BOC GROUP v. Lummus Crest

597 A.2d 1109, 251 N.J. Super. 271, 1990 N.J. Super. LEXIS 513
CourtNew Jersey Superior Court Appellate Division
DecidedAugust 3, 1990
StatusPublished
Cited by27 cases

This text of 597 A.2d 1109 (BOC GROUP v. Lummus Crest) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BOC GROUP v. Lummus Crest, 597 A.2d 1109, 251 N.J. Super. 271, 1990 N.J. Super. LEXIS 513 (N.J. Ct. App. 1990).

Opinion

251 N.J. Super. 271 (1990)
597 A.2d 1109

THE BOC GROUP, INC., PLAINTIFF,
v.
LUMMUS CREST, INC., A CORPORATION, ET AL., DEFENDANTS.

Superior Court of New Jersey, Law Division Bergen County.

Decided August 3, 1990.

*273 David R. Gross argued the cause for defendants (Budd, Larner, Gross, Rosenbaum, Greenberg & Sade, attorneys: David J. Novack, Leonard T. Nuara and Daniel Feuerstein, on the brief).

Richard E. Brennan argued the cause for plaintiff (Shanley & Fisher, P.C., attorneys; A. Dennis Terrell and Richard E. Brennan, on the brief)

MEEHAN, J.S.C.

This case is before the court on defendant, Lummus' motion to dismiss the 12th count of plaintiff's complaint alleging violations of the Consumer Fraud Act. N.J.S.A. 56:8-1, et seq.

This case arises from the design, engineering and operation of a plant in Texas intended to manufacture needle coke, which is used to produce graphite electrodes. Needle coke can be produced from various petroleum-derived feedstocks, including decant oil and pyrolysis tar.

Since the late 1960's, defendants, Lummus Co. (Lummus) and Maruzen Petrochemical Co. (Maruzen), had been conducting research and development efforts to produce high-quality needle coke from pyrolysis tars. Decant oil was the most often used feedstock at this point in time.

Plaintiff's subsidiary, Airco, after evaluating needle coke samples produced from pyrolysis tars by both Lummus and Maruzen, contacted defendant, Maruzen in 1976 in reference to Maruzen's research. In 1979, plaintiff began looking into the construction of its own needle coke production plant in conjunction with proposed plans to build another graphite electrode manufacturing plant. Plaintiff contacted Lummus and two other engineering companies to investigate the feasibility of constructing a plant which would produce needle coke from pyrolysis tar. Airco then authorized pilot plan tests, using defendants' technology, at each of three competing engineering companies and spent months performing tests to evaluate needle *274 coke samples supplied by the engineering companies to determine if it had the characteristics to produce graphite electrodes.

On May 28, 1980, plaintiff, after reviewing proposals from the three engineering companies, selected Lummus to design a commercial needle coke plant based on a modified "L Process". Between 1980 and 1981, Airco had Lummus perform numerous pilot plant tests using additional feedstocks to aid in the design of a commercial scale plant. Airco determined the suitability of each coke sample for the production of its graphite electrodes. In November, 1980, Airco contracted with the engineering company of Foster Wheeler to build a pilot plant in Niagara Falls, New York, to allow it to conduct tests using the modified "L Process".

Airco conducted studies of market demand and anticipated market share for its proposed coke needle plant which included investment and operation cost estimates from Foster Wheeler and Lummus and the retention of independent consultants. Airco also studied the use of decant oil rather than pyrolysis tar in the production of needle coke. In April, 1981, a Lummus feedstock screening study revealed that the plant production would be less than the designated needle coke production with Exxon pyrolysis tar, than if other pyrolysis tar and decant oil were used. Airco then authorized Lummus to redesign the plant using Airco, CCPC and Shell pyrolysis tars.

In June of 1981, Lummus gave Airco an initial product specification and performance guarantee based on the use of Exxon pyrolysis tar in the production of needle coke. In July of 1981, Airco requested that CCPC pyrolysis tar feedstock be used as the basis for guarantees, rather than the Exxon tar. Also during July, Airco's parent, the BOC Group (BOC), authorized $115 million for construction of the coke plant but required that the plant also be designed for the designated needle coke production rate when utilizing a decant oil stock. Due to this extra requirement BOC authorized an additional $5 million *275 for design, engineering and construction. Airco further directed Lummus to conduct pilot plant tests with two additional decant oils.

