Bodwell v. FDIC CV-96-021-B 07/05/96 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
In re Bodwell Development Trust Civil No. 96-021-B
Bodwell Development Trust
v.
Federal Deposit Insurance Corporation as Liquidating Agent for First Service Bank; Robie Construction, et al.
O R D E R
This bankruptcy appeal involves the competing claims of two
secured creditors to a fund of $250,000 remaining from the sale
of the debtor's real estate project. The Federal Deposit
Insurance Corporation ("FDIC"), as successor in interest to the
First Service Bank for Savings ("the Bank"), bases its claim on
the Bank's mortgage and the FDIC's payment of delinguent real
estate taxes on the Bodwell property. Robie Construction, Inc.
seeks payment for its work on the project secured by a mechanic's
lien attachment. The bankruptcy court held that Robie's
mechanic's lien attachment was timely as to all of its unpaid
work and had priority over both the FDIC's construction mortgage and its claim for reimbursement of the taxes paid. For the
reasons that follow, I affirm.
I. BACKGROUND
The background facts are taken from the bankruptcy court's
factual findings.1 The parties do not dispute the bankruptcy
court's factual findings on appeal, nor could they as they have
not provided a complete transcript or a full record of the
proceedings below. See In re Abiioe Realty Corp., 943 F.2d 121,
123 n.1 (1st Cir. 1991).
In October 1987, Bodwell Development Trust purchased a
multi-lot subdivision in Manchester. Bodwell intended to
complete single family houses on twenty-five lots in the first
phase of the development and to build a planned unit development
on the remaining parcel in the second phase.2 The first phase of
1 The bankruptcy court made factual findings in both its findings of fact order dated April 28, 1995, and in its memorandum opinion. In re Bodwell Development Trust, 187 B.R. 63 (Bankr. D.N.H. 1995). The findings of fact order references particular numbered exhibits that were not appended to the document and were not included in the record on appeal although some of the same documents seem to have been submitted as part of the "defendant's exhibits."
2 The second phase of the project is not at issue in this appeal.
2 the project was financed by the Bank in a series of mortgages
with security agreements executed in 1987 and 1988. Bodwell
hired Lexro Development Company as its general contractor.
Robie Construction contracted with Lexro to provide
materials and labor for site work on the Bodwell project. The
first contract, dated April 14, 1988, (the April contract),
specified work on lots 11, 12, 13, 14, 23, and 25 listing
separate prices for each lot totalling $25,625.00. The second
contract, dated May 19, 1988, (the May contract), specified work
and prices for lots 5, 6, 7, 8, 9, and 10 for a total of
$82,901.75. Robie last worked on a lot listed in the April
contract on December 15, 1988, and last worked on a lot listed in
the May contract on December 14, 1988. Robie was not paid for
its materials and labor and brought suit against Bodwell and
Lexro in Hillsborough County Superior Court on February 3, 1989.
Robie recorded an ex parte mechanic's lien attachment on
February 21, 1989,3 in the amount of $200,000 on Bodwell's first
3 The bankruptcy court's factual findings state that Robie obtained ex parte permission from Hillsborough County Superior Court on February 22, 1989, to record the attachment. See Findings of Fact No. 19. The bankruptcy court also found that Robie filed its ex parte attachment on February 21, 1989, referencing "Exhibit 7," which is not included in the record on appeal. See Findings of Fact No. 35. As the parties do not
3 phase lots numbered one through fourteen, sixteen, eighteen
through twenty-six, and twenty-eight. The attachment was
recorded within ninety days of work done on only one lot listed
in the April contract and two lots in the May contract. On
November 6, 1989, the state court granted Robie a final default
judgment against Bodwell, and Robie recorded a writ of execution
against Bodwell on January 10, 1990.
The FDIC was appointed liguidating agent for the Bank in
March 1989. Thereafter, the FDIC paid delinguent real estate
taxes to the City of Manchester for the years 1988 through 1990
on the lots in the first phase of the project after Robie
recorded its mechanic's lien attachment. Bodwell filed a Chapter
11 bankruptcy petition on November 8, 1993. At the time Bodwell
filed its petition, the FDIC's claim against Bodwell for the
Bank's first phase mortgages exceeded one million dollars. The
first phase lots in Bodwell's development project were sold
pursuant to the reorganization plan for a total of $625,000.00.
Bodwell brought an adversary proceeding in the bankruptcy
court to resolve the claims of several creditors to the proceeds
dispute the date or validity of Robie's mechanic's lien attachment, I merely note the apparent inconsistency in the factual findings.
