Bogue v. Sizemore

608 N.E.2d 1246, 241 Ill. App. 3d 250, 181 Ill. Dec. 772, 1993 Ill. App. LEXIS 181
CourtAppellate Court of Illinois
DecidedFebruary 18, 1993
Docket4-92-0457
StatusPublished
Cited by1 cases

This text of 608 N.E.2d 1246 (Bogue v. Sizemore) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bogue v. Sizemore, 608 N.E.2d 1246, 241 Ill. App. 3d 250, 181 Ill. Dec. 772, 1993 Ill. App. LEXIS 181 (Ill. Ct. App. 1993).

Opinions

JUSTICE GREEN

delivered the opinion of the court:

Plaintiff Robert O. Bogue (Robert), an excavation subcontractor, filed a small claims complaint against defendant Greg Sizemore (Size-more), seeking to recover on an alleged contract to perform excavation services as a subcontractor to Sizemore on a contract with a third party. Following a bench trial in the circuit court of Edgar County, that court entered judgment in favor of Robert and against Sizemore in the sum of $2,002.81 and costs. Sizemore appeals and we affirm.

The parties’ dispute centers on a written document signed by Sizemore, whereby Robert was to perform excavation work for Size-more for $2,700, in preparation for a commercial telephone system to be installed by Sizemore for Bredeman Ford, a car dealership in the Chicago area. Subsequent to entering into the contract with Bogue, Sizemore, however, was not awarded the contract by Bredeman Ford, and Robert, therefore, never performed the excavation work. In the trial court, a dispute arose as to whether Sizemore or the firm for which he was vice-president was the proper defendant. On appeal, Sizemore does not dispute that he was the proper party defendant. The dispute concerns whether Sizemore was contractually bound under the written document to pay Robert for the described work, as the court found, or whether any obligation of Sizemore to pay Robert for the work was at most conditioned upon Sizemore obtaining the contract to do the work for Bredeman Ford, as Sizemore contended.

The record does not contain a transcript of the evidence at the bench trial. However, a document is provided in the record, designated “Report of Proceedings,” but in the nature of a bystander’s report which was approved by the trial judge. It states that Robert testified as follows: (1) he owned a second business engaging in trenching and backhoe work as a contractor; (2) he previously worked for Sizemore as an operations manager at Sizemore’s prior communications business; (3) his brother, Ross Bogue (Ross), is part owner of Sizemore’s current communications business; (4) in November 1990 Ross called him concerning the potential subcontracting opportunity at Bredeman Ford; (5) the job was to be done independent of the communications business; (6) Sizemore subsequently discussed the job with him indicating it “would be a rush job which needed to be done immediately over the weekend of November 30 and December 1, 1990”; (7) the job consisted of “trenching and boring under driveways to lay cable to connect two automobile dealerships”; (8) he had previously done subcontract work for his brother and Sizemore personally, and for their communications business; (9) usually he would inspect the site and give his brother or Sizemore a “quote” on the trenching work, and they would use that bid in their bid for the overall contract; and (10) generally his brother or Sizemore would contact him for excavation bids.

Robert further testified that (1) prior to the weekend he was to begin work he sent a proposed contract by “fax machine” to Sizemore because “he would not agree to leave Paris or perform any work until he had received a signed contract” from Sizemore; (2) on November 29, 1990, the day before the job was scheduled to begin, he received by “fax machine” a copy of his proposed contract signed by Sizemore; (3) at 3:30 p.m. on November 29, 1990, just prior to receiving the signed contract, he received a call from his brother and Sizemore informing him the job was delayed for a week but “still on”; (4) he was told that the job was delayed because of a problem with obtaining the cable; (5) Sizemore agreed to pay his additional expenses due to the delay; (6) the delay continued until January 1991, when he was told that “the contract had died”; and (7) Sizemore told him “the contract would not be completed.”

Sizemore did not testify at the hearing; however, Robert’s brother, Ross, testified for the defense as follows: (1) in early 1990, Sizemore’s firm was invited by Bredeman Ford to submit a bid on an “integrated communications and computer system to be installed between two automobile dealerships owned by Bredeman Ford”; (2) he contacted Robert “so that he could look at the trenching work to be done as part of the general contract”; (3) he received a quote from Robert for the excavation work; (4) he used Robert’s quote in his bid for the general contract; (5) the next day after receiving the subcontract quote from Robert, Sizemore’s firm did not get the Bredeman Ford contract; (6) they continued to try and secure the Bredeman Ford contract for the next month to six weeks; (7) during that time they advised Robert they were trying to secure the contract, but had not yet been successful; and (8) he told Robert “there was no contract but they still had hopes of getting the contract as it had not been given to any other contractor.”

Ross further testified that the “quotation” signed by Sizemore was merely for internal use in the business, and that they use the “quotations in agreements with subcontractors to lock in subcontractor quotes prior to making general quotes to a perspective customer.” Ross denied that the Bredeman Ford job was independent of Size-more’s firm, and he denied ever telling Bogue that the Bredeman Ford contract was a “special deal not involving the corporation.” Finally, Ross testified that it was their practice to sign subcontract quotes to “indicate that the complete job was as described and to lock in the subcontract at the quoted price.”

The evidence included the written document prepared by Robert and signed by Sizemore, which was transmitted to Robert by fax machine on November 29, 1990, after Sizemore had informed Robert of a delay in the Bredeman Ford project. The document was on a form which had Robert’s name and company name printed on top, along with a listing of the various types of work which Robert did, including trenching and mechanical service, which had been circled. The form also had “Estimate/Invoice No.” printed on top. Handwritten on the form were the names of Ross Bogue and Sizemore, their company name, and a description of Robert’s work to be done for the Bredeman Ford project for $2,700. In small print were the “Conditions of Contract,” which, among other things, provided for progress payments “upon receipt of invoice.” The agreement was not expressly conditioned on Sizemore being awarded the Bredeman Ford contract. Sizemore’s signature appears on a line near the bottom of the document and under that line a statement was printed in the following words: “Signature indicates the price stated above is agreeable. Signee promises to pay for the above described work.”

On appeal, Sizemore does not dispute the court’s finding that the written document he signed was a binding contract. Rather, Size-more claims that the agreement was a binding bilateral contract conditioned on his being awarded the Bredeman Ford contract. Although the document did not expressly contain this condition, Sizemore claims that the condition should be implied. Sizemore bases his contention on a theory in construction contract law which purportedly indicates that bilateral contracts arising from bidding between a subcontractor and a general contractor are generally, as a matter of law, impliedly conditioned on the general contractor receiving the overall contract. The contract is conditional because the parties allegedly do not know at the time of contracting whether the general contractor will get the overall contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogue v. Sizemore
608 N.E.2d 1246 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
608 N.E.2d 1246, 241 Ill. App. 3d 250, 181 Ill. Dec. 772, 1993 Ill. App. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bogue-v-sizemore-illappct-1993.