Bogunia Electric, Inc., d/b/a Mr. Electric and Steven Bogunia v. James Yakym

CourtIndiana Court of Appeals
DecidedJanuary 22, 2015
Docket71A04-1405-CC-238
StatusUnpublished

This text of Bogunia Electric, Inc., d/b/a Mr. Electric and Steven Bogunia v. James Yakym (Bogunia Electric, Inc., d/b/a Mr. Electric and Steven Bogunia v. James Yakym) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bogunia Electric, Inc., d/b/a Mr. Electric and Steven Bogunia v. James Yakym, (Ind. Ct. App. 2015).

Opinion

Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing the defense of res judicata, collateral estoppel, or the law of the case.

ATTORNEY FOR APPELLANTS: Jan 22 2015, 10:06 am RICHARD J. LASALVIA South Bend, Indiana

IN THE COURT OF APPEALS OF INDIANA

BOGUNIA ELECTRIC, INC. ) d/b/a MR. ELECTRIC and ) STEVEN BOGUNIA, ) ) Appellants-Defendants/Counterplaintiffs, ) ) vs. ) No. 71A04-1405-CC-238 ) JAMES YAKYM, ) ) Appellee-Plaintiff/Counterdefendant. )

APPEAL FROM THE ST. JOSEPH SUPERIOR COURT The Honorable Jenny Pitts Manier, Judge Cause No. 71D05-1302-CC-134

January 22, 2015

MEMORANDUM DECISION - NOT FOR PUBLICATION

CRONE, Judge Case Summary

Bogunia Electric, Inc. d/b/a Mr. Electric appeals the trial court’s judgment in favor of

James Yakym on his complaint against it for breach of contract.1 The trial court found that

Bogunia Electric failed to provide a total house rewire as required under its contract with

Yakym and that its work did not comply with the Mishawaka Electrical Code (“the Code”)

and was unworkmanlike. The trial court found that Yakym was entitled to recover the costs

necessary to bring his home’s electrical system into compliance with the Code and up to a

workmanlike manner. On appeal, Bogunia Electric argues that there is no evidence in the

record to support the trial court’s findings that Bogunia Electric’s work did not comply the

Code and was unworkmanlike and that Yakym’s expert witness provided the best evidence

for the electrical work that needs to be done to bring the house into compliance with the

Code and to a workmanlike standard. It also asserts that Yakym did not suffer any damages.

We conclude that the trial court’s findings are supported by evidence in the record.

We are also unpersuaded by Bogunia Electric’s argument that Yakym did not suffer

damages. Accordingly, we affirm.

1 Pursuant to Indiana Appellate Rule 17(A), a party of record in the trial court shall be a party on appeal. In the notice of appeal, both Bogunia Electric and Steven Bogunia were named as appealing parties and attorney Richard LaSalvia failed to specify for whom he was filing an appearance. However, the trial court found that Steven Bogunia was not personally liable to Yakym, and the appellant’s brief appears to be written on behalf of Bogunia Electric only.

2 Facts and Procedural History

Yakym owns a home in Mishawaka. Steven Bogunia is a certified electrical

contractor who does business in Indiana and Michigan. Bogunia conducts his business

through Bogunia Electric, which uses the assumed name “Mr. Electric.” In August 2012,

Yakym contacted Bogunia Electric to obtain an estimate for electrical work to his home. A

representative from Bogunia Electric visited Yakym’s home, and Yakym showed him the

work he wanted done. Bogunia Electric subsequently sent Yakym a two-page proposal (“the

Proposal”). Page one of the Proposal set forth a summary of the work to be performed and

an estimated price for that work. The work to be performed was described as follows:

“Replace 100 A main breaker panel with new 100 main breaker panel[,] [g]round and bond

electrical service per code[, and] trace down bathroom circuits and rewire to eliminate knob

and tube.” Plaintiff’s Ex. 2. The estimated total cost for the work was $10,811.84. Page two

provided a room-by-room description of the electrical work to be completed.

Yakym decided that he wanted to upgrade his electrical service from 100 to 200 amps.

Bogunia sent Yakym an email stating that Bogunia Electric “agreed to upgrade to 200 [amp]

service for the 100 [amp] [Proposal] price,” and that “[a]ll the numbers are exactly as listed

in the original [Proposal].” Plaintiff’s Ex. 5. Yakym signed a one-page document (“the

Authorization”) that authorized Bogunia Electric to bill Yakym’s credit card. The

Authorization constitutes the contract between the parties. Plaintiff’s Ex. 4; Defendants’ Ex.

