Board of Regents v. Denton Construction Co.

652 S.W.2d 588, 12 Educ. L. Rep. 176, 1983 Tex. App. LEXIS 4468
CourtCourt of Appeals of Texas
DecidedMay 19, 1983
Docket2-82-159-CV
StatusPublished
Cited by16 cases

This text of 652 S.W.2d 588 (Board of Regents v. Denton Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Regents v. Denton Construction Co., 652 S.W.2d 588, 12 Educ. L. Rep. 176, 1983 Tex. App. LEXIS 4468 (Tex. Ct. App. 1983).

Opinion

OPINION

JORDAN, Justice.

The appeal is from an adverse judgment in the total amount of $417,757.69 rendered by the trial court on a jury verdict in a suit involving two construction contracts between the parties hereto with respect to two buildings at North Texas State University in Denton, Texas.

Appellants advance thirty points of error to support their contentions that the judgment rendered against them was erroneous and must be reversed. We agree with some of appellants’ points of error and reverse and remand the cause for a new trial.

There are two different construction contracts between Denton Construction Company, as general contractor, and North Texas State University and the State of Texas, as owners, involved in this suit. The first contract, entered into in November, 1974, provided for the renovation and alteration by appellee, hereafter referred to as Contractor, of two dormitory buildings at North Texas State University (The University). These two dormitory buildings, by the terms of the first contract, were to be made into Music Practice Buildings. In June of 1976, another contract was entered into between these parties for the construction of a new Visitors Center Building.

After work on the two Music Practice Buildings was commenced, appellee Contractor encountered numerous delays which resulted in the job not being finished for inspection until more than 190 days after the completion date called for in the contract. While the cause of the delays was disputed at trial, Contractor claimed that the delays were all caused by indecision and *590 delays by the University involving installation of different items in the construction of the two Music Practice Buildings. Contractor contended that there was an aggregate of 902 days delay, as set out in its exhibit at trial number 49, exclusive of delays caused by weather or labor strikes.

The jury agreed with appellee’s contentions and answered all of the special issues submitted in favor of appellee.

Specifically, the delays were encountered because of unforeseen problems confronting Contractor with respect to the replacement and reworking of certain “relieving angles” which were not properly secured to the building and which fell off when bricks were removed. Additional reasons for delay were, according to Contractor: an unusual floor texture on the bathroom floors which required a substantial amount of extra work; uncertainty on the part of the University in deciding what material it wanted on the music practice room walls; uncertainty on the part of the University as to the texture and material wanted for its sidewalk system; a change in plans by the University in some of the hardware originally specified for the Music Practice Buildings; a delay in the delivery and installation of wall carpet because the University ultimately required a repair of the existing walls to receive the new carpet as wall covering; delay with regard to the bathroom floors because, according to Contractor, the University delayed in issuing a change order.

Appellee Contractor sought and recovered damages for all of these items allegedly causing delay in completion of the contract.

After the work on the Music Practice Buildings was completed, appellants withheld $8,000.00 from Contractor because they claimed certain air conditioning screens did not meet the contract specifications, and withheld $10,000.00 because certain pitch pans did not meet contract requirements.

With respect to the contract for the construction of the new Visitors Center Building, work was commenced thereon in July, 1976, and the Contractor again encountered delays, with the result that the work on this new building was not completed for final inspection until 59 days after the date called for in the contract. Again, the reasons for the delays were disputed, but for our purposes, they were attributable to delay in the delivery of brick and masonry products ordered on a “closed specification”, delay in the delivery of steel, and an error in the design of the driveway ramp for the building which caused a repouring of the driveway, and consequent delay.

Appellee Contractor alleged that it was delayed a total of 59 days in completing the Visitors Center project as the result of acts and omissions of appellant University, and it sought and recovered the sum of $49,-660.00 as damages for this delay.

Appellants withheld $8,360.00 as liquidated damages for appellee’s failure to timely complete the construction of the Visitors Center Building. Appellant also, because of the alleged delay on the part of Contractor on all these projects, refused to permit Contractor to bid on other, later projects, which caused Contractor, in its suit, to sue for exemplary damages, in addition to its alleged actual damages.

The jury, in answering Special Issues 14, 15, 16, and 17, found that the University’s actions in disqualifying Contractor as an acceptable bidder on additional construction projects were undertaken without just cause, that such actions caused Contractor additional actual damages in the amount of $33,000.00 and exemplary damages in the sum of $115,000.00. Since Contractor in its suit only pled for $82,180.00 in exemplary damages, it tendered by way of remittitur the sum of $32,820.00 which was the excess of the amount found by the jury over the amount pled.

In points of error one, two, three, ten and twelve appellants take the position that exemplary damages will not lie against the State of Texas, and that, accordingly, it was error on the part of the trial court to overrule appellants’ exceptions to the pleading of exemplary damages, to submit an issue thereon, and to enter judgment in favor of *591 appellee for exemplary damages. We sustain these points of error.

In points of error four, five, six, seven, eight and eleven appellants contend that the State of Texas had not waived its sovereign immunity to the extent that appellee could recover each of its specific and delineated elements of damages, such as delay and consequential loss because of “relieving angles”, air conditioning screens, changes in the bathroom floors and other specified damages. We overrule points of error four through eight and eleven.

Since the first twelve points of error all involve appellants’ claim that the State had not waived its sovereign immunity as to the items mentioned above, those points of error will be discussed together.

After appellants refused to satisfy appel-lee’s claim for damages caused by the delays in completing both contracts, and after appellant University prohibited Contractor from bidding on additional construction projects, appellee sought and obtained consent from the Texas Legislature to sue the University, which is an arm of the State of Texas, and the State itself. The legislative consent read in pertinent part:

WHEREAS, Denton Construction Co. alleges that on December 4, 1974, it entered into a written contract with North Texas State University for construction of a music practice building; and
WHEREAS, Denton Construction Co. alleges that on June 22, 1976, it entered into another written contract with North Texas State University for the remodeling of the campus visitors center; and
WHEREAS, Denton Construction Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West v. TRIPLE B SERVICES, LLP
264 S.W.3d 440 (Court of Appeals of Texas, 2008)
Redwine v. AAA Life Insurance Co.
852 S.W.2d 10 (Court of Appeals of Texas, 1993)
City of La Porte v. Prince
851 S.W.2d 876 (Court of Appeals of Texas, 1993)
First National Bank of Amarillo v. Jarnigan
794 S.W.2d 54 (Court of Appeals of Texas, 1990)
American Bankers Insurance Co. of Florida v. Caruth
786 S.W.2d 427 (Court of Appeals of Texas, 1990)
Lively Exploration Co. v. Valero Transmission Co.
751 S.W.2d 649 (Court of Appeals of Texas, 1988)
Hirdler v. Boyd
702 S.W.2d 727 (Court of Appeals of Texas, 1985)
Mader v. Aetna Casualty & Surety Co.
683 S.W.2d 731 (Court of Appeals of Texas, 1984)
American Petrofina, Inc. v. PPG Industries, Inc.
679 S.W.2d 740 (Court of Appeals of Texas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
652 S.W.2d 588, 12 Educ. L. Rep. 176, 1983 Tex. App. LEXIS 4468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-regents-v-denton-construction-co-texapp-1983.