Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc.

CourtLouisiana Court of Appeal
DecidedFebruary 25, 2026
Docket56,765-CA
StatusPublished
AuthorRobinson

This text of Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc. (Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc., (La. Ct. App. 2026).

Opinion

Judgment rendered February 25, 2026. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 56,765-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

BOSSIER PARISH BY AND THROUGH Plaintiff-Appellee THE BOSSIER PARISH POLICE JURY

versus

BOGGS & POOLE CONTRACTING Defendant-Appellant GROUP, INC.

Appealed from the Twenty-Sixth Judicial District Court for the Parish of Bossier, Louisiana Trial Court No. 172,938

Honorable Charles A. Smith, Judge

SINCLAIR LAW FIRM, LLC Counsel for Appellant By: Scott C. Sinclair

WIENER, WEISS & MADISON, APC Counsel for Appellee, By: Geoffrey D. Westmoreland Bossier Parish by and Reid Allen Jones through the Bossier Parish Police Jury

PATRICK R. JACKSON Counsel for Appellee, Bossier Parish

LONG LAW FIRM, LLP Counsel for Appellees, By: Albert Dale Clary Prevot Design Services Alec Brendan Keane and Civil Design Group

DONOHUE, PATRICK & SCOTT, PLLC Counsel for Appellee, By: Leigh F. Groves Estes, McClure & Associates, Inc. D/B/A EMA Engineers & Consultants

Before ROBINSON, MARCOTTE, and ELLENDER, JJ. ROBINSON, J.

Boggs & Poole Contracting Group, Inc. (“B&P”), which was awarded

a contract to build a new central branch public library in Bossier Parish,

appeals a judgment denying its petition for a writ of mandamus under La.

R.S. 38:2191 to order the Bossier Parish Police Jury (“Bossier”) to make the

final payment under the construction contract.

Concluding that mandamus was not available because the final

payment was not due under the construction contract when the project

architect had not approved the final payment, we affirm the judgment.

FACTS

B&P agreed to construct the library for $9,267,001. Substantial

completion was to be reached within 365 days from the start of the work.

B&P agreed to pay $2,500 in liquidated damages for each calendar day that

the project was inexcusably delayed in meeting substantial completion.

B&P provided a performance bond executed by Travelers Casualty and

Surety Company. The contract was awarded to B&P on October 6, 2021.

The official start date of the project was October 25, 2021. After

B&P requested extensions, Bossier agreed to move the deadline for

substantial completion to July 5, 2023.

The project architect, Prevot Design Services, issued a certificate of

substantial completion on December 4, 2023. On January 10, 2024, Bossier

voted to accept the certificate of substantial completion, which was recorded

in the Bossier Parish mortgage records on January 11, 2024. The clerk of

court issued a clear lien certificate on February 27, 2024. The library

opened to the public on March 11, 2024. Change orders had increased the construction cost to $9,342,355.87.

Bossier has paid $8,715,977 to B&P, leaving an unpaid balance of

$626,378.87.

The construction contract provides in Section 5.2.1 that final payment

shall be made to B&P when (1) B&P has fully performed the contract except

for B&P’s responsibility to correct work and to satisfy other requirements, if

any, which extend beyond final payment, and (2) a final certificate of

payment has been issued by the architect.

Section 9.5.1 of the contract states:

The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner, if in the Architect’s opinion the representations to the Owner required by Section 9.4.2 cannot be made. . . . The Architect may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to such extend as may be necessary in the Architect’s opinion to protect the Owner from loss for which the Contractor is responsible, including loss resulting from acts and omissions described in Section 3.3.2. . . .

The contract also provides in Section 9.10.1 that when the architect

finds the work acceptable under the contract documents and the contract

fully performed, the architect will promptly issue a final certificate for

payment stating to the best of the architect’s knowledge, information, and

belief, and on the basis of the architect’s onsite visits and inspections, the

work was completed in accordance with the contract and the entire balance

found to be due to the contractor and noted in the final certificate was due

and payable.

Section 9.10.2 of the contract states that neither final payment nor any

remaining retained percentage shall become due until B&P submits to the

2 architect: (1) an affidavit that payrolls, bills for materials and equipment, and

other indebtedness connected with the work for which Bossier or Bossier’s

property might be responsible or encumbered (less amounts withheld by

Bossier) had been paid or otherwise satisfied; (2) a certificate evidencing

that insurance required by the contract documents to remain in force after

final payment was currently in effect; (3) a written statement that B&P knew

of no reason that the insurance would not be renewable to cover the period

required by the contract documents; (4) consent of the surety, if any, to final

payment; (5) documentation of any special warranties, such as

manufacturers’ warranties or specific subcontractor warranties; and (6) if

required by Bossier, other data establishing payment or satisfaction of

obligations, such as receipts and releases and waivers of liens, claims,

security interests, or encumbrances arising out of the contract to the extent

and in such form as may be designated by Bossier.

On February 27, 2024, B&P submitted a payment application to

Prevot. On April 4, 2024, B&P requested that Bossier pay the total contract

price minus the value of certain punch list items.

Prevot did not approve the final payment application. On April 17,

2024, Prevot wrote to B&P that given the value of the liquidated damages

and unresolved issues concerning outstanding architectural, MEP, and civil

items, it could not recommend payment at the time because it was unable to

provide the representations to Bossier as required by Section 9.4.2 and as

outlined in Section 9.5.

On April 29, 2024, Bossier Parish filed suit against B&P. Bossier

alleged that B&P owed $377,500 in liquidated damages for 151 days of

3 unexcused delays. Bossier also alleged that B&P failed to install a dry pipe

sprinkler system as set forth in the construction contract. It estimated the

cost to convert the system to a dry system would be $245,000. Bossier

further alleged that B&P failed to complete several items of work. Finally,

Bossier alleged that there were construction defects from B&P’s failure to

construct the library in accordance with the plan and specifications. Bossier

alleged that the cost to correct the defects and finish the work would likely

exceed $48,000.

In its lawsuit, Bossier sought a declaratory judgment that it was not

liable for payment of the remaining balance because of damages owed by

B&P. It also sought damages for the cost to complete the project and to

resolve all construction defects that will exceed the remaining balance

because of B&P’s alleged breach of the construction contract.

On December 12, 2024, B&P filed an answer, a reconventional

demand, and a third party demand. Prevot Design Services, EMA

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colvin v. LOUISIANA PATIENT'S COMP. FUND
947 So. 2d 15 (Supreme Court of Louisiana, 2007)
Hoag v. State
889 So. 2d 1019 (Supreme Court of Louisiana, 2004)
Wallace C. Drennan, Inc. v. St. Charles Parish
202 So. 3d 535 (Louisiana Court of Appeal, 2016)
Woodrow Wilson Constr. LLC v. Orleans Parish Sch. Bd.
245 So. 3d 1 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bossier-parish-by-and-through-the-bossier-parish-police-jury-v-boggs-lactapp-2026.