossier) had been paid or otherwise satisfied; (2) a certificate evidencing that insurance required by the contract documents to remain in force after final payment was currently in effect; (3) a written statement that B&P knew of no reason that the insurance would not be renewable to cover the period required by the contract documents; (4) consent of the surety, if any, to final payment; (5) documentation of any special warranties, such as manufacturers’ warranties or specific subcontractor warranties; and (6) if required by Bossier, other data establishing payment or satisfaction of obligations, such as receipts and releases and waivers of liens, claims, security interests, or encumbrances arising out of the contract to the extent and in such form as may be designated by Bossier.

On February 27, 2024, B&P submitted a payment application to Prevot. On April 4, 2024, B&P requested that Bossier pay the total contract price minus the value of certain punch list items.

Prevot did not approve the final payment application. On April 17, 2024, Prevot wrote to B&P that given the value of the liquidated damages and unresolved issues concerning outstanding architectural, MEP, and civil items, it could not recommend payment at the time because it was unable to provide the representations to Bossier as required by Section 9.4.2 and as outlined in Section 9.5.

On April 29, 2024, Bossier Parish filed suit against B&P. Bossier alleged that B&P owed $377,500 in liquidated damages for 151 days of

unexcused delays. Bossier also alleged that B&P failed to install a dry pipe sprinkler system as set forth in the construction contract. It estimated the cost to convert the system to a dry system would be $245,000. Bossier further alleged that B&P failed to complete several items of work. Finally, Bossier alleged that there were construction defects from B&P’s failure to construct the library in accordance with the plan and specifications. Bossier alleged that the cost to correct the defects and finish the work would likely exceed $48,000.

In its lawsuit, Bossier sought a declaratory judgment that it was not liable for payment of the remaining balance because of damages owed by B&P. It also sought damages for the cost to complete the project and to resolve all construction defects that will exceed the remaining balance because of B&P’s alleged breach of the construction contract.

On December 12, 2024, B&P filed an answer, a reconventional demand, and a third party demand. Prevot Design Services, EMA Engineering & Consulting, Inc., and Civil Design Group, LLC, were named as third party defendants. B&P asserted a claim against Bossier for the balance due under the construction contract, which B&P alleged was $626,378.87 and was due 45 days following receipt of the clear lien certificate. B&P contended it was owed attorney fees and interest as allowed under La. R.S. 38:2191. B&P also asserted a claim against Bossier for delay damages of $259,999.26.

Free access — add to your briefcase to read the full text and ask questions with AI

Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc., (La. Ct. App. 2026).

Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc. (Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Colvin v. LOUISIANA PATIENT'S COMP. FUND
947 So. 2d 15 (Supreme Court of Louisiana, 2007)
Hoag v. State
889 So. 2d 1019 (Supreme Court of Louisiana, 2004)
Wallace C. Drennan, Inc. v. St. Charles Parish
202 So. 3d 535 (Louisiana Court of Appeal, 2016)
Woodrow Wilson Constr. LLC v. Orleans Parish Sch. Bd.
245 So. 3d 1 (Louisiana Court of Appeal, 2018)