4 of the sale of the property. The parties submitted a statement
of stipulated and disputed facts, and a hearing was held in
August 1994. After the hearing, the FDIC filed a motion to
reopen the hearing record for new evidence pertaining to the type
of mortgage the Bank granted to Bodwell. The bankruptcy court
held a hearing on the FDIC's motion in December 1994 and denied
the motion to reopen in an oral order.
After the claims of several creditors were resolved,
$250,000.00 remained in the fund subject to the FDIC's mortgage
claims, which exceed the amount of the fund, the FDIC's claim for
payment of real estate taxes of $117,153.81, and Robie's
mechanic's lien claim for $108,525.00. The bankruptcy court
issued findings of fact dated April 28, 1995, and heard the
parties' oral arguments in June. The bankruptcy court issued its
memorandum decision on August 3, 1995, in which it determined
that Robie's claim, based on its mechanic's lien attachment, was
prior to the FDIC's claims for the Bank's mortgages and for
payments of real estate taxes on the mortgaged property. The
FDIC appeals.
5 II. ANALYSIS
On appeal, the FDIC contends that the bankruptcy court
abused its discretion in denying its motion to reopen the hearing
record on the relative priority of its mortgage claims with
respect to Robie's claim. The FDIC also contends that the
bankruptcy court erred in determining that Robie's mechanic's
lien attachment was timely as to work done more than ninety days
before the lien was perfected, and by determining that Robie's
mechanic's lien attachment was entitled to priority over the
FDIC's claims for payment of the delinguent property taxes. I
begin with the bankruptcy court's decision not to reopen the
hearing record to allow additional evidence.
A. FDIC's Motion to Reopen the Hearing
A trial court is granted broad discretion in determining
whether to reopen the evidentiary record, and its decision is
Free access — add to your briefcase to read the full text and ask questions with AI
Bodwell v. FDIC CV-96-021-B 07/05/96 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
In re Bodwell Development Trust Civil No. 96-021-B
Bodwell Development Trust
v.
Federal Deposit Insurance Corporation as Liquidating Agent for First Service Bank; Robie Construction, et al.
O R D E R
This bankruptcy appeal involves the competing claims of two
secured creditors to a fund of $250,000 remaining from the sale
of the debtor's real estate project. The Federal Deposit
Insurance Corporation ("FDIC"), as successor in interest to the
First Service Bank for Savings ("the Bank"), bases its claim on
the Bank's mortgage and the FDIC's payment of delinguent real
estate taxes on the Bodwell property. Robie Construction, Inc.
seeks payment for its work on the project secured by a mechanic's
lien attachment. The bankruptcy court held that Robie's
mechanic's lien attachment was timely as to all of its unpaid
work and had priority over both the FDIC's construction mortgage and its claim for reimbursement of the taxes paid. For the
reasons that follow, I affirm.
I. BACKGROUND
The background facts are taken from the bankruptcy court's
factual findings.1 The parties do not dispute the bankruptcy
court's factual findings on appeal, nor could they as they have
not provided a complete transcript or a full record of the
proceedings below. See In re Abiioe Realty Corp., 943 F.2d 121,
123 n.1 (1st Cir. 1991).
In October 1987, Bodwell Development Trust purchased a
multi-lot subdivision in Manchester. Bodwell intended to
complete single family houses on twenty-five lots in the first
phase of the development and to build a planned unit development
on the remaining parcel in the second phase.2 The first phase of
1 The bankruptcy court made factual findings in both its findings of fact order dated April 28, 1995, and in its memorandum opinion. In re Bodwell Development Trust, 187 B.R. 63 (Bankr. D.N.H. 1995). The findings of fact order references particular numbered exhibits that were not appended to the document and were not included in the record on appeal although some of the same documents seem to have been submitted as part of the "defendant's exhibits."
2 The second phase of the project is not at issue in this appeal.
2 the project was financed by the Bank in a series of mortgages
with security agreements executed in 1987 and 1988. Bodwell
hired Lexro Development Company as its general contractor.
