Boehm Electrical Contractors, LLC v. Edward Rose Development Co.

2026 IL App (5th) 241159-U
CourtAppellate Court of Illinois
DecidedFebruary 13, 2026
Docket5-24-1159
StatusUnpublished

This text of 2026 IL App (5th) 241159-U (Boehm Electrical Contractors, LLC v. Edward Rose Development Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boehm Electrical Contractors, LLC v. Edward Rose Development Co., 2026 IL App (5th) 241159-U (Ill. Ct. App. 2026).

Opinion

NOTICE 2026 IL App (5th) 241159-U NOTICE Decision filed 02/13/26. The This order was filed under text of this decision may be NO. 5-24-1159 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the

Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1). APPELLATE COURT OF ILLINOIS

FIFTH DISTRICT ______________________________________________________________________________

BOEHM ELECTRICAL CONTRACTORS, LLC, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Champaign County. ) v. ) No. 18-CH-61 ) EDWARD ROSE DEVELOPMENT COMPANY, LLC, ) Honorable ) Jason M. Bohm, Defendant-Appellee. ) Judge, presiding. ______________________________________________________________________________

JUSTICE SHOLAR delivered the judgment of the court. Justices Moore and McHaney concurred in the judgment. ∗

ORDER

¶1 Held: The trial court did not err by granting defendant’s motion for summary judgment. The trial court did not abuse its discretion by awarding attorney fees to defendant. Further, the trial court did not err by denying plaintiff’s motion to reconsider.

¶2 Plaintiff, Boehm Electrical Contractors, LLC (Boehm), appeals the Champaign County

circuit court’s order granting summary judgment in favor of defendant, Edward Rose Development

Company, LLC (Edward Rose), and the trial court’s award of attorney fees to defendant. Boehm

appeals, arguing there were genuine issues as to material facts, and therefore the court erred by

granting defendant’s motion for summary judgment. Boehm further argues the court abused its

* Justice Moore fully participated in the decision prior to his retirement. See Cirro Wrecking Co. v. Roppolo, 153 Ill. 2d (1992). 1 discretion in awarding attorney fees to Rose. For the reasons that follow, we affirm the judgment

of the circuit court.

¶3 I. BACKGROUND

¶4 In 2015, Rose oversaw the construction of several apartment buildings in Champaign. In

April 2015, Rose first contracted with Boehm to provide underground electrical services, electrical

wiring, and electrical fixtures for three buildings in construction project. Those buildings were

designated as Buildings 13, 16, and 17 (electrical contract). In October 2015, Rose contracted with

Boehm to install cable and telecommunications wiring for the same three buildings (cable

contract). The contracts contained the following paragraphs:

“5. Contractor shall commence work promptly when notified and shall work continuously until work is completed. *** 13. If, in Builder’s opinion, Contractor fails to perform substantially in accordance with this contract, or is responsible for substantial delays and fails within 48 hours of written notice to satisfy all unsatisfactory matters, Builder may terminate this contract for all buildings, or for any specific building(s), included in this contract. Builder may avail himself of any legal remedies available to secure satisfaction of this contract. If Contractor fails to perform in accordance with the terms of this contract, Contractor shall pay all costs, including, without limitation, attorney fees, administrative expenses and court costs incurred by Builder in enforcing the terms of this contract.”

¶5 The terms of the electrical contract called for Boehm to be paid approximately $390,000,

50% to be paid upon completion of the “rough in” work and 50% to be paid upon completion of

the “finishing” work. The terms of the cable contract called for Boehm to be paid a total of $31,008,

45% to be paid upon completion of the “rough in” work and 55% to be paid upon completion of

the “finishing” work.

¶6 On October 6, 2017, Rose sent Boehm a letter (48-hour notice). That letter referenced the

“ELECTRICAL CONTRACT, DATED 4/6/15” and the “CABLE TV AND TELEPHONE

WIRING CONTRACT, DATED 10/22/15.” The body of the letter read as follows:

2 “This letter will serve as your ‘48 Hour Written Notice” in accordance with paragraph #13 of the above captioned contracts. You are responsible for substantial delays.

We have given you schedules for both Buildings #16 & 17, requesting you meet them. You have failed to do so and continue to fall further behind. You are now required to have Building #17 finish plumbing completed in the first three corridors by October 30, 2017 and the second three corridors by November 24, 2017, along with final inspections.

