Board of School Commissioners v. Bender

72 N.E. 154, 36 Ind. App. 164, 1904 Ind. App. LEXIS 158
CourtIndiana Court of Appeals
DecidedOctober 11, 1904
DocketNo. 5,012
StatusPublished
Cited by29 cases

This text of 72 N.E. 154 (Board of School Commissioners v. Bender) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of School Commissioners v. Bender, 72 N.E. 154, 36 Ind. App. 164, 1904 Ind. App. LEXIS 158 (Ind. Ct. App. 1904).

Opinion

Wiley, J.

Appellee was plaintiff below, and his complaint was held good on a demurrer for want of sufficient facts, and the only question presented by the assignment of error is the sufficiency of the complaint.

The substantial averments of the complaint are that appellant had advertised for competitive bids for the erection of an addition to.one of its school buildings; that the notice published for such bids contained the following clause: “Each proposal must be accompanied by a certified check for the sum of $300 as a guaranty that the bidder will enter into a contract and file a satisfactory bond with the board of school commissioners of the city of Indianapolis, within the time specified. A failure on the part of the contractor to enter the contract will forfeit said amount or amounts deposited.” It was further averred that all bids and proposals should be at the office of appellant on or be[166]*166fore 4 o’clock p. m. of February 25, 1902; that the appellee did not see the notice as published, but that after its publication appellant’s architect notified him to make estimates and to make a bid and proposal for the work according to the plans and specifications, and on the 22d day of February, 1902, furnished appellee such specifications, and informed him that his bid must be accompanied with a certified check for $300 and must be 'in at or before 4 o’clock p. m. of February 25, 1902; that the plans, specifications and addenda to the specifications for the construction and erection of said building contained the following provisions, to wit: “Hotice to Bidders. Sealed proposals will be received for an addition to school building Uo. 33, corner Sterling and Twelfth streets, until 12 o’clock noon, the 25th day of February, 1902, at the office of the board of school commissioners (Library building) of the city of Indianapolis, Indiana.” .That the addenda to said specifications were affixed thereto, and contained on the first page thereof the following, to wit: “Bids to be opened at 8 o’clock p. m. February 25, instead of noon, as specified;” that appellee examined said specifications for no other purpose than to ascertain the description of the materials and of the work required, and that he did not read at any time the provisions in the specifications and addenda above quoted as to the time of opening said bids, and that he did not know until after the 25th day of February that he might have had until 8 o’clock p. m. of. said day in which to prepare and present his bids and proposals, as aforesaid; that appellee did examine the plans and specifications, and made his estimate for all the work and material, and returned the same to the architect on said 25th day of February, 1902, after having carefully placed his estimates in his book, known . and designated as his “estimate book;” that the plans and specifications further provided that bidders should make several and separate bids on certain work and material, which should be obliga[167]*167tory on the bidders and on the appellant, and which were afterward described by appellant as “general or regular bids,” and on certain other material and work therein specified, which were designated therein as “alternate basement and foundation plan,” the adoption and use of bids last aforesaid to be optional with appellant; that the material and work described in said “alternate and fofindation plan” were not to be required of the bidder, except at the option of appellant; that on the 25th day of February, 1902, exactly at 4 o’clock p. m., he delivered his bid in writing, signed by him, to appellant at the place designated in the notice, which bid was in the following words and figures, to wit: “Indianapolis, February 25,. 1902. Board of School Commissioners: I, the undersigned, propose to build addition to ISTo. 33, according to plans and specifications, for the sum of $11,337. Also, additional for alternate, $3,349.”

