BMC Industries v. Barth Industries

160 F.3d 1322
Court of Appeals for the Eleventh Circuit·Decided November 18, 1998·No. 95-5137·Published·Cited by 2 cases

Opinion

PUBLISH

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT

FILED

U.S. COURT OF APPEALS

ELEVENTH CIRCUIT

Nos. 95-5137, 95-5338 11/18/98 THOMAS K. KAHN

CLERK

D. C. Docket No. 89-6443-CIV-MOORE

BMC INDUSTRIES, INC., Plaintiff-Appellee,

versus

BARTH INDUSTRIES, INC., NESCO, INC., f.k.a. Nesco Management, Inc., BARTH INDUSTRIES CO. LIMITED PARTNERSHIP, BIC CORPORATION, NESCO HOLDINGS, INC., f.k.a. Nesco, Inc.,

Defendants-Appellants.

Appeals from the United States District Court for the Southern District of Florida

(November 18, 1998)

Before TJOFLAT and BARKETT, Circuit Judges, and GODBOLD, Senior Circuit Judge.

TJOFLAT, Circuit Judge:

This appeal arises from a contract entered into between BMC Industries, Inc., and Barth Industries, Inc., for the design, manufacture, and installation of equipment to automate BMC’s production line for unfinished eyeglass lenses. Eighteen months after the delivery date set out in the contract had passed, BMC filed suit against Barth for breach of contract.1 Barth, in turn, counterclaimed for breach of contract. BMC’s suit also included a claim against Barth’s parent company, Nesco, Inc.2 According to BMC, Nesco had orally promised to ensure Barth’s completion of the contract, and therefore was liable under the theory of promissory estoppel for Barth’s nonperformance.

A jury resolved the breach of contract and promissory estoppel issues in favor of BMC, and returned a verdict of $3 million against Barth and $2.1 million against Nesco. After denying Barth’s and Nesco’s alternative motions for judgment as a matter of law and for a new trial, the district court rendered judgment in accordance with the jury’s verdicts, and Barth and Nesco

1 As indicated in the text, infra, in addition to suing for breach of contract, BMC sought judgment against Barth on a variety of legal theories. All stemmed from the parties’ contractual relationship.

2 After BMC and Barth entered into the contract in question here, Barth reorganized its corporate structure. Barth Industries, LP, a limited partnership, was formed and received all of the assets and liabilities of Barth Industries, Inc. Barth Industries, Inc., then dissolved. Additionally, Nesco, Inc., which was the sole shareholder of Barth Industries, Inc., changed its name to Nesco Holdings, Inc., and became a limited partner of Barth Industries, LP, holding a 99% interest in the partnership. The remaining one percent interest was acquired by BIC Corporation, the limited partnership’s general partner.

In its suit against Barth Industries, Inc., and Nesco, Inc., BMC named seven other parties, including Barth Industries, LP, and BIC Corporation, as defendants. By the time of trial, BMC had dismissed five of the seven from the case. The final judgment in this case was entered against Barth Industries, Inc. and Nesco Holdings, Inc. For ease of discussion, we refer to the Barth entities collectively as “Barth,” and the Nesco entities collectively as “Nesco.”

appealed. We affirm the district court’s decision denying Barth judgment as a matter of law. We conclude, however, that the court erroneously instructed the jury on the contract issues, and therefore vacate the judgment against Barth and remand the case for a new trial on these issues. As for Nesco, we conclude that the court should have granted Nesco judgment as a matter of law, and thus direct the district court to dismiss Nesco from this case.

I.

A.

BMC, through its Vision-Ease division, manufactures semi-finished polymer opthalmic lenses that are used in the production of eyeglasses. These lenses are created by an assembly- line process. First, an employee fills a mold assembly with a monomer fluid, and places the mold assembly on a conveyor. Next, the assembly is inspected and then heated and cured until the monomer solidifies into a plastic lens. Finally, the lens is removed from the mold assembly through a process called “de-clipping and de-gasketing”; an employee removes the spring clip holding the mold assembly together and slices open the rubber gasket that holds the lens. The lens is then packaged and sold to a finished eyeglass retailer.

In order to decrease labor costs, and thereby remain competitive with other lens manufacturers who were utilizing cheaper foreign labor, BMC decided to become the first company to automate portions of its lens manufacturing process. Consequently, in early 1986, BMC commissioned Barth to complete a preliminary design and feasibility study. Barth’s subcontractor, Komech, finished the study in June 1986. Based on this study, Barth and BMC entered into a contract (the “Contract”) which provided that Barth would “design, fabricate,

debug/test and supervise Field installation and start up of equipment to automate the operations of mold assembly declipping, clip transport, mold assembly clipping, and mold filling.” The Contract, which stated that it was governed by Florida law, listed a price of $515,200 and provided for delivery of four automated production lines by June 1987. The Contract also stated that time was of the essence.

On November 4, 1986, Barth and BMC executed a written amendment to the Contract, extending the delivery date by one month. In February 1987, Barth terminated Komech as design subcontractor, and hired another engineering company, Belcan, in its place. Belcan subsequently redesigned the automation equipment, which delayed Barth’s progress and led the parties to execute the second (and last) written amendment, which extended the delivery date to “October 1987.”

After this second amendment, Barth continued to experience technical problems and design difficulties that caused repeated delays. The parties did not extend the delivery date beyond October 1987 to accommodate these delays, however. Instead, Barth and BMC each demonstrated a willingness to continue performance under the Contract.

One such delay, for example, occurred in June 1987, when Belcan decided that the equipment design posed a risk of explosion because of the proximity of certain chemicals to electrical components. Although BMC perceived no such risk, it told Barth and Belcan to “go ahead” and redesign the equipment. Barth revised its estimated delivery schedule to account for the resulting delay, listing December 1987 as the new delivery deadline. It sent this schedule to BMC with a cover letter that stated: “Please look over the attached & let me know what you think.” BMC’s response, if any, is not contained in the record.

This design problem was only one of many technical difficulties that developed; other problems arose with the filling nozzles and mold assembly springs, among other components. Consequently, by October 1987, the amended Contract’s delivery deadline, Barth estimated that it could not deliver the equipment until April 1988. BMC executives were still anxious, however, to continue the automation project. Thus, during the spring of 1988, although they protested Barth’s failure to deliver the equipment on time, these executives encouraged Barth to continue working on the project.

In June 1988, Barth completed the four automated de-clip/de-gasket machines and delivered them to BMC. Without the entire automated system, however, BMC could not fully test these machines; the whole production line had to be in place.

By August 1988, BMC’s mounting apprehension about Barth’s ability to perform led it to seek assurance that Barth would be able to complete performance under the Contract. In an effort to obtain such assurance, BMC executives met with Robert Tomsich, a Barth officer (and director) who also served as Nesco’s president.3 According to these executives, Tomsich ensured them that Barth would perform the Contract, that Nesco’s resources were committed to the project, and that, in the future, BMC should deal directly with Nesco.

Free access — add to your briefcase to read the full text and ask questions with AI

BMC Industries v. Barth Industries, 160 F.3d 1322 (11th Cir. 1998).

160 F.3d 1322 (BMC Industries v. Barth Industries) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rogelio C. Gomez v. Robert A. McDonald
28 Vet. App. 39 (Veterans Claims, 2015)