We are hereby requiring you to honor paragraph #5 of your contracts, man the job properly, commence work promptly when notified and work continuously until the work is completed. If you fail to perform, we will terminate the contracts and hire others to complete the work, charging the cost thereof to your account.”

¶7 On December 22, 2017, Rose sent a letter to Boehm terminating the contracts. That letter

referenced the same contracts and stated the following, in pertinent part:

“The purpose of this letter correspondence is to terminate the above captioned contracts.

On October 6, 2017, we sent you a completion date of November 24, 2017 for Building #17, including final inspections. As of today, December 22, 2017, the building is still not complete. You have not properly managed or manned this job and we cannot continue to wait for you to complete the work remaining on Building #16.[ ]

Once work is complete at Building #17, you will need to submit an invoice to the Jobsite Superintendent to receive payment. We will hire others to complete the remaining work on Building #16.[ ]” (Bold in original.)

On January 23, 2018, Boehm appeared on the job and was denied entry to the jobsite.

¶8 Boehm filed mechanic’s liens for each contract and against the property. On March 7, 2018,

Boehm filed a complaint requesting foreclosure on both mechanic’s liens. The complaint also

contained two counts for breach of contract, one for each contract. On May 11, 2018, Edward Rose

filed an answer, affirmative defenses, and a counterclaim alleging Boehm had breached the

contracts by failing (1) to provide adequate labor and materials, (2) to work continuously, (3) to

3 meet job completion and project schedules, and (4) to provide sworn statements and lien waivers

as provided by the contracts.

¶9 Boehm filed a motion for summary judgment on March 16, 2022. It was supported by an

affidavit signed by Patrick A. Boehm. In addition to claiming the monies owed, it stated:

“8. That Edward Rose *** refused to allow Boehm *** to complete the work on the job and ejected Boehm *** from the project, preventing Boehm from doing any further work. *** 12. That all labor and materials that my company provided were of excellent quality and improved the property and further allowed Edward Rose *** to complete the development project.”

Documentation attached to the Boehm affidavit included copies of the contracts, paid invoices,

unpaid invoices, and the mechanic’s liens.

¶ 10 On April 5, 2022, Edward Rose filed a response to Boehm’s motion for summary judgment.

Attached was a counteraffidavit signed by Jim Vincent (Rose affidavit), a construction manager

for Edward Rose. The Rose affidavit alleged, in part, that:

“9. Boehm failed to provide adequate labor and materials to meet job completion schedules and caused significant delays to the Project. *** 11. Boehm’s performance failures were raised during monthly construction meetings, including during the time period of June 1, 2017 through February 1, 2018.”

The Rose affidavit also asserted that Edward Rose properly terminated the contracts after

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaiser v. MEPC American Properties, Inc.
518 N.E.2d 424 (Appellate Court of Illinois, 1987)
Abdul-Karim v. First Federal Savings & Loan Ass'n
462 N.E.2d 488 (Illinois Supreme Court, 1984)
McNiff v. Mazda Motor of America, Inc.
892 N.E.2d 598 (Appellate Court of Illinois, 2008)
General Motors Acceptance Corp. v. Stoval
872 N.E.2d 91 (Appellate Court of Illinois, 2007)
Sameer v. Butt
796 N.E.2d 1063 (Appellate Court of Illinois, 2003)
State Farm Insurance v. American Service Insurance
773 N.E.2d 666 (Appellate Court of Illinois, 2002)
Mercado v. Calumet Federal Savings & Loan Ass'n
554 N.E.2d 305 (Appellate Court of Illinois, 1990)
J.B. Esker & Sons, Inc. v. Cle-Pa's Partnership
757 N.E.2d 1271 (Appellate Court of Illinois, 2001)
Mirar Development, Inc. v. Kroner
720 N.E.2d 270 (Appellate Court of Illinois, 1999)
Anthony Hill v. Daniel M. Tangherlini
724 F.3d 965 (Seventh Circuit, 2013)
Nissan Motor Acceptance Corp. v. Abbas Holding I
2012 IL App (1st) 111296 (Appellate Court of Illinois, 2012)
Liceaga v. Baez
2019 IL App (1st) 181170 (Appellate Court of Illinois, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2026 IL App (5th) 241159-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boehm-electrical-contractors-llc-v-edward-rose-development-co-illappct-2026.