Bolser Enterprises, Inc. v. Arizona Registrar of Contractors

139 P.3d 1286, 213 Ariz. 110, 2006 Ariz. App. LEXIS 83
CourtCourt of Appeals of Arizona
DecidedJuly 25, 2006
DocketNo. 1CA-CA 05-0355
StatusPublished
Cited by9 cases

This text of 139 P.3d 1286 (Bolser Enterprises, Inc. v. Arizona Registrar of Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolser Enterprises, Inc. v. Arizona Registrar of Contractors, 139 P.3d 1286, 213 Ariz. 110, 2006 Ariz. App. LEXIS 83 (Ark. Ct. App. 2006).

Opinion

OPINION

TIMMER, Judge.

¶ 1 This appeal stems from a decision by the Arizona Registrar of Contractors (“ROC”) to revoke a residential contractor’s license issued to Bolser Enterprises, Inc., doing business as A-l Builders (“Bolser”), because Bolser performed substandard work building a garage for Ray and Barbara Ford.1 2The superior court ruled that it lacked subject matter jurisdiction to consider Bol-ser’s complaint seeking judicial review of the [111]*111ROC’s decision and therefore dismissed the complaint. For the reasons that follow, we disagree with the ruling and therefore reverse and remand for further proceedings.

BACKGROUND

¶ 2 In 2002, Bolser, a licensed contractor, built a garage for the Fords pursuant to the parties’ agreement. The Fords, dissatisfied with Bolser’s craftsmanship, filed separate complaints with the ROC in 2003 alleging numerous construction deficiencies. After inspections by ROC inspector John Prince, the ROC issued citations and complaints against Bolser in both eases.

¶ 3 After additional events occurred in the cases, which are not relevant to this appeal, an administrative law judge (“ALJ”) from the Office of Administrative Hearings (“OAH”) conducted a consolidated evidentia-ry hearing on both complaints on April 27, 2004. The ALJ issued a recommended order in the cases on May 17. Regarding the first complaint, the ALJ found that Bolser had installed one overhang without a signed change order, thereby failing to build the garage as specified, and had additionally failed to rectify the error. With respect to the second complaint, the ALJ found that Bolser had improperly installed shingles and had failed to repair cracked ridge bracing on the garage roof.

¶4 In separate orders, the ROC adopted the ALJ’s decision and recommended dispositions in both eases. On June 3, the ROC issued an order in the first ease stating that Bolser’s license would be revoked on July 13 unless before that date Bolser corrected the mismatched overhangs in a workmanlike manner. The order additionally provided that it constituted “a final administrative decision reviewable pursuant to the provisions of [Arizona Revised Statute (“A.R.S.”) section 12-901 (2003)],” and that the order would be in full force and effect on July 13 unless a stay order was secured from the superior court on or before that date. Finally, the order advised that if the Fords denied access to the property, thereby preventing Bolser from performing the corrective work, the ROC would deem Bolser in compliance with the order, and the case would be closed without discipline.

¶ 5 On June 4, the ROC issued an order in the second case stating the Bolser’s license would be revoked on July 14 unless before that date Bolser fixed the shingles and cracked ridge bracing in a workmanlike manner. The order also provided that any request for rehearing must be filed on or before July 9 and that any appeal to the superior court, and attendant request for a stay order, must be filed on or before July 14. As in the June 3 order, the ROC informed the Fords that if they denied Bolser access to the property, the ROC would deem Bolser in compliance with the order, and the ease would be closed without discipline. Finally, the ROC assessed a $200 civil penalty against Bolser.

¶ 6 Bolser did not appeal the June 3 or June 4 orders, electing to proceed with the corrective work. After securing a time from the Fords to access the property, Bolser informed the ROC that the required work would begin on June 14.

¶7 On June 17, Bolser filed notices of compliance in both cases, stating that it had complied with the ROC’s June 3 and June 4 orders and enclosing payment of the $200 civil penalty.2 The ROC notified the Fords by letter dated June 21 that Bolser had filed a notice of compliance in the first case and that the Fords had ten days from that date to file a response or objection.3 The record does not reflect that the Fords filed any [112]*112response or objection to either notice of compliance. Documents filed by Bolser on August 9 and 27, however, state that the Fords filed objections and notices of noneompliance on July 21, well after the ten-day deadline imposed by the ROC.

¶ 8 On September 20, Bolser objected to John Prince continuing to serve as the ROC’s inspector in both cases due to an alleged bias stemming from Prince’s former employment with Bolser. Also on that date, Prince conducted a compliance inspection. Prince found that Bolser had sufficiently corrected the ridge bracing and some of the shingles problem. Prince concluded, however, that the overhang correction did not meet workmanship standards and that Bolser had failed to properly nail some shingles. The record does not reflect that the ROC ruled on Bol-ser’s objection to Prince’s role as inspector.

¶ 9 On October 13, Bolser requested a hearing on the compliance report and requested a stay of discipline. Bolser also reiterated its objection to Prince serving as the inspector. The record does not reflect a ruling on this request.

¶ 10 On January 13, 2005, Prince conducted another inspection. His subsequent report reflected that the overhang remained in the same condition as noted in the September 20 inspection, one shingle remained damaged, and some caulking of nails was excessive and did not meet workmanship standards. On January 27, the ROC notified the parties by form letter (the “January 27 disciplinary notice” or “notice”) of its decision to revoke Bolser’s license effective that day “in compliance with the Decision and Order” in both cases. The notice further enclosed a form permitting the Fords to apply to recover monies from the residential contractors’ recovery fund established by A.R.S. § 32-1132 (Supp.2004).

¶ 11 On February 2, Bolser filed a complaint in superior court appealing the ROC’s disciplinary decision in both cases. The Fords moved to dismiss the complaint on the ground that Bolser’s untimely appeal deprived the court of subject matter jurisdiction. The ROC appeared as a nominal party and joined the Fords’ position. The Fords and ROC asserted that Bolser’s complaint was defective because Bolser had not appealed from the June 3 and June 4 orders and the January 27 disciplinary notice was merely an administrative action that implemented the prior orders and was therefore not susceptible to judicial review. Following oral argument, the court granted the Fords’ motion and dismissed Bolser’s complaint. This appeal followed.4

¶ 12 Because the interpretation of statutory requirements governing judicial review of administrative decisions is a question of law, we independently determine whether the superior court properly dismissed Bolser’s complaint for lack of subject matter jurisdiction. Guminski v. Ariz. State Veterinary Med. Examining Bd., 201 Ariz. 180, 182, ¶ 10, 33 P.3d 514, 516 (App.2001).

DISCUSSION

¶ 13 The Administrative Review Act (“ARA”), A.R.S. §§ 12-901

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shea v. Maricopa
Arizona Supreme Court, 2023
Leanna S. v. Dcs
Court of Appeals of Arizona, 2017
Best v. Adhs
Court of Appeals of Arizona, 2017
Flood Control v. Abc Sand
Court of Appeals of Arizona, 2014
Arizona Physicians IPA, Inc. v. Western Arizona Regional Medical Center
263 P.3d 661 (Court of Appeals of Arizona, 2011)
Grosvenor Holdings, L.C. v. Figueroa
218 P.3d 1045 (Court of Appeals of Arizona, 2009)
Grosvenor Holdings v. Pinal County
Court of Appeals of Arizona, 2009
Twin Peaks Construction Inc. v. Weatherguard Metal Construction, Inc.
154 P.3d 378 (Court of Appeals of Arizona, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
139 P.3d 1286, 213 Ariz. 110, 2006 Ariz. App. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolser-enterprises-inc-v-arizona-registrar-of-contractors-arizctapp-2006.