Bohme, Inc. v. Sprint International Communications Corp.

686 N.E.2d 300, 115 Ohio App. 3d 723
CourtOhio Court of Appeals
DecidedNovember 25, 1996
DocketNo. 70331.
StatusPublished
Cited by19 cases

This text of 686 N.E.2d 300 (Bohme, Inc. v. Sprint International Communications Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bohme, Inc. v. Sprint International Communications Corp., 686 N.E.2d 300, 115 Ohio App. 3d 723 (Ohio Ct. App. 1996).

Opinion

*725 James M. Porter, Judge.

Plaintiffs-appellants, Bohme, Inc. and its insurer, Aetna Insurance Company, appeal from a summary judgment entered by the trial court in favor of defendant-appellee Sprint International Communications Corporation on plaintiffs’ claim that defendant Sprint or its predecessor was negligent in the maintenance of a rooftop air conditioning unit which caused electrical problems adversely affecting the operations of Bohme’s graphic/printing business in the same building. Plaintiffs contend that disputed issues of material fact precluded the grant of summary judgment in defendant Sprint’s favor, that Sprint was responsible for the negligent conduct of its independent contractors, and harm to plaintiffs was foreseeable from the defective installation or maintenance of the unit. We find merit in the appeal and reverse and remand.

Plaintiff Bohme, Inc. provides typesetting and graphic arts services to customers from its plant and offices on the fourth floor of the Caxton Building in downtown Cleveland. Sprint is a cotenant on the fourth floor. By 1992, Bohme had come to rely on two printer/output machines manufactured by Alphatype Corporation, known as the CRS 99000 Series machine, in producing a particular segment of its photographic typesetting. These machines are highly sensitive and susceptible to minor power fluctuations.

In April 1992, Bohme began experiencing imperfections in the product being generated by its Alphatype machines in that the printed or film product was intermittently marked with lines running through the finished material. The machines continued to produce unacceptable product over the next six months, during which Bohme and experts labored to find the source of the problem.

Originally, Bohme believed that the problem was caused by a defect in the equipment itself. Alphatronics, a Chicago company specializing in service and maintenance of Alphatype machines, was consulted, and despite numerous service calls and component replacements and adjustments, the problems persisted. During this service period, Bohme never advised the Caxton Building management or Sprint of its production difficulties.

On October 16,1992, on a service call by the Alphatronics technician, a variance in the three-phase power servicing the Bohme premises was finally discovered. This came as a shock to Bohme personnel, who contacted the building manager and demanded that the problem be corrected. The Caxton Building retained Spectrum Electric and its president, William Rennie, to locate the source of the building ground causing the variance in the electrical power serving the Bohme premises. Rennie testified that he spent two full days, October 16 and 17, at the Caxton Building attempting to locate the source of the building ground through a process of elimination and trial and error.

*726 Eventually, the ground was isolated in the fourth floor premises occupied by Sprint and traced to a rooftop condensing unit that was part of the air conditioning equipment serving the Sprint premises. Rennie discovered that some of the electrical connections had been made using improper materials and that the disconnected device on the unit had become corroded, allowing one of the three-phase wires to come in contact with the metal housing, causing the device to ground out. Rennie estimated that the condition had been in existence for six months to a year, and testified that the ground would not have prevented the air conditioning unit itself from continuing to operate properly.

The premises in the Caxton Building occupied by defendant Sprint had been occupied by various telecommunication companies since 1981, when Sprint’s predecessor, GTE Telenet, leased the space. At that time, GTE Telenet provided the Caxton Building management with copies of detailed drawings and electrical specifications for the build-out of its space.

After a bidding process, the contract for installing the ten-ton Trane air conditioning system (including two five-ton compressors) was awarded to Cooling Systems, Inc., and the necessary electrical hookup and wiring to the GTE Telenet premises was awarded to Ed Godenswager, d.b.a. Ed’s Electrical Service. The installation and electrical hookup of the air conditioning system was completed by February 9, 1982 in accordance with plans and applications on file with the city building department.

From March 1982 to September 1991, Cooling Systems provided monthly maintenance services to the rooftop air conditioning unit to ensure proper, normal operation. None of the Cooling Systems monthly reports revealed problems in the wiring, a potential for building-wide power fluctuations, or the need to repair or replace any electrical components.

In September 1991, Sprint contracted with York International to provide maintenance and repair services to its heating, ventilation and air conditioning equipment on a nationwide basis. York accordingly succeeded Cooling Systems in providing service and maintenance work on the rooftop air conditioning unit. The regularly scheduled service calls performed by York in April 1992 and June 1992 indicated no problems with the air conditioning equipment, other than the need to clean and/or change the filters more frequently than usual, due to excessive dirt and dust caused by the nearby Gateway construction.

On October 20, 1992, the Caxton Building management notified Sprint that Bohme had experienced malfunctions in its printing equipment which were traced to Sprint’s rooftop air conditioning unit. Sprint retained Cooling Systems to remove the offending unit and install a new indoor air conditioner for its fourth floor premises. The replacement was completed by November 17, 1992.

*727 Sprint had no problems with its air conditioning system between April and October 1992, and was unaware until the October 20 notice that Bohme was experiencing problems with voltage fluctuations, power shortages or equipment malfunctions in its business. No other tenant in the building was similarly affected.

Bohme brought this negligence action against Sprint, claiming damages from business interruptions resulting from the fluctuations in the electrical power supplied to its leased premises caused by the defective air conditioning unit serving Sprint’s premises. Bohme subsequently filed an amended complaint, joining Aetna Insurance Company as a party-plaintiff, which claimed it was subrogated to some of the losses incurred by Bohme, which Aetna had indemnified.

' Sprint answered and filed third-party claims for indemnity and contribution against Cooling Systems, York International and Ed Godenswager, d.b.a. Ed’s Electrical Service, in the event that Sprint was found liable to the plaintiffs. Plaintiffs filed no direct claims against these third parties, and the statute of limitations for filing such claims has now expired.

Bohme and Sprint filed cross-motions for summary judgment. In support of its motion, Sprint filed transcripts of deposition testimony and affidavits of witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wunderle v. Ohio Dept. of Transp.
2016 Ohio 1108 (Ohio Court of Claims, 2016)
Stewart v. Urig
893 N.E.2d 245 (Ohio Court of Appeals, 2008)
Sullivan v. Oregon Ford, Inc.
552 F. Supp. 2d 681 (N.D. Ohio, 2008)
Rettig v. Gen. Motors Corp., Unpublished Decision, (12-14-2006)
2006 Ohio 6576 (Ohio Court of Appeals, 2006)
Poiry v. Certified Power, Inc., Unpublished Decision (6-23-2006)
2006 Ohio 3183 (Ohio Court of Appeals, 2006)
Bultema v. United States
Sixth Circuit, 2004
James Bultema v. United States
359 F.3d 379 (Sixth Circuit, 2004)
Gore v. Ohio Department of Transportation
2002 Ohio 4263 (Ohio Court of Claims, 2002)
Estep v. Rieter Automotive North America, Inc.
774 N.E.2d 323 (Ohio Court of Appeals, 2002)
Frost v. Dayton Power and Light Company
138 Ohio App. 3d 182 (Ohio Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
686 N.E.2d 300, 115 Ohio App. 3d 723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bohme-inc-v-sprint-international-communications-corp-ohioctapp-1996.