Board of Com'rs v. Dowdle & Windett

67 So. 324, 136 La. 447, 1915 La. LEXIS 2011
CourtSupreme Court of Louisiana
DecidedJanuary 25, 1915
DocketNo. 20374
StatusPublished

This text of 67 So. 324 (Board of Com'rs v. Dowdle & Windett) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Com'rs v. Dowdle & Windett, 67 So. 324, 136 La. 447, 1915 La. LEXIS 2011 (La. 1915).

Opinion

O’NIELL, J.

[1, 2] By the very able arguments and briefs of the counsel of the plaintiff and defendants, the issues in this ease are reduced to two simple questions, viz.:

First. Had the plaintiff the right, under section 9 of the contract of the 16th of October, 1902, to relet the contract for the account and at the expense of Dowdle & Windett, in the event it was vacated or annulled?

Second. Was the contract of the 16th of October, 1902, vacated or annulled?

It was decided by this court on the former appeal in this ease (129 La. 517, 56 South. 426) that section 9 of the contract of the 16th of October, 1902, was not abrogated by the amendments agreed to by the contracting parties on the 11th of May, 1904. That section of the contract, stated in separate paragraphs, for convenience, is as follows:

“Should the contractor fail to prosecute the work under this contract with the vigor necessary to its completion within the time stipulated, in the opinion of the engineer 'in charge, all estimates may be withheld; and it shall be competent for and the duty of the president of the board "to employ such additional force as he may deem necessary at the expense of the contractors.
“Should it become necessary, in the judgment of the president of the board, to suspend this contract, or to declare it vacated or annulled, for negligence, inefficiency, or abandonment by contractor, he may proceed to do so, and in such a case the 20 per cent, reserved as security for completion of contract, and all other sums due to said contractor by the Plaque-mines parish, East Bank levee district, shall be forfeited, the decision of the board of commissioners to be final as to the cause of action oh the part of the president or eiigineer in charge.
“Should damage accrue to the district, or to those to be protected by the levee from such laches, or from abandonment of the work, the contractor and his sureties shall be responsible for such amount as shall be awarded by the courts.
“A contract, vacated or annulled as above described, may be relet by the president of the board to another-contractor without advertisement or another formality.”

Assuming that the contractor was at fault in failing to prosecute the work with the vigor necessary for its completion within the time stipulated, the board had the right, under the first paragraph of section 9 of the contract, to withhold all estimates, and it was competent for, and the duty of, the president of the board to employ such additional force as he might deem necessary at the expense of the contractor. The board did, in its resolution of the 4th of January, 1905, withhold all payments; but the board did not at any time employ an additional force for the completion of the work.

The second paragraph of the section under consideration gave the president of the board absolute authority to suspend the contract or declare it vacated or annulled if he deemed it necessary, in his judgment, for negligence, inefficiency, or abandonment by the contractor; and in that event all sums due by the board to the contractor were to be forfeited.

The third paragraph of this section of the contract is not pertinent to the issues in this case.

The fourth and last paragraph of section 9 gave the president of the board the right to relet the contract to another contractor without advertisement or other formality, if the contract should be vacated or annulled as above described, that is, as described in the second paragraph of section 9.

If the president of the board had availed himself of the right to employ an additional force, it would have been at the expense of the contractor, under the first paragraph of section 9; and the contract would not have been vacated or annulled. But the last paragraph, giving the president of the board the right to relet the contract to another contractor without advertisement or any other formality, in the event of its being vacated or annulled, did not provide that the reletting should be at the expense of the contractor whose contract was vacated or annulled.

The contingency, in the last paragraph of [451]*451section 9, i. e., if the contract should be vacated or annulled as above described, meant clearly if it should be vacated or annulled by the board for negligence, inefficiency, or abandonment by the contractor, as provided in the second paragraph. Under that paragraph, the authority of the president of the board to declare the contract vacated or annulled was absolute. If he deemed it necessary to vacate or annul the contract, all he had to do was to declare it vacated or annulled for negligence, inefficiency, or abandonment by the contractor, and the decision of the board as to the cause of action on the part of the president — i. e., as to the negligence, inefficiency, or abandonment by the contractor rendering the annulment of the contract necessary — was to be final. If then, in addition to forfeiting all sums due to the contractor, the board had the right to relet the contract to another contractor, without advertisement or any other formality, at the expense of the original contractor, it was indeed an unilateral contract. We are constrained to conclude that, if the parties had intended to make such an anomalous agreement, the last paragraph of section 9 would have concluded precisely as the second paragraph concludes, “at the expense of the contractor.”

Counsel for the plaintiff contend that the board did not, in its resolution of the 2d of March, 1905, vacate or annul the contract of the 16th of October, 1902, but merely called upon the contractor to perform the contract and declared that the board would relet the work to another contractor for the account and at the expense of Dowdle & Windett,if the latter should not resume work at or before noon on the 15th of March, 1905, and prosecute the work to its completion as provided in the contract. This is true. But the board did in fact relet the work to another contractor before the expiration of the time in which Dowdle & Windett were required to complete the work. It is true that, in the resolution of the 2d of March, 1905, calling upon Dowdle & Windett to resume and complete the work according to the contract, the board declared that the work'would be relet to another contractor for the account of Dowdle & Windett. And, if the board had the right under its contract with Dowdle & Windett to relet the work for the account of Dowdle & Windett, the reletting of the contract would not have vacated or annulled the contract. But we have already observed that the board had no right to relet the contract to another bidder unless it was vacated or annulled, in which event the new contract was not to be for the account of Dowdle & Windett. In fact, the resolution of the board, calling upon 'Dowdle & Windett to resume and complete the work, did not declare that the board would relet the contract, but that the board would relet the work, for account of Dowdle & Windett, if the latter failed to comply with the demand of the board. And the board did relet the work to another contractor- under a new and somewhat different contract. This action on the part of the board vacated and annulled the contract with Dowdle & Windett, and the obligation for damages due by Dowdle & Windett for failing to comply with the demand of the board must be determined by the contract and the law applying to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. O'BRIEN
220 U.S. 321 (Supreme Court, 1911)
Fourche River Lumber Co. v. Bryant Lumber Co.
230 U.S. 316 (Supreme Court, 1913)
Stone, Sand and Gravel Co. v. United States
234 U.S. 270 (Supreme Court, 1914)
Brink v. Bartlett
105 La. 336 (Supreme Court of Louisiana, 1901)
City of New Orleans v. Congregation Dispersed of Judah
15 La. Ann. 389 (Supreme Court of Louisiana, 1860)
Kean v. Brandon
17 La. Ann. 37 (Supreme Court of Louisiana, 1865)
Graugnard v. Forsyth
44 La. Ann. 327 (Supreme Court of Louisiana, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
67 So. 324, 136 La. 447, 1915 La. LEXIS 2011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-comrs-v-dowdle-windett-la-1915.