Board of Education v. Barracks

235 Ill. App. 35, 1924 Ill. App. LEXIS 113
CourtAppellate Court of Illinois
DecidedOctober 22, 1924
DocketGen. No. 7,731
StatusPublished
Cited by13 cases

This text of 235 Ill. App. 35 (Board of Education v. Barracks) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education v. Barracks, 235 Ill. App. 35, 1924 Ill. App. LEXIS 113 (Ill. Ct. App. 1924).

Opinion

Mr. Presiding Justice Shurtleff

delivered the opinion of the court.

James Franklin Barracks, an owner of land and a taxpayer of Villa Grove Township, Hlinois, on behalf of himself and other taxpayers, filed his bill of complaint in this cause on the 15th day of February, 1922, against the Board of Education of Villa Grove Township High School District, Illinois, the Township School Treasurer and F. J. Schwartz, a contractor, seeking to enjoin and restrain the Board of Education and the said Township School Treasurer from paying certain vouchers issued to said contractor for additional costs alleged to be due in the construction of a high school building.

An injunction writ was granted.

The bill alleged inter alia that the school district was duly organized, and that a Board of Education was duly elected; that the said Board of Education was legally authorized to erect the school building, and that the said board duly advertised for bids, and that, on or about the 15th day of June, 1919, the said Board of Education awarded to F. J. Schwartz a contract to build the school building for said district for the sum of $88,500, according to the plans and specifications theretofore adopted by the said board. The said F. J. Schwartz entered into a bond or undertaking with approved sureties conditioned for the faithful erection of said building; that the said F. J. Schwartz promptly began the erection and construction of said building and proceeded in every way in accordance with the plans and specifications of said contract, and continued so to construct said building until its completion.

The bill further alleges that on, to wit, the 14th day of April, 1921, the said F. J. Schwartz presented to the Board of Education a verified statement, in writing, showing a balance due for labor and materials furnished upon the said building in the sum of $24,500; that the said board, in meeting duly convened, on or about April 14, 1921, approved of the said statement, and by resolution duly passed, directed the sum of $24,500 to be paid to said contractor; that the said sum of $24,500 is over and above the sum of $88,500, for which the said F. J. Schwartz originally undertook to erect the said school building; that warrants were issued to the said F. J. Schwartz for the payment of this amount, and were then and there delivered to the said F. J. Schwartz; that the first voucher issued, for $7,500, was duly paid upon presentation by F. J. Schwartz, and the bill prays for a permanent injunction to prevent the payment of the remaining vouchers out of the funds belonging to said school district, and that the court decree that the said board had no right either in law or equity to authorize the payment of said sum, or any part thereof, and that the said F. J. Schwartz may be compelled to return the said sum of money received by him in payment of the first voucher.

The members of the Board of Education, the School Treasurer, and F. J. Schwartz, the contractor, appeared and filed their joint and several general and. special demurrer, calling in question the jurisdiction of the court to entertain the bill, which was overruled, and the defendants thereafter, by leave of court, filed their joint and several answer, in which they admitted that the school district was duly organized; that it proceeded legally to elect the Board of Education, and that it was legally authorized to erect a school building; that said district duly advertised for bids for the erection of a school building, and that the said board awarded the contract for the construction of said building to F. J. Schwartz, who was the lowest bidder, for the sum of $88,500.

The answer also admitted the making of the contract between said Schwartz and the board for the erection of said building, and that the said Schwartz had filed his bond conditioned in pursuance of said contract.

The answer further alleges that subsequently a parol agreement to pay additional compensation for the erection of said school building was entered into between the parties and later a further compromise agreement was made after the completion of the building in full settlement of all claims.

The answer further alleges substantially that owing to increase in prices of labor and material brought about by war conditions, the said defendant F. J. Schwartz presented to the various members of the Board of Education the matter of the additional cost of the construction of the school building, and that he had decided to abandon the completion of the structure, in view of the fact that his funds were depleted and a heavy loss was in prospect for him; that the board held an informal meeting on August 15, 1920, and advised the contractor Schwartz to continue the erection of said building, and that they, the board, would pay the additional cost, and that he, the said Schwartz, should bring in a statement showing all costs when the building was completed. That on April 13,1921, the said defendant Schwartz submitted a verified statement to the board, showing the actual cost of the construction of the school building to be $122,000 or $33,500 in excess of the contract price, and that as a result of negotiations the board then and there agreed to pay him the sum of $24,500 in full settlement, the basis of such computation being that this additional payment would increase his original contract price to that of the next lowest bidder.

There was replication and the cause was submitted to the master to take and report the proofs, with his conclusions of law and fact.

The master took the proofs and reported same with his finding that the payment of said warrant for $7,500 to the defendant F. J. Schwartz was unlawful, and recommended that a decree be entered in accordance with the prayer of the bill, awarding a perpetual injunction against the school board and its treasurer, enjoining and restraining the payment of any further sum of money to said F. J. Schwartz, and directing that the said F. J. Schwartz make restitution for the warrant, amounting to $7,500, paid to him, and that in default thereof that the members of the school board be severally held liable therefor. Objections were interposed before the master and overruled, and exceptions filed thereto in the circuit court, which were overruled, and a decree was entered.

It appears from the proofs that bids for the construction of said building were opened on June 5, 1939, and that Schwartz was the lowest bidder and $24,500 under the next lowest bid.

It further appears that thereafter Schwartz was questioned by the Board of Education and architect as to whether the work could be done for the amount of the bid, and Schwartz and the architect, having completely refigured the plans and specifications, came to the conclusion that the work could be done and material furnished and a contract was entered into on June 10, 1919, and a good and sufficient bond with sureties was signed by Schwartz, the contractor, under seal, covenanting that all of the terms of the contract would be fully carried out by the contractor.

It further appears that thereafter Schwartz entered upon the work of constructing said building under the contract in good faith, and that in December, 1919, owing to conditions brought about by the World War, he became unable to obtain material for the construction of said building, except at greatly enhanced prices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education v. Sered
850 N.E.2d 821 (Appellate Court of Illinois, 2006)
White v. Village of Homewood
628 N.E.2d 616 (Appellate Court of Illinois, 1993)
Greenberg v. Mallick Management, Inc.
527 N.E.2d 943 (Appellate Court of Illinois, 1988)
Garber v. Harris Trust & Savings Bank
432 N.E.2d 1309 (Appellate Court of Illinois, 1982)
Harlem-Irving Realty, Inc. v. Alesi
425 N.E.2d 1354 (Appellate Court of Illinois, 1981)
Lake View Trust & Savings Bank v. Filmore Construction Co.
393 N.E.2d 714 (Appellate Court of Illinois, 1979)
Noll Baking & Ice Cream Co. v. Sparks Milling Co.
26 N.E.2d 425 (Appellate Court of Illinois, 1940)
Marcus v. S. S. Kresge Co.
283 Ill. App. 556 (Appellate Court of Illinois, 1936)
Lindsey v. Rosen
255 Ill. App. 21 (Appellate Court of Illinois, 1929)
Shortal v. School Directors of District No. 27
255 Ill. App. 89 (Appellate Court of Illinois, 1929)
Postell v. Joseph Brothers Lumber Co.
240 Ill. App. 384 (Appellate Court of Illinois, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
235 Ill. App. 35, 1924 Ill. App. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-v-barracks-illappct-1924.