Marcus v. S. S. Kresge Co.

283 Ill. App. 556, 1936 Ill. App. LEXIS 672
CourtAppellate Court of Illinois
DecidedFebruary 11, 1936
DocketGen. No. 38,005
StatusPublished
Cited by5 cases

This text of 283 Ill. App. 556 (Marcus v. S. S. Kresge Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marcus v. S. S. Kresge Co., 283 Ill. App. 556, 1936 Ill. App. LEXIS 672 (Ill. Ct. App. 1936).

Opinion

Mr. Justice Friend

delivered the opinion of the court.

Plaintiff sued in assumpsit to recover $4,538 additional compensation for work done in the erection of a store building for defendant in the City of Chicago. Plaintiff’s declaration consisted of an amended first count and the common counts. By leave of court the common counts were withdrawn. To the amended first count defendant filed a general demurrer, which was sustained by the court. Plaintiff elected to abide by his declaration, and the court dismissed the suit at plaintiff’s costs. This appeal followed.

The amended first count alleged that plaintiff was engaged in business as a general building contractor, and on April 30, 1930, entered into a written contract to construct for defendant a two-story building located at 1357-61 E. 55th street, in Chicago, for a stated consideration of $48,648. Plaintiff undertook to furnish all labor and material required and to execute all the work according to plans and specifications attached to the contract.

As bearing upon the principal question in controversy, the specifications attached to the agreement contained the following provision:

“Note.

“The general figures and price for this work to be based on any and all existing soil conditions and formations, except ledge rock.

“If excavation in ledge rock formation is encountered, the excavator must mine and remove the same, using channeling and drilling machines operated by air power. Excavations in such rock formation to be done as per city ordinances or laws governing such cases. Contractors must state in their bids the extra amount per cubic yard to be paid for excavations in ledge rock, — this price to include ‘line drilling.’

“Any and all loose rock or other loose matter encountered must be removed without extra charge.”

The amended first count further averred that plaintiff commenced excavating for the building in question April 30, 1930; that the foundation for the building described in the contract was generally known as a “spread footing,” which in buildings of this kind generally does not exceed the depth of 20 feet below the surface of the ground, and that the foundation for this particular structure did not exceed the depth of 20 feet; that in excavating for spread footing foundations quicksands are not generally encountered in the ground between the depth of 20 to 30 feet, and persons contracting for the erection of buildings such as the one called for in the agreement have knowledge that quicksands are not encountered, and that the contract prices for the erection of such buildings are fixed upon the assumption that no quicksand will be encountered; that when the parties entered into the agreement herein they did not contemplate that any quicksand would be encountered, in arriving at the contract price of $48,648; that the words, “all existing soil conditions and formations,” contained in the specifications, when applied to buildings such as the one described in this agreement, did not and do not, by general custom and usage, include quicksand.

It is further alleged that the specifications contained, among others, the following provisions:

“Wherever the words ‘Supervisor of Construction Division’ are used it refers to the delegated representative of the Owner who will supervise, and have full control of the award of contracts and of the construction work in the field.

“Wherever the words ‘Division Superintendent’ are used it refers to the delegated representative of the Supervisor of the Construction Division who will be in charge of field construction in a certain geographical subdivision of the territory in which building operations are to be conducted. The Division Superintendent shall have power to decide all matters coming up in connection with the field construction in his territory, subject, however, to the approval of the Supervisor of the Construction Division.

“Wherever the words ‘Job Superintendent’ are used it refers to the representative of the Supervisor of the Construction Division who is in direct charge .of the work at the site. He shall have power to decide all matters coming up, subject, however, to the approval of the Division Superintendent.”

It is averred that when plaintiff commenced the work for the erection of the building in question, defendant had on the job a representative designated as “Job Superintendent”; that for several years preceding the execution of the agreement, the parties herein had entered into numerous contracts for the erection of buildings; that during the course of the execution of the work under these prior contracts disputes arose from time to time as to whether certain work was or was not covered by the contracts, and when such disputes arose the job superintendent authorized plaintiff to proceed with the additional or disputed work under a promise to pay therefor, and plaintiff, relying upon such order and promise of the job superintendent, proceeded with the work and was paid therefor by defendant pursuant to a. practice and course of dealing adopted by the parties herein.

It is further alleged that about May 17, 1930, plaintiff commenced excavating for a spread footing foundation for the building in question, and while so engaged encountered quicksand, which hindered and delayed him in and about his work, necessitating the expenditure of an additional $4,538, over and above the sum contemplated by the parties in their contract; that plaintiff then called to the attention of the job superintendent the fact that plaintiff was not obligated under his contract to pay any additional money necessitated by the encountering of the quicksand; that the job superintendent, acting under his powers and with the approval of the division superintendent, thereupon ordered and directed plaintiff to proceed with the work and promised to pay plaintiff the sum of $4,538 in addition to the contract price; that plaintiff, relying upon practice theretofore established between the parties, and upon the order of the job superintendent and his promise to pay, proceeded with the work and completed the building; that defendant accepted the building from plaintiff as completed, with full knowledge of the order and promise made by the job superintendent and knowing* that plaintiff was relying upon the order and promise of the job superintendent to supply the additional work under the oral promise made.

In conclusion, it is averred that upon completion of the building plaintiff demanded the additional sum of $4,538, which defendant refused and still refuses to pay, wherefor plaintiff brings suit for the recovery thereof together with interest at the rate of six per cent per annum since July 26, 1930.

It is urged on behalf of plaintiff that he is entitled to recover the additional costs incurred by him and necessitated by a condition which neither party contemplated at the time the contract was made, because (1) the demurrer admits all the allegations well pleaded in the declaration; (2) defendant’s promise to pay was based on a sufficient consideration; (3) that since the parties had established a course of dealing between them, their practices in the past may be resorted to in order to determine whether plaintiff is entitled to recover; and (4) that defendant accepted plaintiff’s work and was therefore bound to pay therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenberg v. Mallick Management, Inc.
527 N.E.2d 943 (Appellate Court of Illinois, 1988)
Dayan v. McDonald's Corp.
466 N.E.2d 958 (Appellate Court of Illinois, 1984)
Crerar Clinch Coal Co. v. Board of Education
141 N.E.2d 393 (Appellate Court of Illinois, 1957)
Wuellner v. Illinois Bell Telephone Co.
54 N.E.2d 853 (Appellate Court of Illinois, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
283 Ill. App. 556, 1936 Ill. App. LEXIS 672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marcus-v-s-s-kresge-co-illappct-1936.