Board of Natural Resources v. Walker County

407 S.E.2d 436, 200 Ga. App. 301, 1991 Ga. App. LEXIS 969
CourtCourt of Appeals of Georgia
DecidedJune 19, 1991
DocketA91A0068
StatusPublished
Cited by7 cases

This text of 407 S.E.2d 436 (Board of Natural Resources v. Walker County) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Natural Resources v. Walker County, 407 S.E.2d 436, 200 Ga. App. 301, 1991 Ga. App. LEXIS 969 (Ga. Ct. App. 1991).

Opinion

Beasley, Judge.

This case involves the Georgia Hazardous Waste Management Act, OCGA § 12-8-60 et seq.

We granted discretionary appeal to the Director of the Environmental Protection Division of the State Department of Natural Resources (EPD), the State Board of Natural Resources (Board), and Redox, Inc., from an order of the superior court which reversed two orders and a final decision of the administrative law judge (ALJ) affirming EPD’s issuance of a permit to Redox for the construction and operation of a hazardous waste treatment and storage facility in unincorporated Walker County.

Following issuance of the permit, Walker County and its commissioner petitioned for a hearing and review before an ALJ appointed by the Board pursuant to OCGA § 12-2-2 (c) (2). The petition raised in excess of 90 questions. It alleged, inter alia, that EPD’s actions in issuing the permit were arbitrary, capricious, an abuse of discretion or *302 an unwarranted exercise of discretion because:

(A) The waste management process described in the permit application did not fully and completely comply with applicable law and did not provide for the protection of the general health and welfare of the county’s citizens.

(B) The described waste analysis plan did not fully comply with applicable law and did not provide for protection of the citizens’ general health and welfare.

(C) The described procedures to prevent hazards did not fully and completely comply with the law and did not provide for protection of the citizens’ general health and welfare.

(D) The water supply in the area of the proposed facility would be unreasonably endangered.

(E) The application and permit did not adequately address the problem of air pollution.

(F) Adequate water with sufficient pressure was not available at the proposed site to combat a fire of any magnitude.

(G) The application and permit failed to require any type of automatic fire fighting system.

(H) There was a failure to consider the accident potential of transporting the chemicals prior to treatment.

(I) There was a failure of adequate procedure for controlling mixtures or combinations of wastes that have a delayed reaction time.

(J) There was no adequate contingency plan to cover temporary or permanent overloads of hazardous wastes.

(K) There was a failure to require procedures to control disposal of waste residues from testing and rejected shipments. The petition also alleged that the notice of the public hearing for permitting the facility, as required by OCGA § 12-8-66 (h), was insufficient inasmuch as there was not 30 days notice prior to the date of the public hearing. 1

EPD and the county filed cross-motions for a summary determination on the question of adequacy of notice. 2

On August 22, 1989, the ALJ issued an order in favor of EPD. He rejected the county’s contention that OCGA § 1-3-1 (d) (3) applied to computing time under OCGA § 12-8-66 (h) so as to render the notice insufficient.

*303 EPD also moved for partial summary determination on 79 legal issues raised by the county’s petition. On October 26, 1989, the ALJ issued a lengthy and detailed order granting EPD a favorable determination on 71 of the issues and denying summary decision on the other eight.

As a result of the summary determinations granted to EPD, the scope of the eventual administrative hearing was limited to 12 legal questions involving the remaining nine areas:

(1) Adequacy of the water supply for fire fighting.

(2) Construction and operation of the facility in terms of preventing or controlling fires, explosions, or unplanned releases.

(3) Prevention of accidental ignition or reaction of wastes.

(4) Arrangements with local fire, police, and emergency authorities.

(5) The schedule for inspections of equipment at the facility.

(6) Containment of spills or leaks of hazardous materials and of any contaminated water from fire fighting or rain.

(7) Treatment and handling of the drums used to transport or store hazardous wastes.

(8) Provisions for sampling wastes upon arrival.

(9) The potential for groundwater contamination.

On February 23, 1990, the ALJ issued a 34-page final decision, addressing in detail the remaining legal challenges to the permit and affirming its issuance. The county petitioned the superior court for judicial review. The court determined:

(1) The ALJ erred in his August 22, 1989, order because there was insufficient public notice in that the days were to be computed in accordance with OCGA § 1-3-1 (d).

(2) The ALJ erred in his October 26, 1989, order when he granted EPD a favorable summary determination with respect to 23 issues because in each instance the ALJ incorrectly construed the provisions of 40 CFR § 270.32 (b) (2). As to each of these issues the county submitted affidavits which created factual issues as to whether the matter raised should have been required as a condition to issuance of the permit or specified as a term of the permit in order to protect human health and the environment.

(3) In the October 26 order, the ALJ erroneously determined as a matter of law that the provisions of 40 CFR Part 264, Subpart J, governing the use of tanks at hazardous waste facilities, were not applicable to the Redox facility.

(4) The Redox application was insufficient because the contingency plan and emergency procedures described in the application did not describe arrangements agreed to by local police departments, fire departments, hospitals, contractors, and state and local emergency services as required by 40 CFR §§ 270.14; 264.52 (c); and *304 264.37.

(5) Review of the ALJ’s three decisions showed that substantial rights of the county and its commissioner had been prejudiced because the ALJ’s determinations were in violation of statutory provisions and affected by legal error.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Service Industries, Inc. v. Here to Serve Restaurants, Inc.
695 S.E.2d 669 (Court of Appeals of Georgia, 2010)
Georgia Public Service Commission v. Sawnee Electric Membership Corp.
529 S.E.2d 186 (Court of Appeals of Georgia, 2000)
Children's Hospital v. Georgia Department of Medical Assistance
509 S.E.2d 725 (Court of Appeals of Georgia, 1998)
Miller v. Calhoun/Johnson Co.
497 S.E.2d 397 (Court of Appeals of Georgia, 1998)
Georgia Public Service Commission v. Alltel Georgia Communications Corp.
497 S.E.2d 50 (Court of Appeals of Georgia, 1998)
Hospital Authority v. State Health Planning Agency
438 S.E.2d 912 (Court of Appeals of Georgia, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
407 S.E.2d 436, 200 Ga. App. 301, 1991 Ga. App. LEXIS 969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-natural-resources-v-walker-county-gactapp-1991.