Robie Construction contracted with Lexro to provide
materials and labor for site work on the Bodwell project. The
first contract, dated April 14, 1988, (the April contract),
specified work on lots 11, 12, 13, 14, 23, and 25 listing
separate prices for each lot totalling $25,625.00. The second
contract, dated May 19, 1988, (the May contract), specified work
and prices for lots 5, 6, 7, 8, 9, and 10 for a total of
$82,901.75. Robie last worked on a lot listed in the April
contract on December 15, 1988, and last worked on a lot listed in
the May contract on December 14, 1988. Robie was not paid for
its materials and labor and brought suit against Bodwell and
Lexro in Hillsborough County Superior Court on February 3, 1989.
Robie recorded an ex parte mechanic's lien attachment on
February 21, 1989,3 in the amount of $200,000 on Bodwell's first
3 The bankruptcy court's factual findings state that Robie obtained ex parte permission from Hillsborough County Superior Court on February 22, 1989, to record the attachment. See Findings of Fact No. 19. The bankruptcy court also found that Robie filed its ex parte attachment on February 21, 1989, referencing "Exhibit 7," which is not included in the record on appeal. See Findings of Fact No. 35. As the parties do not
3 phase lots numbered one through fourteen, sixteen, eighteen
through twenty-six, and twenty-eight. The attachment was
recorded within ninety days of work done on only one lot listed
in the April contract and two lots in the May contract. On
November 6, 1989, the state court granted Robie a final default
judgment against Bodwell, and Robie recorded a writ of execution
against Bodwell on January 10, 1990.
The FDIC was appointed liguidating agent for the Bank in
March 1989. Thereafter, the FDIC paid delinguent real estate
taxes to the City of Manchester for the years 1988 through 1990
on the lots in the first phase of the project after Robie
recorded its mechanic's lien attachment. Bodwell filed a Chapter
11 bankruptcy petition on November 8, 1993. At the time Bodwell
filed its petition, the FDIC's claim against Bodwell for the
Bank's first phase mortgages exceeded one million dollars. The
first phase lots in Bodwell's development project were sold
pursuant to the reorganization plan for a total of $625,000.00.
Bodwell brought an adversary proceeding in the bankruptcy
court to resolve the claims of several creditors to the proceeds
dispute the date or validity of Robie's mechanic's lien attachment, I merely note the apparent inconsistency in the factual findings.
4 of the sale of the property. The parties submitted a statement
of stipulated and disputed facts, and a hearing was held in
August 1994. After the hearing, the FDIC filed a motion to
reopen the hearing record for new evidence pertaining to the type
of mortgage the Bank granted to Bodwell. The bankruptcy court
held a hearing on the FDIC's motion in December 1994 and denied
the motion to reopen in an oral order.
After the claims of several creditors were resolved,
$250,000.00 remained in the fund subject to the FDIC's mortgage
claims, which exceed the amount of the fund, the FDIC's claim for
payment of real estate taxes of $117,153.81, and Robie's
mechanic's lien claim for $108,525.00. The bankruptcy court
issued findings of fact dated April 28, 1995, and heard the
parties' oral arguments in June. The bankruptcy court issued its
memorandum decision on August 3, 1995, in which it determined
that Robie's claim, based on its mechanic's lien attachment, was
prior to the FDIC's claims for the Bank's mortgages and for
payments of real estate taxes on the mortgaged property. The
FDIC appeals.
5 II. ANALYSIS
On appeal, the FDIC contends that the bankruptcy court
abused its discretion in denying its motion to reopen the hearing
record on the relative priority of its mortgage claims with
respect to Robie's claim. The FDIC also contends that the
bankruptcy court erred in determining that Robie's mechanic's
lien attachment was timely as to work done more than ninety days
before the lien was perfected, and by determining that Robie's
mechanic's lien attachment was entitled to priority over the
FDIC's claims for payment of the delinguent property taxes. I
begin with the bankruptcy court's decision not to reopen the
hearing record to allow additional evidence.
A. FDIC's Motion to Reopen the Hearing
A trial court is granted broad discretion in determining
whether to reopen the evidentiary record, and its decision is
reviewed only for abuse of that discretion. Blinzler v. Marriott
Intern., Inc., 81 F.3d 1148, 1160 (1st Cir. 1996) (citing Zenith
Radio Corp. v. Hazeltine Research, Inc., 401 U.S. 321, 331-32
(1971)). Fairness is the guiding principle in making and
reviewing a decision on reopening the record, and the "trial
court abuses its discretion if its refusal to reopen works an
'injustice' in the particular circumstances." Rivera-Flores v.