Between 1978 and 1982, Airco manufactured and tested electrodes made from needle coke derived from Shell pyrolysis tar. Airco advised Shell that it would make no further purchases of Shell's needle coke, due to the poor performance of the resulting electrodes. Also by 1982, Airco had conducted over 50 tests at its Niagara Falls pilot plant using over one dozen different pyrolysis tar and decant oil feedstock.

During Airco's fiscal year 1982, due to a severe drop in the demand for steel, Airco suffered a 22 percent decrease from the prior year in its graphite electrode shipments, which was in sharp contrast to its projections of a 23 percent increase in shipments. Airco also learned that the only commercially available pyrolysis tar derived needle coke, from Shell, was unsuitable for producing its graphite electrodes.

In March of 1983, after intense negotiations, Lummus and Airco agreed upon and signed the Engineering Services Agreement and Licensing Agreement. This agreement contained a clause which limited Lummus' total liability to $2 million for "all obligations, agreements, representations, warranties or guarantees." The agreement also provided that Lummus shall not be liable "for any special, incidental, indirect, or consequential damage of any nature", regardless of whether such claims were based on contract, tort or otherwise.

The Seadrift plant construction took over 18 months and cost approximately $125 million. The plant processed feedstock for the first time in September of 1983 but had to be shut down shortly thereafter due to mechanical problems. In March of 1984, the plant became fully operational and Airco, after firing its own plant manager, requested that Lummus conduct a comprehensive training program for its plant staff.

Subsequently, certain claims were made and agreements entered into which are not relevant to this decision. Additionally, *276 both parties agreed to embark on a Coke Quality Improvement Program (CQIP) using pyrolysis tar. The program's goal was to improve the quality of needle coke produced from pyrolysis tar to a level higher than that specified in the contractual guarantees. At this time, the plant was producing needle coke predominantly from decant oil. Both parties exchanged information, performed tests and prepared reports through October of 1985.

On June 19, 1985, Airco and Lummus management representatives met to discuss Lummus' rumored equity participation in a needle coke project undertaken by ANIC, an Italian petrochemical producer. Lummus told Airco that it was about to sign a contract with ANIC to build a needle coke plant in Italy that would use the M-L Process and not the L-Process used by Airco.

Airco was concerned that information it revealed during the CQIP would be utilized by Lummus in the design of the plant in Italy. Airco indicated that it was unhappy with the performance of the Seadrift plant and that its legal staff had recommended the commencement of a lawsuit against Lummus based on fraud. On July 11, 1985, Lummus assured Airco that it would take strict precautions to prevent Airco information and data from being utilized in the ANIC project.

On October 23, 1985, Lummus transmitted to Airco the final report on the experimental portion of the CQIP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Heartland Payment Systems, Inc.
834 F. Supp. 2d 566 (S.D. Texas, 2011)
539 Absecon Boulevard, LLC v. Shan Enterprises Limited P'ship
967 A.2d 845 (New Jersey Superior Court App Division, 2009)
Finderne Mgmt. Co. v. Barrett
955 A.2d 940 (New Jersey Superior Court App Division, 2008)
South Broward Hospital District v. Medquist Inc.
516 F. Supp. 2d 370 (D. New Jersey, 2007)
Papergraphics Intern., Inc. v. Correa
910 A.2d 625 (New Jersey Superior Court App Division, 2006)
In Re Managed Care Litigation
298 F. Supp. 2d 1259 (S.D. Florida, 2003)
Kavry v. Herbalife International of America
820 A.2d 677 (New Jersey Superior Court App Division, 2003)
Kavky v. HERBALIFE INTERNATIONAL
820 A.2d 677 (New Jersey Superior Court App Division, 2003)
Bracco Diagnostics Inc. v. Bergen Brunswig Drug Co.
226 F. Supp. 2d 557 (D. New Jersey, 2002)
Arc Networks, Inc. v. Gold Phone Card Co.
756 A.2d 636 (New Jersey Superior Court App Division, 2000)
Electric Mobility Corp. v. Bourns Sensors/Controls, Inc.
87 F. Supp. 2d 394 (D. New Jersey, 2000)
Naporano Iron & Metal Co. v. American Crane Corp.
79 F. Supp. 2d 494 (D. New Jersey, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
597 A.2d 1109, 251 N.J. Super. 271, 1990 N.J. Super. LEXIS 513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boc-group-v-lummus-crest-njsuperctappdiv-1990.