The complaint further avers that appellee relied upon and believed the architect’s statement aforesaid, that said bids must be in at or before 4 o’clock p. m. of said day; that in making his said bid and proposal he intended to include therein his estimates for all material and work, including that which was optional, as well as that which was obligatory, and that he made and placed in his “estimate book” all such estimates accordingly; that the placing of his bid and estimate was delayed without any fault or negligence on his part, but solely through the delay of two of his sub-bidders, until the hour of 3:30 o’clock p. m. of said day, and that in order to get his bid and proposal filed at 4 o’clock p. m., as he understood was requisite, there was not sufficient opportunity for verification of his bids; that he erroneously submitted his bid, as aforesaid, for the obligatory and peremptory part of said work; that his bid and proposal, in order to cover and include all of said work and material, should have embraced, and was intended to embrace, his estimate for. the obligatory and peremptory material and work, as aforesaid, the sum of [168]*168$3,319, and the further sum of $1,061, each of said amounts being on separate pages of his “estimate book,” in addition to said sum of $11,337, which was on a separate and distinct page thereof; that appellee’s bid and proposal, in order to embrace all the material and work, should have been in the sum made up of the three amounts last aforesaid,-to wit, $15,750; that appellee’s estimates for his bid on the optional and alternate work and material aforesaid were in said “estimate book” on a fourth and distinctly separate page, and that his bid on said branch of said erection was intended by him to have been, and should • have been, in the sum of $1,172 instead of the sum of $3,319, as aforesaid; that, in putting into writing his form of bid and proposal, owing to the limit of time, as he understood it, it was necessary that said bid and proposal be forwarded and delivered in great haste, and that he, in so hastily making up said bid, mistook the totals on the first page of his “estimate book,” to wit, $11,337, as and for his estimate for all the obligatory work and material, or, in other words, in the sum of $1,113 less than his estimates, and in that amount less than he intended and understood. It is further averred that in his haste in drafting and submitting his bid and estimate appellee mistook the amount' — $3,319—which was a part of his estimate on the work and material of the obligatory part of such erection, for the amount of his estimate on said “alternate basement and foundation plan,” optional with appellant, and erroneously made his bid and proposal for said optional material and work for said sum of $3,319, instead of for the sum of $1,172, or, in other words, in a sum $2,177 greater than lie intended and understood; that he delivered his said bid as aforesaid without any knowledge on the part of the appellee that he might have delayed such delivery, without detriment, until 8 o’clock p. m. of the same day; that at 8 o’clock p. m. February 25, 1902, appellant opened and examined the [169]*169bid and proposal of appellee, and those of others, and found appellee’s bid to be the lowest and best for the obligatory and optional work and material combined, and formally accepted said bid; that on the following day appellant, through its’ architect, notified appellee of such acceptance, but that he, having discovered his mistake and error so made and committed, forthwith informed said architect concerning the same, and on the same day notified John E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Porter County School Corp. v. Gough, Inc.
965 N.E.2d 684 (Indiana Court of Appeals, 2012)
Mid-States General & Mechanical Contracting Corp. v. Town of Goodland
811 N.E.2d 425 (Indiana Court of Appeals, 2004)
Jackson v. Blanchard
601 N.E.2d 411 (Indiana Court of Appeals, 1992)
Wilkin v. 1st Source Bank
548 N.E.2d 170 (Indiana Court of Appeals, 1990)
Regional School District Number 4 v. United Pacific Insurance
493 A.2d 895 (Connecticut Appellate Court, 1985)
Aluminum Co. of America v. Essex Group, Inc.
499 F. Supp. 53 (W.D. Pennsylvania, 1980)
Board of Water and Sewer Com'rs of Mobile v. Spriggs
146 So. 2d 872 (Supreme Court of Alabama, 1962)
Mayor of Baltimore v. DeLuca-Davis Construction Co.
124 A.2d 557 (Court of Appeals of Maryland, 1956)
State Highway Commission v. State Construction Co.
280 P.2d 370 (Oregon Supreme Court, 1955)
Puget Sound Painters, Inc. v. State
278 P.2d 302 (Washington Supreme Court, 1954)
M. F. Kemper Construction Co. v. City of Los Angeles
235 P.2d 7 (California Supreme Court, 1951)
School District of Scottsbluff v. Olson Const. Co.
45 N.W.2d 164 (Nebraska Supreme Court, 1950)
Rainey v. Quigley
178 P.2d 148 (Oregon Supreme Court, 1947)
Geremia v. Boyarsky
140 A. 749 (Supreme Court of Connecticut, 1928)
Olson v. Shephard
206 N.W. 711 (Supreme Court of Minnesota, 1926)
Lovell v. City of Altus
1925 OK 704 (Supreme Court of Oklahoma, 1925)
Board of Regents Murray Normal School v. Cole
273 S.W. 508 (Court of Appeals of Kentucky (pre-1976), 1925)
Kutsche v. Ford
192 N.W. 714 (Michigan Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
72 N.E. 154, 36 Ind. App. 164, 1904 Ind. App. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-school-commissioners-v-bender-indctapp-1904.