6 Puerto Rico Tel. Co., 64 F.3d 742, 746 (1st Cir. 1995). In
evaluating the potential for injustice in particular
circumstances, the court should assess whether:
(1) the evidence sought to be introduced is especially important and probative; (2) the moving party's explanation for failing to introduce the evidence earlier is bona fide; and (3) reopening will cause no undue prejudice to the nonmoving party.
Id.; see also Blinzler, 81 F.3d at 1160. I review the bankruptcy
court's decision only to determine whether it abused its
discretion.
New Hampshire law provides that a mechanic's lien attachment
shall have priority over a construction mortgage. N.H. Rev.
Stat. Ann. § 447:12-a (1991). The FDIC stipulated that the each
of the Bank's mortgages to Bodwell was a "Construction Mortgage
and Security Agreement." The bankruptcy court held a hearing on
the relative priorities of the mortgagee's and mechanic's
lienholders' claims to the Bodwell fund in August 1994. The FDIC
did not argue or present evidence in its pleadings or at the
hearing that the Bank's mortgages were other than construction
mortgages.
After the hearing but before the bankruptcy court decided
the parties' priorities, the New Hampshire Supreme Court issued
Lewis v. Shawmut Bank, 139 N.H. 50 (1994), in which the court
7 enforced an exception to the priority rule imposed by § 447:12-a
when the loan was made for both the land purchase and
construction. The FDIC then moved to introduce evidence that the
Bank's mortgage loan to Bodwell was a "mixed" loan intended to
finance both the property purchase and project construction
arguing only that the record should be reopened because the Lewis
decision was a new interpretation of the priority rule.
The bankruptcy court denied the FDIC's motion on the grounds
that the Lewis decision did not present a sufficiently new
interpretation of the priority statute to justify allowing the
FDIC to withdraw its stipulation that the Bank's loans to Bodwell
were construction mortgages. As noted by the bankruptcy court,
the decision in Lewis, followed Gerritv Co., Inc. v. Laconia
Savings Bank, 120 N.H. 304 (1980), in which the court considered
the bank's claim of an exception to the priority rule under §
447:12-a if the mortgage payments were made for purposes other
than financing construction. In Gerritv, the court held that the
bank's advancement of funds in part for the mortgagor's land
purchase did not exempt that portion of the mortgage from the
priority rule in § 447:12-a because the purpose of the loan was
determined by the loan agreement, which was to finance
construction, not by the disbursements. Id. at 307. Although the Lewis decision may have focused attention on the "mixed
mortgage" exception to the priority rule and may have clarified
the proof necessary to meet the exception, it did not change the
law. Therefore, when the FDIC stipulated that the bank's loans
were construction mortgages and presented evidence at the August
hearing, it should have known the significance of evidence
suggesting that the loan agreement was to finance the purchase of
the property as well as for construction. Thus, the FDIC did not
fall into erroneous and prejudicial stipulations based on a
justifiable legal mistake. See, e.g., I I Federal Credit Union
v. Delbonis, 72 F.3d 921, 928 (1st Cir. 1995) (parties are not
free to extricate themselves from stipulations absent "a clear
mistake" or "a manifest injustice"); Wheeler v. John Deere Co.,
935 F.2d 1090, 1097-98 (10th Cir. 1991) (stipulation must be
based on a reasonable mistake of law for relief to be
appropriate).
The FDIC's stipulations may have been erroneous and
certainly had a significant effect on the priority of its claim
behind Robie's mechanic's lien pursuant to § 447:12-a. In
addition, the bankruptcy court acknowledged that reopening the
record would not cause unfair prejudice to Robie. Nevertheless,
the bankruptcy court decided that it was inappropriate to relieve the FDIC from its stipulations because such stipulations would be
of little value to the parties or the court in future cases if a
party could avoid the enforcement of a stipulation merely by
demonstrating that its decision to enter into the stipulation was
based on an incorrect legal judgment. Although I might reach a
different conclusion if I were reviewing the matter de novo, the
bankruptcy court did not abuse its discretion in balancing the
competing interests in the way that it did.
B. Timeliness of Robie's Mechanic's Lien Attachment
Under New Hampshire law, a subcontractor, who performs labor
or provides materials for construction "by virtue of a contract
with an agent, contractor or subcontractor of the owner" and who
meets the other statutory reguirements, has a lien on the
materials, the buildings, and the land where the project is
located. N.H. Rev. Stat. Ann. § 447:5 (1991) . A mechanic's lien
may be secured "by an attachment of the property upon which it
exists at any time while the lien continues." N.H. Rev. Stat.
