Board of Supervisors v. Pennsylvania Public Utility Commission

41 A.3d 142, 2012 WL 112213, 2012 Pa. Commw. LEXIS 23
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 13, 2012
Docket1624 C.D. 2009
StatusPublished
Cited by1 cases

This text of 41 A.3d 142 (Board of Supervisors v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Supervisors v. Pennsylvania Public Utility Commission, 41 A.3d 142, 2012 WL 112213, 2012 Pa. Commw. LEXIS 23 (Pa. Ct. App. 2012).

Opinions

OPINION BY

Judge PELLEGRINI.

Springfield Township petitions for review of an order of the Pennsylvania Public Utility Commission (Commission) granting a certificate of public convenience to PPL Electric Utility Corporation (PPL) to construct a seven-mile high-voltage (HV) electric transmission line and substation using the “PPL Functional Configuration” rather than the “Springfield Configuration.” For the reasons that follow, we affirm the Commission’s decision.

I.

This case deals with the need for an upgrade to Lehigh Valley’s HV electric transmission network and the best way to meet that need. Due to the rapid growth in PPL’s southern Lehigh Valley region, a great demand has been placed on PPL’s existing electrical facilities and it has to reinforce the existing 69 kV transmission system serving Northern Bucks and Southern Lehigh and Northampton Counties. The problems consist of conductor and transformer overloads and low voltage, as well as the long range requirements for PPL’s Southern Lehigh region up through the year 2020. Failure to reinforce the facilities affects reliable service to the public and will create the potential for loss of service to many of PPL’s customers in the area.

To alleviate this problem, PPL engineers need to evaluate electrical solutions or “functional configurations” to identify the best solutions to resolve the reliability issues. “A ‘functional configuration’ is a potential electrical solution that addresses the reliability issues based upon engineering considerations as determined by engineers in PPL electric’s Planning Department ... (Citations omitted.) Stated otherwise, a functional configuration is simply an electrical solution; it does not identify or evaluate the project location or alternative routes for the associated transmission lines.” (PPL’s brief at 13.) PPL further explained that after the functional configurations are identified, it compares and selects the one configuration that best meets its customers’ electric needs in a reliable manner over its planning horizon which, in this case, would be until the year 2020:

The evaluation of alternative functional configurations considers the ability of each solution to solve the original reliability problem and provide the ability and flexibility to meet future system needs, as well as the overall cost. Importantly, a full siting analysis is not part of the initial determination of alternative functional configurations; rather, a functional configuration is selected on the basis of how well it accomplishes PPL Electric’s statutory obligation to provide safe and reliable service to its customers over time and at a reasonable cost. Simply stated, a full siting analysis, including consideration of the environmental impacts, is not conducted at this stage because a functional configuration is not an alternative route for a high voltage transmission line but, rather, is a possible electrical or engineering [144]*144solution to an identified reliability problem.

(PPL’s brief at 13-14.)

In this case, PPL studied two functional configurations for enhancing the reliability of its transmission grid in the region. The first option, referred to as the “Springfield Functional Configuration,” involved constructing a new three or four-mile HV transmission line. The second option, referred to as the “PPL Functional Configuration,” involved constructing a new substation in Springfield Township and constructing a new six-or-seven-mile HV transmission line beginning in Southern Lehigh County and traversing through Springfield and Richland Townships in Northern Bucks County. PPL selected the PPL Functional Configuration because it believed that method was less expensive and provided flexibility for predicted future system expansion needs. Specifically, the PPL Functional Configuration would eliminate overload and excessive voltage drop violations and improve reliability by providing additional high-capacity transmission lines and increased substation transmission capacity for the region. It would also improve transfer capability for load restoration and increase load sectionalizing flexibility for line maintenance. Without the new substation, the load would be served by the Hosensack substation which was eight miles away and would not provide the same benefits, reliability and flexibility. The Springfield Functional Configuration would not provide the degree of load transfers and re-sectionalizing of load because of the magnitude of customer load supplied by the longer transmission paths. It would also require longer lines; would require transformer reinforcements at existing regional substations; and would require rebuilding the substation structures, which would be difficult because all substation loads would need to be transferred away to temporary substation facilities during construction. It would also have substantial social impacts because the transmission lines would cross densely populated areas and impact numerous homes. Last, but not least, the cost of the PPL Functional Configuration, for just those portions to be constructed through 2011, was $36 million compared to the $41 million it would cost to construct the Springfield Functional Configuration for the same time period.

After PPL chose the PPL Functional Configuration, it then presented the preferred functional configuration to PPL’s siting team which conducted a general review of the relevant area. This included a preliminary consideration of the environmental impacts of the selected functional configuration. If the siting team had found the selected functional configuration had significant environmental or other relevant impacts, the siting team would have communicated its concerns to the planning department for further consideration of an alternative functional configuration. Because that did not occur, the siting team then conducted a full siting analysis to identify and analyze possible alternative routes for the HV transmission lines that would be necessary to implement the selected functional configuration.

PPL analyzed three line route options: “the Cross Country Corridor;”3 “the [145]*145Route 309 Line;”4 and “the SEPTA line.”5 After reviewing the associated costs and other considerations, PPL selected the Cross Country Corridor.

II.

On February 14, 2008, PPL filed an application with the Commission for approval of the siting and reconstruction of the proposed the Coopersburg # 1 and # 2 138/69 kV Tap in Upper Saucon Township, Lehigh County and Springfield and Rich-land Townships, Bucks County, Pennsylvania. It also sought to construct a related substation control building at Hickon Road in Springfield Township to protect control equipment (the Substation).6 PPL further sought to acquire rights-of-way (ROW) for the construction, use, operation, repair and maintenance of the preferred route for its transmission line, the proposed Cross Country Corridor. PPL filed several applications for approval to exercise the power of eminent domain to acquire ROWs and easements necessary for the construction, operation and maintenance of the proposed Cross , Country Corridor.

Numerous parties filed protests to the application and various parties filed petitions to intervene based on environmental concerns, including Springfield Township (Township).7 On August 12, 2008, tour [146]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Supervisors v. Pennsylvania Public Utility Commission
41 A.3d 142 (Commonwealth Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
41 A.3d 142, 2012 WL 112213, 2012 Pa. Commw. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-supervisors-v-pennsylvania-public-utility-commission-pacommwct-2012.