B. The Authorization does not expressly incorporate the Proposal by reference. The

3 Authorization describes the recommended repairs as “1- Replace 100A main breaker panel

with new 200A main breaker panel[,] 2 - Ground and bond service to code[, and] 3 - Trace

down bathroom circuits and rewire to eliminate knob and tube.” Id. Below that, the

Authorization lists specific tasks and provides the cost for each task as follows:

200 AMP Main Breaker 1,008.40 GROUND ELECTRICAL SERVICE 430.09 Rewire house and eliminate knob and tube. New devices. 11,175.49 1 YEAR PLAN 89.95 ADV PLAN DISCOUNT -1,892.09

Id. The total cost was $10,811.84. Id.

In October 2012, Bogunia Electric began electrical work on Yakym’s house. During

November and December 2012, Mishawaka electrical inspector Les Villanueva visually

inspected Yakym’s house three times to determine whether the electrical work performed by

Bogunia Electric complied with the Code. After the first two inspections, Villanueva

determined that work still needed to be done to bring the electrical system in compliance with

the Code. On his third visual inspection, Villanueva determined that the home’s electrical

system was in compliance with the Code and issued a letter stating, “The house has been

upgraded to a 200 amp service and its wiring, according to all visible evidence, is in good

working order. The system does meet the present requirements of the [Code].” Defendants’

Ex. J. By this time, Yakym had paid $6811.84 to Bogunia Electric under the contract.

In February 2013, Yakym filed a complaint against Bogunia Electric and Steven

Bogunia, alleging that (1) they failed to perform the work as promised in the Authorization;

(2) they failed to perform the work in a good and workmanlike manner and the work did not

4 meet the Code’s requirements; (3) the Authorization did not comply with the requirements of

the Home Improvement Contracts Act (“the Act”) and constituted a deceptive act; (4) as a

result of their failure to perform the work and their deceptive acts, he had been damaged in

excess of $20,000; and (5) he was entitled to treble damages under the Act because

defendants’ deceptive acts were part of a scheme, artifice, or device with intent to defraud or

mislead. Appellant’s App. at 13-14. Yakym also asked for attorney fees and costs. Bogunia

Electric filed a counterclaim against Yakym alleging that he failed to pay the full contract

amount and owed $4000 under the contract.

A bench trial was held. Yakym introduced the testimony of expert witness Thomas E.

McCormick, a licensed electrician and owner of McCormick Electrical Services. McCormick

had inspected Yakym’s home and determined that twenty-nine areas in Yakym’s electrical

system did not comply with the Code. McCormick prepared a report (“McCormick’s

Report”) identifying the electrical work that was needed to bring Yakym’s electrical system

in compliance with the Code and up to a workmanlike standard. Plaintiff’s Ex. 1. The cost

for this work was $19,013.15. McCormick’s Report included the following statement: “The

Electrical Inspector of the City of Mishawaka would be the ‘Authority having Jurisdiction’

and the final interpretation in regard to these and possibly other concerns with [the] residence

in the City of Mishawaka.” Id. On cross-examination, McCormick testified that “the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Insurance v. Freeman
847 N.E.2d 1047 (Indiana Court of Appeals, 2006)
Hopper Resources, Inc. v. Webster
878 N.E.2d 418 (Indiana Court of Appeals, 2007)
Bussing v. Indiana Department of Transportation
779 N.E.2d 98 (Indiana Court of Appeals, 2002)
JONES v. First Nat. Bank, Adm.
239 N.E.2d 398 (Indiana Court of Appeals, 1968)
Walker v. Cuppett
808 N.E.2d 85 (Indiana Court of Appeals, 2004)
Ferdinand Furn. Co., Inc. v. Anderson
399 N.E.2d 799 (Indiana Court of Appeals, 1980)
Cyr v. J. Yoder, Inc.
762 N.E.2d 148 (Indiana Court of Appeals, 2002)
L.H. Controls, Inc. v. Custom Conveyor, Inc.
974 N.E.2d 1031 (Indiana Court of Appeals, 2012)
Farah, LLC v. Architura Corp.
952 N.E.2d 328 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Bogunia Electric, Inc., d/b/a Mr. Electric and Steven Bogunia v. James Yakym, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bogunia-electric-inc-dba-mr-electric-and-steven-bogunia-v-james-indctapp-2015.