Ann. § 447:10 (1991). When Robie obtained its mechanic's lien
attachment in February 1989, the mechanic's lien statute provided
10 that the lien would continue for ninety days4 after the
subcontractor provided services or materials. N.H. Rev. Stat.
Ann. § 447:9 (1991) .
Robie filed its attachment after it completed all of the
work described in the two contracts, rather than filing
attachments as it completed the specified work on each lot. When
the attachment was filed, Robie had worked on only three lots
within the preceding ninety days, one lot specified in the April
contract and two lots specified in the May contract. The FDIC
argues that Robie's mechanic's lien attachment was untimely and
invalid as to the lots not worked on within the statutory ninety
day period.
The New Hampshire Supreme Court has not addressed the
timeliness of a mechanic's lien attachment in this context.
Other jurisdictions generally have held that an attachment filed
within the statutory period following the last work on a project
is timely as to the property as a whole when the property is
owned by a single owner and the construction contract provides
for work on a single project although it consists of separate
4 The statute was amended effective January 1, 1992, to allow the lien to continue for 120 days.
11 lots or buildings. See, e.g. S.K. Drvwall, Inc. v. Developers
Financial Group, Inc., 819 P.2d 931, 933-35 (Ariz. 1991) (single
lien may be filed within statutory period following end of work
on a single project under a single contract and discussing cases
from other jurisdictions); see also First Nat. Bank v. Hemingway
Center Ltd., 846 F. Supp. 186, 189 (D. Conn. 1994) (materials and
labor provided for two of three condominium buildings benefitted
entire project so that lien was properly recorded on entire
property); Annotation, Mechanic's Lien for Work on or Material
for Separate Buildings of One Owner, 15 A.L.R.3d 73, § 11 (1967
and Supp. 1995). The FDIC does not dispute that the Bodwell
development was a single project consisting of a subdivision of
individual lots all owned by a single owner.
The FDIC argues, however, that the Robie contracts are
divisible and should be construed as individual contracts for the
work on each separate lot specified. Under New Hampshire law,
"[i]f the parties gave a single assent to the whole transaction,
the contract is indivisible, while it is divisible if they
assented separately to several things." In re Trailer and
Plumbing Supplies, 133 N.H. 432, 435 (1990) (guotation omitted).
The bankruptcy court found that in the context of
construction financing, a developer must get a construction
12 lending commitment and the lender requires proof that the project
is moving forward to continue to advance money. As a result,
subcontractors' contracts often include "progress payment
accounting" features, such as the work and prices specified for
individual lots in the Robie contracts, to show what will be
charged for work on each lot. The bankruptcy court also found
that Robie's contracts covered all of the site work for the
Bodwell project, and that Robie was obligated to provide all of
the work specified. The court found that Robie could have been
sued for breach if it failed to perform any part of the specified
work even if it completed all other specifications, and Robie
could have sued Lexro if it breached its commitment to Robie for
all of the work specified. Bodwell, 187 B.R. at 65.
Thus, while each of the two contracts specified particular
work on particular lots, the facts show that the parties agreed
to the work specified in each contract as a single transaction.
In addition, because Robie was hired to provide all of the site
work for the project, the work benefitted the entire project, not
just the individual lots. The FDIC has presented no facts to
support a contrary conclusion. Under these circumstances, the
FDIC's arguments fail, and I affirm the bankruptcy court's
13 decision that Robie's lien attachment was timely filed.
C. Priority of Claim for Property Taxes
The FDIC argues that its claim for payment of the delinquent
property taxes is entitled to priority over Robie's mechanic's
lien claim. Because the remaining fund of $250,000 is sufficient
to pay both Robie's claim of $108,525.00 and the FDIC's property
tax claim of $117,153.81, the issue of their relative priority is
now immaterial and, therefore, moot. Accordingly, I need not
determine their relative priority.
The FDIC apparently presented a different argument to the
bankruptcy court claiming a right to reimbursement from Robie for
the amount of the taxes which would completely offset Robie's
claim leaving the entire $250,000 fund available to the FDIC. In
re Bodwell, 187 B.R. at 66. The FDIC has not pressed this
argument on appeal. Therefore, I do not address the bankruptcy
court's decision on the question.
CONCLUSION
For the foregoing reasons, the decision of the bankruptcy
court is affirmed.
14 SO ORDERED.
Paul Barbadoro United States District Judge
July 5, 1996
cc : Jennifer Rood, Esq. Douglas Mclninch, Esq. George Vannah, USBC